IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
CIV 2014-419-0045
CIV2014-419-000365 [2017] NZHC 783
BETWEEN CONCRETE STRUCTURES (NZ)
LIMITED Plaintiff
AND
INFRAMAX CONSTRUCTION LIMITED
Defendant
Hearing: On the papers Judgment:
26 April 2017
COSTS JUDGMENT OF DUFFY J
This judgment was delivered by me on 26 April 2017 at 3.00 pm pursuant to
Rule 11.5 of the High Court Rules.
Registrar/ Deputy Registrar
Solicitors / Counsel: McCaw Lewis, Hamilton Holland Beckett, Tauranga
CONCRETE STRUCTURES (NZ) LIMITED v INFRAMAX CONSTRUCTION LIMITED [2017] NZHC 783 [26 April 2017]
[1] There are two proceedings, to which I will refer as the Okura proceeding (CIV 2014-419-045) and the Rugby Road proceeding (CIV 2014-419-365). The trial of the Okura proceeding was scheduled to commence on 22 August 2016 with the Rugby Road proceeding to commence immediately afterwards. However, neither trial proceeded. Reasons for this are set out in the minute of 22 August 2016.1
[2] Adjournment of trial fixtures close to or on the day of trial necessarily give rise to costs issues, often with each opposing side blaming the other for why the trial did not proceed. This is what has happened here. The parties have been unable to agree costs.
[3] In its costs memorandum the plaintiff continues to maintain the stance that its late attempt to argue the existence of an implied contractual term was simply a clarification of its existing pleading and did not materially change the nature of its claim against the defendant. This is wrong. The original claim said nothing about an implied contractual term. It was clear from the defendant’s statement of defence that its defence proceeded on the basis it did not have to meet an allegation of an implied contractual term.
[4] I do not accept the plaintiff’s argument that reading an implied term into the contract is simply part and parcel of contractual interpretation. That is not so. If a plaintiff wants to assert the existence of terms of a contract that are not expressed either orally, in writing or by conduct it must allege in its statement of claim that such terms are implied and the facts and circumstances from which the implication
arises.2
[5] The plaintiff’s late change of course through its wish to include the existence
of an implied term in the contract upon which it was suing was the main reason for the trial not proceeding on 22 August 2016.
1 The minute of 22 August 2016 which fully explains why the trial was adjourned should be read together with this judgment on costs.
2 IH Jacob Bullen and Leake and Jacob’s Precedents of Pleadings (12th ed, Sweet and Maxwell, London, 1975) at 345.
[6] The defendant’s failure to have its contribution to the agreed bundle properly sorted out before the trial date was a factor in the trial not proceeding. However, had it been the sole factor the trial could have proceeded, as this was something that could have been accommodated. Accordingly, I am satisfied that the prime responsibility…
Keep reading for free
Create a free CaseChat account to read Concrete Structures (NZ) Limited v Inframax Construction Lim... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZHC 783
- Decision Date
CaseChat Overview and Summary
The court found that the plaintiff's late attempt to argue an implied contractual term, which was not mentioned in its original pleadings, was the primary reason for the postponement. The court rejected the plaintiff's argument that this was merely a clarification of its existing claim. The court also acknowledged the defendant's failure to have its contribution properly sorted out, though it noted that this alone would not have prevented the trial from proceeding. The court concluded that the plaintiff bore the main responsibility for the trial not proceeding as scheduled. Additionally, the court accepted that there had been wasted trial preparation and granted the defendant costs for three days of preparation at category 2B, as well as costs for dealing with the consequences of the plaintiff's late amendment.
The court awarded the defendant category 2B costs amounting to $14,383.50, rejecting the defendant's request for a rounded sum of $15,000. The court decided that the merits of the plaintiff's amended claim could not be assessed at that stage and left the possibility of additional costs for the plaintiff to be determined once the trial had occurred. The court emphasised that the approach to awarding costs was based on the specific circumstances of the case.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.