Concrete Structures (NZ) Limited v Dezign Works HB Limited HC NAP CIV 2009-441-115

Case

[2009] NZHC 2335

22 October 2009

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND

NAPIER REGISTRY

CIV-2009-441-115

BETWEEN  CONCRETE STRUCTURES (NZ)

LIMITED Plaintiff

ANDDEZIGN WORKS HB LIMITED Defendant

Hearing:         16 October 2009

Appearances:  K. Badcock - Counsel for Plaintiff

A.J.L. Wedekind - Counsel for Defendant

Judgment:      22 October 2009 at 3.30 pm

JUDGMENT OF ASSOCIATE JUDGE D.I. GENDALL

This judgment was delivered by Associate Judge Gendall on 22 October 2009 at

3.30 pm pursuant to r 11.5 of the High Court Rules.

Solicitors:            Lance Lawson, Solicitors, PO Box 2279, Rotorua 3040

Morgan Coakle, Solicitors, PO Box 114, Auckland

CONCRETE STRUCTURES (NZ) LIMITED V DEZIGN WORKS HB LIMITED HC NAP CIV-2009-441-115

22 October 2009

Introduction

[1]     In  this  application  the  plaintiff,  Concrete  Structures  (NZ)  Limited  (“CSL”) seeks   summary   judgment   against   the   defendant,   Dezign   Works   HB   Limited (“DWL”) for some $207,214.71 interest and costs.

[2]     The application is opposed by DWL.

Background Facts

[3]     On 22 November 2007 CSL entered into a contract with Carter Holt Harvey Limited (“CHH”), to design and install six new log conditioning chambers (“the chambers”) at CHH’s Kinleith Mill.  Around 27 November 2007 CSL entered into a sub-contract with DWL as a provider of engineering design services  pursuant  to which DWL would carry out the structural design and provide construction drawings

for the chambers.   From December 2007 to April 2008 DWL carried out the design work and issued construction drawings on about 7 April 2008.

[4]     Between 7 and 22 April 2008 CSL constructed three of the chambers, it says in accordance with DWL’s design. Defects in the chambers later became apparent, in particular, the  roof  panels  had  deflected  downwards. This had occurred by July

2008.  CSL says that it advised DWL about the defects and advised DWL to inform their insurer. CSL claims that the defects are a result of design faults.

[5]     On  or  about  17  July  2008  DWL  issued  to  CSL  sketches  of  remedial  work required to correct the problems. Later in July 2008 CSL constructed the next three chambers, incorporating the remedial work, and in September 2008 CSL carried out the remedial work that needed to be done to the first three chambers.

[6]     CSL alleges that around the end of July 2008 it  discussed  these  remedial matters with DWL, which advised CSL first that its insurer had instructed DWL to have the repairs carried out, secondly that the insurer had accepted the claim to carry out the remedial work, and thirdly that CSL should invoice DWL’s insurer directly

for the remedial work whereupon CSL would be paid directly by the insurer. CSL alleges that DWL again advised in September 2008 that CSL should send its claim to DWL’s insurer and that all CSL’s costs would  be  covered  by  the  insurer.  In

response, DWL denies that it ever gave assurance that its insurer had accepted the claim.

[7]     In its present claim, CSL pleads three causes of  actions:   breach of contract, breach of the Fair Trading Act 1986, and equitable estoppel. Before me,  however, counsel for CSL sought only to pursue the estoppel claim, apparently accepting that the  other  two  causes  of  action  were  not  appropriate  for  determination  in summary judgment.

Summary Judgment Principles

[8]     Rule 12.2(1) of the High Court   Rules   deals   with   summary   judgment applications and provides that the court may give judgment against a defendant if the plaintiff satisfies the court that the defendant has no defence to a cause of action.

[9]     The applicable principles  for  summary  judgment  applications  are well traversed and summarised in Krukziener v Hanover Finance Ltd [2008] NZCA 187:

“[26]  The principles are well settled. The question on  a  summary  judgment  application  is whether the defendant has no defence to the claim; that is, that there is no real question to be tried: Pemberton v Chappell [1987] 1 NZLR 1; (1986) 1 PRNZ 183 (CA), at p 3; p 185. The Court must be left without any real doubt or uncertainty. The onus is on the plaintiff, but where

its evidence is sufficient to show there is no defence, the defendant will have to respond if the application is to be defeated: MacLean v Stewart (1997) 11 PRNZ 66 (CA). The Court will not normally resolve  material conflicts of evidence or  assess  the credibility of deponents.  But it need not accept uncritically evidence that is inherently lacking in credibility, as for example where the evidence is inconsistent with undisputed contemporary   documents or other statements by the same deponent, or is inherently improbable: Eng Mee Yong v Letchumanan

[1980] AC 331; [1979] 3 WLR 373 (PC), at p 341; p 381. In the end the Court's assessment of the evidence is a matter of judgment. The Court may take a robust and realistic approach where the facts warrant it: Bilbie Dymock Corp Ltd v Patel (1987) 1 PRNZ 84 (CA).”

Estoppel

[10]   In order to make out a cause of action in estoppel, a plaintiff must show that a belief or  expectation was created by a representation made by the defendant;   and that the plaintiff relied on that belief or expectation to   their   detriment,   in circumstances where it would be unconscionable for the defendant to depart from the belief or expectation which s/he had created: Gold Star Insurance Co Ltd v Gaunt

[1998] 3 NZLR 80, 86 (CA); Gillies v Keogh [1989] 2 NZLR 327, 346 (CA).

[11]   Counsel  for  CSL  argues  that,  in  instructing  CSL  to  carry  out  the  remedial work, DWL gave the following assurances to CSL:

(a)     That DWL had contacted their insurer and advised of CSL’s claim; (b)  That the insurer had accepted CSL’s claim;

(c)     That CSL should carry out the remedial work in accordance with DWL’s remedial design;

(d)     That  the  insurer  accepted  it  would  pay  CSL  the  costs  of  the  remedial work.

[12]   Counsel further argues that CSL relied on the above representations in carrying out the remedial work, to CSL’s detriment. CSL states that it incurred $133,564.33

to carry out remedial  works, a further  $34,275.38  for  the  cost  of  CHH  remedial works, and that it lost its right to an early completion bonus of $39,375.00 because

of the need to carry out  the remedial works, hence the present summary judgment claim for an amount totalling $207,214.71.

[13]   DWL does not deny representing that the proposed remedial works would fix the sagging roofs of the chambers, nor does it deny that it advised CSL that it had notified its insurer. DWL, however, strongly repudiates the other representations alleged.  In  particular,  DWL  denies  that  it  ever  advised  CSL  that  its  insurers  had accepted liability for the cost of carrying out the remedial works.

[14]   While this would suggest that facts essential to CSL’s cause of action are in dispute, CSL submits that on the basis of the evidence it has put before the Court, the Court can be satisfied that the disputes raised by DWL are spurious and should not prevent an award of summary judgment here.

[15]   On these aspects,  the  first  13  February  2009  affidavit  of  Mr  Michael  John Romanes  (“Mr  Romanes”)  director  of  CSL,  refers  to  discussions  between  himself and Mr Russell Grant Nettlingham (“Mr Nettlingham”) a director of DWL, in which Mr  Romanes  states  (at  para  21)  that  Mr  Nettlingham  advised  him  that  “our instructions  from  the  insurer  were  to  implement  the  repairs  and  put  a  claim  into them”.  Mr  Romanes  has  exhibited  at  “MR11”  a  handwritten  file  note  made  by himself of this meeting.  In response, Mr Nettlingham in his 17 April 2009 affidavit

at  paras  26  to  29  denies  making this  statement,  and  says  he  notified  Mr  Romanes only that a claim had been notified and that the matter was in the insurer’s hands.

[16]   Mr Romanes further claims that at the meeting on 30 July 2008, Mr Nettlingham advised that his insurers accepted the claim and would meet the costs of the remedial works. This is denied by both Mr Nettlingham and Mr Duncan Robert Bruce (“Mr Bruce”), an engineer employed by DWL who was present at the meeting. Mr  Romanes exhibits another handwritten file note of this  meeting,  and also exhibits a facsmile which he says was sent  to  DWL  on  21  August  2008, requesting confirmation that “your insurers have accepted your claim and will meet

all costs of the remedial work”. Mr Nettlingham and Mr Bruce deny having seen this facsmile, and in any event, DWL did not reply. Counsel for DWL submits that Mr Romanes’ file notes are self-serving and are firmly contradicted by DWL’s witnesses.

[17]   In my view, there is clearly a substantial factual dispute here between the parties. As I see it, this can only be determined by a thorough testing of the competing evidence at trial. The presentation by Mr Romanes of the facsmile and the file  notes  is  not  enough  to  make this a case where “the credibility of one party is shown to be so suspect that his evidence can be rejected without need to assess him

as a witness or to listen to any further explanation he may wish to make”, as asserted

by counsel for CSL.

[18]   I am also concerned at what I see as real credibility issues which arise here. As

I have noted both Mr Nettlingham and Mr Bruce confirm in their affidavits that DWL’s insurers were awaiting a formal claim regarding this matter but had not agreed to meet the claim and the remedial costs. At this early stage of the proceeding it is simply not appropriate to dismiss this evidence of both Mr Nettlingham and Mr Bruce on credibility grounds, given particularly that at the appropriate time they would no doubt have been receiving advice from their insurer and lawyers and would be highly unlikely to  advise that the insurer had  agreed to meet CFL’s claim if the insurer had not agreed to that course.

[19]   Even if there were no conflict of evidence as to whether the alleged representations  in  question  were  actually made,  in  my view,  there  is  a  reasonable

argument here that CSL has not shown that it relied on those representations to its detriment. Counsel for DWL argues that CSL was presumably bound by its contract with CHH to deliver appropriate log chambers. Once the problem with the chambers became apparent, CSL had no choice but to remedy this or no doubt it would have been in breach of its contract with CHH. As such, counsel argues that in carrying out the remedial work, CSL could not say that it was relying on the representations, but rather that it was acting as required by its contract with CHH.

[20]   In response, counsel for CSL endeavoured to argue that, while it was obliged

to remedy the defects in the chambers pursuant to its contract with CHH, it was not obliged to do so in the particular manner that it did, which incurred over $200,000.00

in repair costs. Counsel states that CSL went with this remedial option in reliance on DWL’s representations that their insurer would meet these costs. It follows therefore that this reliance was detrimental, because without it, DWL maintains it would have resolved the defects in another, presumably less costly, way. This is another matter

of disputed fact.  It needs to be acknowledged that there is no conclusive evidence before  the  Court  that  CSL  only  took  the  option  that  it  did  because  of  the  alleged representations, or that other, less costly options were available to CSL in the event that there was no insurance coverage.

[21]   I  take  the  view  here  that  there  is  a  clear  and  genuine  conflict  of  evidence between  the  affidavits  provided  on  behalf  of  each  party  to  this  proceeding  and  it follows that there are real questions to be tried in this case.   As I see it the plaintiff has been unable to satisfy the Court that the defendant has no fairly arguable defence here.      Although   this   effectively   disposes   of   the   present   summary   judgment application I will turn now to briefly consider the other causes of action raised in the plaintiff’s statement of claim.

Other Causes of Action

[22]   As I have noted, the causes of actions in breach of contract and for breach of the Fair Trading Act 1986 were not pursued before me. For completeness, however, I will mention them briefly.

[23]   In its claim, CSL argues that DWL was in breach of s 13(b) of the Fair Trading

Act 1986. This states that no  person  in  trade  in  connection  with  the  supply  of

services  shall  make  a  false  or  misleading  representation  that  the  services  are  of  a particular standard, kind, or quality. In order to obtain an order under s 43 of the Act, CSL must establish reliance on the representation and show that the reliance caused the loss.  In my view, it has failed to do this here in the same way that it has failed to show these elements in the estoppel ground.

[24]   It  appears  that  CSL’s  claim  here  is  really  one  involving  allegations  of negligence or breach of  contract against  a professional firm. Even if it is assumed that DWL’s design contained errors which were  the cause of the chamber defects, that  alone  would  not  necessarily  show  that  DWL  has  been  negligent.  In  order  to determine  a  claim  such  as  this,  the  Court  ultimately may well  decide  that  it  must compare  DWL’s  conduct  in  creating  the  design  to  what  can  be  expected  of  a reasonably well  informed  and  competent   professional  engineer:  Saif  Ali  v  Sydney Mitchell & Co [1978] 3 All ER 1033, 1043. That is an enquiry which can only be addressed at trial, with expert evidence and the opportunity for cross-examination.

Result

[25]   For  the  reasons  outlined  above,  CSL’s  application  for  summary judgment  is dismissed.

[26]   Costs are reserved.

‘Associate Judge D.I. Gendall’

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

1