Clarke Road Developments Limited v Rohits Civil & Infrastructure Limited

Link copied
Case Copied 19 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2017-404-2558 [2017] NZHC 2844

BETWEEN

CLARK ROAD DEVELOPMENTS

LIMITED Plaintiff

AND

ROHITS CIVIL & INFRASTRUCTURE LIMITED

First Defendant

CHINA CONSTRUCTION BANK (NEW ZEALAND) LIMITED

Second Defendant

CIV-2017-404-2519

BETWEEN  ROHITS CIVIL & INFRASTRUCTURE LIMITED

Plaintiff

ANDCHINA CONSTRUCTION BANK (NEW ZEALAND) LIMITED

Defendant

Hearing: 13 November 2017

Appearances:

K F Gould for Clark Road Developments Limited
J Miles QC and A Stuart for Rohits Civil & Infrastructure
Limited
A E Murray for China Construction Bank (New Zealand
Limited

Judgment:

20 November 2017

JUDGMENT OF MUIR J

This judgment was delivered by me on Monday 20 November 2017 at 3.00 pm

Pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar  Date:…………………………

CLARK ROAD DEVELOPMENTS LTD v ROHITS CIVIL & INFRASTRUCTURE LTD [2017] NZHC 2844 [20 November 2017]

Introduction

[1]      In two related proceedings Rohits  Civil & Infrastructure Limited (RCIL) seeks summary judgment against China Construction Bank (New Zealand) Limited (CCB) under a document styled “Principal’s Bond” (“the Bond”), and Clark Road Developments Limited (CRDL) seeks an injunction against RCIL preventing it from claiming under the Bond and against CCB from making payment accordingly.

[2]      I intend  to  approach  the  respective  claims  by  asking  whether  RCIL can satisfy the Court that CCB has no defence to the claims against it.  To do so it must establish the absence of any real questions to be tried.1   Assuming it can, then there can be no basis for the issue of the injunction CRDL seeks against CCB.

[3]      Insofar as CRDL seeks to restrain RCIL from making a call under the Bond it is accepted that the horse has already bolted.  A call was made on 9 October 2017 prior to the application for the interim injunction which was filed on 25 October

2017.

Background

[4]      RCIL is a contracting company with approximately 50 full-time employees. On 27 April 2016 it entered into a contract with CRDL to undertake the civil works associated with the subdivision of a property at 165 Clark Road, Hobsonville.  The contract adopted NZS form 3910:2013 Conditions of Contract for Building and Civil Engineering Construction.

[5]      By that stage work had in fact already started on the site, with the first progress payment claim being for work undertaken in the period up to 29 February

2016.

[6]      In its terms, the contract was a measure and value contract which meant that the contract price was to be calculated according to the measured quantity as determined by the engineer of each item of work carried out at the rate specified in a

schedule of prices attached to it.

1      Pemberton v Chappell [1987] 1 NZLR 1 (CA) at 3.

[7]      From  an  early  stage  RCIL  complained  that  CRDL was  late  in  meeting payment claims.  It says that of the 19 claims it in fact made, CRDL failed to make payment when due on 13 occasions.  On 7 April 2017 it says that it received payment by cheque, in respect of claim No 13,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Clarke Road Developments Limited v Rohits Civil & Infrastruc... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NZHC 2844
Decision Date

CaseChat Overview and Summary

The case of Clarke Road Developments Limited v Rohits Civil & Infrastructure Limited involved a dispute between a contractor, Rohits Civil & Infrastructure Limited (RCIL), and a principal, Clark Road Developments Limited (CRDL), over the interpretation and enforceability of a Principal’s Bond issued by China Construction Bank (New Zealand) Limited (CCB). RCIL sought summary judgment against CCB to enforce the bond, while CRDL sought an injunction against RCIL and CCB to prevent the enforcement of the bond. The central issue before the court was whether the bond was an on-demand bond or a conditional bond, which would affect the obligations of CCB under the bond.

The court held that the bond was an on-demand bond, meaning CCB was obligated to pay any sum demanded by RCIL up to the bond’s nominal value, without requiring proof of CRDL’s default or any other conditions. The court found that the bond’s terms clearly established an unconditional obligation on CCB to pay upon demand, consistent with the nature of demand guarantees in construction contracts. The court further determined that the bond was not null and void because the contract price had not been fully paid to RCIL at the time of the demand. The court rejected CRDL’s argument that the bond was discharged due to an overpayment identified in the engineer’s certificate, holding that the bond’s obligations were independent of the underlying contract between RCIL and CRDL.

As a result, the court entered summary judgment in favour of RCIL against CCB for the full amount of the bond. The court declined CRDL’s application for injunctive relief, finding that CRDL had not established a seriously arguable case that the bond was null and void. The court also noted that CCB’s decision to abide by the court’s determination might mitigate against awarding indemnity costs to RCIL.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.