CBC Construction (Auckland) Limited v Auckland Concrete Limited

Link copied
Case Copied 23 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2019-404-92

[2019] NZHC 1104

BETWEEN CBC CONSTRUCTION (AUCKLAND) LIMITED
Applicant

AND

AUCKLAND CONCRETE LIMITED

Respondent

Hearing: 14 May 2019

Appearances:

M L Broad and L Rozendaal for the Applicant K A Badcock for the Respondent

Judgment:

14 May 2019


ORAL JUDGMENT OF ASSOCIATE JUDGE R M BELL


Solicitors:

Kensington Swan, Auckland Badcock Law, Rotorua

CBC CONSTRUCTION (AUCKLAND) LIMITED v AUCKLAND CONCRETE LIMITED [2019] NZHC 1104 [14 May 2019]

[1]    CBC Construction (Auckland) Limited applies to set aside a statutory demand of Auckland Concrete Limited dated 15 January 2019 requiring it to pay $352,300.36 including GST, plus actual and reasonable costs of recovery of $2,817.50. The statutory demand says that the $352,300.36 is “a debt due pursuant to a progress payment claim dated 25 October 2018 (PC19), issued under s 20 of the Construction Contracts Act 2002 of which only part payment has been made, in relation to CBC Construction (Auckland) Limited, Waterford Apartments – Block 2, Hobsonville contract”.

[2]    CBC, a construction contractor, had the head contract to build apartments at Hobsonville. Auckland Concrete Limited, a concreting contractor, had the concreting subcontract between April 2017 and October 2018 for the Hobsonville job. Auckland Concrete says that CBC’s indebtedness arose under the sudden death provisions of the Construction Contracts Act 2002. On 25 October 2018 it gave CBC ‘Payment Claim 19’. It was for $355,188.82 (excluding GST); with GST the total amount payable was

$408,467.14. The payment claim specified the due date for payment as 30 November 2018. An invoice accompanying the payment claim also stated that the due date for payment was 30 November 2018. On 30 November 2018 CBC sent Auckland Concrete a payment schedule under s 21 of the Construction Contracts Act, rejecting many  of  the  claims   by  Auckland  Concrete  and  stating  a  schedule   amount   of

$56,166.78 (including GST). It paid Auckland Concrete that sum on the same day. Auckland Concrete Ltd says however that the sudden death provisions under ss 22 and 23 of the Construction Contracts Act have taken effect, because CBC gave its payment schedule too late. In issuing the statutory demand it has brought into account the payment of $56,166.78. The statutory demand is for the balance of the amount stated in the payment claim of 25 October 2018. CBC, on the other hand, says that it did give its payment schedule in time. The difference between the parties turns on which party’s version of the terms of contract applies and on their conduct during the contract. CBC says that the governing terms are set out in its subcontract agreement which it sent to Auckland Concrete on 11 April 2017. On the other hand, Auckland Concrete says that the terms are set out in its response, which it sent on 20 April 2017.

Preliminary matters

[3]    Auckland Concrete served its statutory demand on 16 January 2019. CBC filed and served its application on 30 January…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CBC Construction (Auckland) Limited v Auckland Concrete Limi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NZHC 1104
Decision Date

CaseChat Overview and Summary

CBC Construction (Auckland) Limited applied to set aside a statutory demand of Auckland Concrete Limited. The demand was for $352,300.36 plus GST, plus actual and reasonable costs of recovery. The demand was issued under s 289 of the Companies Act 1993. Auckland Concrete claimed that CBC owed the money under the sudden death provisions of the Construction Contracts Act 2002 because CBC had given its payment schedule too late. CBC, on the other hand, said that it did give its payment schedule in time. The difference between the parties turned on which party’s version of the terms of the contract applied and on their conduct during the contract. The court declined to resolve the disputed question of fact and found that there was a genuine and substantial dispute as to the existence of the debt. The court set aside the statutory demand. Auckland Concrete was to pay CBC costs on the application. The court took the demand for costs in the statutory demand into account in fixing costs. It awarded extra costs as a deterrent for the practice of making unjustified claims for costs on statutory demands.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established