IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
I TE KŌTI MATUA O AOTEAROA TE WHANGANUI-A-TARA ROHE
CIV-2024-485-000384
[2024] NZHC 3377
UNDER the Construction Contracts Act 2002 and the High Court Rules 2016 IN THE MATTER OF
an application to rescind the interlocutory order of Gordon J dated 4 July 2024
BETWEEN
CANNON POINT DEVELOPMENT LIMITED
Applicant
AND
WELLINGTON DEVELOPMENTS LIMITED
Respondent
Hearing: 31 October 2024 Counsel:
J T Wollerman and F N Hallett for Applicant
F B Q Collins and F A Hollingworth for Respondent
Judgment:
13 November 2024
JUDGMENT OF GRAU J
[Application to rescind order of the Court]
The application
[1] On 4 July 2024 Gordon J granted a without notice application by Wellington Developments Ltd (WDL) for retentions totalling $94,131.88 (including GST) to be placed by Cannon Point Development Ltd (CPDL) into the trust account of Ford Sumner Lawyer’s Westpac Bank trust account.1 The retentions were held by CPDL
1 Wellington Developments Ltd v Cannon Point Development Ltd [2024] NZHC 1798 [Decision of Gordon J].
WELLINGTON DEVELOPMENTS LIMITED v CANNON POINT DEVELOPMENT LIMITED [2024] NZHC 3377 [13 November 2024]
pursuant to a construction contract between the parties for civil works that is now the subject of a high level of dispute.
[2] CPDL has applied to rescind Gordon J’s order because it says WDL’s application was inaccurate and omitted relevant facts, breaching the duty of utmost good faith CPDL owed to the Court to make full disclosure. In particular, CPDL says WDL’s allegation that an adjudicator determined CPDL had underpaid WDL by
$510,854.95 was incorrect, as was an allegation CPDL was unable to pay monies it owed to WDL. Nor did WDL make any reference to CPDL’s significant claims against WDL in relation to defects arising from WDL’s work, as it was obliged to do. These inaccuracies and/or omissions are said to have gone to the heart of the application and the basis for granting the order.
[3] CPDL agrees the retentions must be safeguarded, but it says that is best achieved by repayment of the retentions to CPDL who will hold the funds (as it had done before the order was granted) in accordance with its statutory obligations. Otherwise, there is a risk of WDL obtaining the retentions after further adjudication and dissipating them. CPDL says it is WDL, not CPDL, that has solvency issues.
[4] WDL’s position is that it provided the Court with the necessary information to determine its application and CPDL’s application to rescind the order is moot. The money can be in no safer place, and it cannot be released unless agreement is reached, or by further order of a court, an adjudicator, or an arbitrator. The retention monies are being safeguarded until determination of the current second adjudication which is likely to happen before the Christmas holiday period. The retentions are held on trust for WDL; they are WDL’s money. If there are significant defects, as CPL alleges, then CPDL has the ability to adduce evidence and seek such…
Continue reading Cannon Point Development Ltd v Wellington Developments Ltd
Sign in free to access the full text
- AGLC
- Cannon Point Development Ltd v Wellington Developments Ltd [2024] NZHC 3377
- Case
- [2024] NZHC 3377
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.