IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
CIV-2014-409-000764 [2015] NZHC 1161
BETWEEN CAN BUILD LIMITED
Plaintiff
AND
GARY FRANCIS KIRKPATRICK AND JOHN LESLIE PURVIS AS TRUSTEES OF THE LAURA KIRKPATRICK FAMILY TRUST
Defendants
Hearing: 20 May 2015 Appearances:
L M Taylor for Plaintiff
P J Shamy for DefendantsJudgment:
27 May 2015
JUDGMENT OF ASSOCIATE JUDGE MATTHEWS
Introduction
[1] On 7 August 2013 the trustees of the Laura Kirkpatrick Family Trust (LKFT) signed a written building contract with South Steel Construction Limited (South Steel) to build a building in Hillsborough, Christchurch. The contract price was
$1,978,450 plus GST. In March 2014, when construction was well advanced, South Steel was placed into receivership. On 8 April 2014 the receiver advised LKFT that South Steel could not complete the building.
[2] Mr R M Forde, a director of Can Build Limited (CBL) says in his affidavit that the receivers of South Steel assigned the contract to CBL on or about 17 March
2014. CBL then started working on the site of LKFT’s new building.
[3] CBL claims from LKFT two sums which are specified in two documents described as payment claim 9 and payment claim 10, respectively. The former is for
$99,933.68. The latter is for $160,896.67. Both sums are exclusive of GST.
CAN BUILD LTD v KIRKPATRICK and PURVIS as trustees of the LAURA KIRKPATRICK FAMILY TRUST [2015] NZHC 1161 [27 May 2015]
[4] The case presented to the Court by CBL essentially follows, step by step, the well-worn path set out in the Construction Contracts Act 2002. CBL says that it issued two valid payment claims under s 20, that LKFT did not respond to either by providing a payment schedule under s 21 and, as a result, LKFT is liable for paying the claimed amounts under s 22. If that is so, CBL is entitled to recover the amounts of the payment claims, together with its actual and reasonable costs, under s 23.
[5] LKFT, however, does not accept that its contract with South Steel was assigned to CBL, or to any other company. Further, it says that the documents described as payment claims 9 and 10 are not payment claims that meet the requirements of s 20 and that, should it be found that they do, it issued satisfactory payment schedules in response.
[6] There are, therefore, three issues for determination in this case:
(a) Was the contract between South Steel and LKFT assigned to CBL?
(b)Did either or both of the purported payment claims 9 and 10 comply with s 20?
(c) If so, did LKFT issue a payment schedule in respect of either or both, under s 21?
Law on summary judgment
[7] CBL applies for summary judgment on its claim. Rule 12.2 of the High
Court Rules provides:
12.2Judgment when there is no defence or when no cause of action can succeed
(1) The court may give judgment against a defendant if the plaintiff satisfies the court that the defendant has no defence…
Keep reading for free
Create a free CaseChat account to read Can Build Limited v Kirkpatrick and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] NZHC 1161
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.