BSC Construction Ltd v Withers

Link copied
Case Copied 33 min read

IN THE HIGH COURT OF NEW ZEALAND NEW PLYMOUTH REGISTRY

CIV 2015-443-003 [2015] NZHC 1988

BETWEEN

BSC CONSTRUCTION LTD

Plaintiff

AND

CLARENCE WILLIAM WITHERS Defendant

Hearing: 22 April and 6 July 2015

Counsel:

R Wilson for BSC Construction Ltd
S W Hughes QC and K R Pascoe for Mr Withers

Judgment:

21 August 2015

JUDGMENT OF HEATH J

This judgment was delivered by me on 21 August 2015 at 11.00am pursuant to

Rule 11.5 of the High Court Rules

Registrar/Deputy Registrar

Solicitors;

Rod Gordon, New Plymouth Nicholsons, New Plymouth Counsel:

R Wilson, New Plymouth

S W Hughes QC, New Plymouth

BSC CONSTRUCTION LTD v WITHERS [2015] NZHC 1988 [21 August 2015]

CONTENTS

The issue  [1] Background  [4] The legal framework  [12] The Arbitral process

(a)      The Expedited Arbitration Rules  [22]

(b)      The pleadings and the evidence  [28] (c)      The awards  [38] The cross-applications  [43] Analysis  [48] Result  [58]

The issue

[1]      Arbitration is a consensual method of resolving disputes.  The parties choose their own “judge” and invite him or her, on terms that they agree, to determine their differences in a binding fashion.1    The Arbitration Act 1996 (the Act) governs the arbitral process in New Zealand, with differing rules applying to domestic and international arbitrations.  Procedural rules in respect of domestic arbitrations are set out in the First Schedule to the Act.

[2]      The end product of an arbitration is a decision on the merits, known as an award.   There are limited circumstances in which a Court may intervene when considering a challenge to an award.2   They are an appeal (or application for leave to appeal),3  an application to set aside an award4  and opposition to an application to

enforce the award.5    One of the grounds on which both an award may be set aside

and enforcement opposed is where the award is in conflict with the public policy of New Zealand, or enforcement would be contrary to public policy.6   The Act makes it clear that the public policy ground will be established if “a breach of the rules of

natural justice [has] occurred … during the arbitral proceedings”.7

1      See the Privy Council’s decision in Pupuke Service Station Ltd v Caltex Oil (NZ) Ltd (reported as an appendix to Gold and Resource Developments (NZ) Ltd v Doug Hood Ltd [2000] 3 NZLR (CA)) at 337–338, para 1.

2      Arbitration Act 1996, First Schedule, art 5.   See also Carr v Gallaway Cook Allan [2014] 1

NZLR 792 (SC) at para [12] per McGrath J, for the majority.

3      Ibid, Second Schedule, cl 5.  Clause 5 of the Second Schedule applies in this case, in the absence of any agreement to the contrary: see s 6(2)(b) of the Act.

4      Ibid, First Schedule, art 34(2).

5      Ibid, First Schedule, art 36(1).

6      Ibid, First Schedule, art 34(2)(b)(ii) and 36(1)(b)(ii).

7      Ibid, First Schedule, art 34(6)(b) and 36(3)(b).

[3]      In this proceeding, the unsuccessful party in a domestic arbitration contends that an award should either be set aside or not…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read BSC Construction Ltd v Withers and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] NZHC 1988
Decision Date

CaseChat Overview and Summary

BSC Construction Ltd commenced proceedings against Clarence William Withers to recover payment of outstanding costs for the construction of an accommodation lodge. The parties agreed to submit their dispute to arbitration. They adopted a standard form arbitration agreement known as the Expedited Arbitration Rules. The Arbitrator found that Mr Withers owed a total sum of $93,898.11 to BSC and was liable to contribute a further sum of $20,000 to the Arbitrator’s fees. BSC applied to enforce the award. Mr Withers opposed that application. Separately, he applied to set aside or appeal against the Awards. Those applications were also opposed. The primary issue was whether the Arbitrator had breached the rules of natural justice in deciding the dispute. The Court found that the parties had agreed to the Expedited Arbitration Rules which included a provision for the Arbitrator to make an award within 45 working days of the date on which acceptance of his appointment was communicated to the parties. The Expedited Arbitration Rules contained statements of both “Purpose” and “Overriding Objective” and confirmed that there would be no opportunity to test the evidence of each deponent by cross-examination at an oral hearing. The Court found that the Arbitrator gave both parties an opportunity to be fully heard and made factual findings on evidence submitted in accordance with the arbitration agreement. Accordingly, BSC’s application to enforce the award was granted and Mr Withers’ application to set the awards aside was dismissed. Within five working days of the date of delivery of this judgment, the solicitors for Mr Withers were to pay to the solicitors for BSC the moneys held in their trust account in satisfaction of the award. Only if any further moneys were payable could enforcement action be taken to recover. Leave to apply was reserved should any difficulties arise.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established