IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2025-404-000979
[2025] NZHC 3120
UNDER the Construction Contracts Act 2002 IN THE MATTER OF
an expired payment claim pursuant to s 23 of the Construction Contracts Act 2002
BETWEEN
BRIGHTWATER ENGINEERING LIMITED
Appellant
AND
PLATINUM ELECTRICAL LIMITED
Respondent
Hearing: 9 October 2025 Counsel:
D Viatos for Appellant
DJK Mitchell for Respondent
Judgment:
21 October 2025
JUDGMENT OF DOWNS J
This judgment was delivered by me on Tuesday, 21 October 2025 at 2 pm pursuant to r 11.5 of the High Court Rules 2016.
Registrar/Deputy Registrar
Solicitors/Counsel: Gibson Sheat, Wellington. DJK Mitchell, Auckland.
BRIGHTWATER ENGINEERING LTD v PLATINUM ELECTRICAL LTD [2025] NZHC 3120 [21 October 2025]
The appeal
[1] The District Court dismissed an application for summary judgment in relation to the Construction Contracts Act 2002.1 The respondent has since paid the entirety of the underlying invoice, so the only question is whether the appellant is entitled to its “actual and reasonable costs of recovery” under the Act.2 That question raises issues identical to those in the District Court, albeit, as observed, through the rubric of costs under the Act.
Background
[2] In April 2024, Platinum Electrical Ltd3 engaged Brightwater Engineering Ltd4 to install an electrical transformer in Whenuapai. The agreed price was $12,800, plus GST.
[3] Work began in June 2024. On 30 June 2024, Brightwater issued an invoice for the agreed price (invoice 1).
[4]On 23 July 2024, Platinum responded by email (the email):
Hi Brightwater,
Unfortunately, this project didn’t go well and we have a few issues with additional costs incurred by Brightwater that need to be resolved.
In agreement with Brightwater, the HV changeover was take place on the 4th of June and to be completed at COB on the 4th of June. The physical work was completed on the 4th of June however Bright waters electrical inspector failed to attend the site to inspect the completed works. We gave ample opportunity for Brightwater to engage the electrical inspector unfortunately Bright water failed to do so. On the 6th of June Platinum Electrical engaged its electrical inspector to carry out the inspection work.
Platinum has incurred additional significant costs in generator hire and inspection costs which will need to be deducted off the Bright water invoice.
Before we resolve the bright water invoice Platinum Electrical requires the testing and commissioning results.
1 Act.
2 The appellant also seeks interest on the (now repaid) invoice amount.
3 Platinum.
4 Brightwater.
[5] Brightwater simply ignored the email. On 28 August 2024, it again invoiced Platinum for the agreed amount (invoice 2).
[6]On 27 September 2024, Brightwater demanded payment.
[7] On 9 October 2024, Platinum sent a second email: (a) reiterating Brightwater had not completed the agreed works and Platinum had suffered loss; and (b) saying it would pay 50 percent of the underlying sum until all matters were resolved. On 14 November 2024, Platinum paid 50 percent.
[8] Brightwater then applied…
Keep reading for free
Create a free CaseChat account to read Brightwater Engineering Ltd v Platinum Electrical Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] NZHC 3120
- Decision Date
CaseChat Overview and Summary
The Court was required to determine the validity of the payment claims issued by Brightwater and the corresponding payment schedules provided by Platinum. Specifically, the court examined whether invoice 1 issued by Brightwater constituted a valid payment claim and whether the email from Platinum constituted a valid payment schedule. The court also considered whether invoice 2 could be regarded as a valid payment claim under the Act.
The court found that invoice 1 was not a valid payment claim due to its failure to meet the statutory requirements outlined in section 20 of the Act, which include identifying the work, the period over which the payment relates, a due date, and how the claimed amount was calculated. The court noted that these deficiencies were not merely technical quibbles, making it difficult to consider the email from Platinum as a valid payment schedule because it responded to a payment claim. Regarding invoice 2, while the court was inclined to accept that it could constitute a valid payment claim, it found it arguable that invoice 2 did not indicate how Brightwater calculated the claimed amount, contrary to the requirements of section 20(2)(e) of the Act. Consequently, the court held that there was a serious question to be tried in relation to the validity of invoice 2, leading to the dismissal of the appeal. As a result, Brightwater's entitlement to costs under the Act was also dismissed.
In conclusion, the appeal was dismissed, and Platinum was awarded 2B scale costs as the successful party.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.