Body Corporate 360683 v Auckland Council

Link copied
Case Copied 23 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2013-404-3415 [2017] NZHC 1785

BETWEEN

BODY CORPORATE 360683

First and Plaintiffs

WILLIAM FREDERICK MULHOLLAND AND OTHERS Second Plaintiffs

AND

AUCKLAND COUNCIL First Defendant

WOODHAMS MEIKLE ZHAN ARCHITECTS LIMITED AND WOODHAMS MEIKLE LIMITED Second Defendants

OTHERS
Third to Ninth Defendants and Third and

Fourth Parties

Hearing: 16 June 2017

Appearances:

G R Grant for the Plaintiffs
PJL Hunt and T W Clark for the Second Defendants

Judgment:

1 August 2017

JUDGMENT OF WOODHOUSE J

This judgment was delivered by me on 1 August 2017 at 4:00 p.m. pursuant to r 11.5 of the High Court Rules 2016.

Registrar/Deputy Registrar

……………………………………

Solicitors:

Ms G R Grant, Rainey Law, Solicitors, Auckland

Mr PJL Hunt and Mr T W Clark, McElroys, Solicitors, Auckland

BODY CORPORATE 360683 v AUCKLAND COUNCIL [2017] NZHC 1785 [1 August 2017]

[1]      This is an application by the second defendants (the architects) to strike out those parts of an amended statement of claim of the plaintiffs (the owners) which allege that the architects negligently carried out on-site observations and inspections (the observation claim) during the construction of an apartment building.

[2]      The central issues are:

(a)      Whether the observation claim is a new cause of action or whether allegations relating to observation are no more than further particulars in respect of a cause of action pleaded in the previous statement of claim.

(b)      If the observation claim is a new cause of action, is it time barred?

Factual and procedural background

[3]      The owners have claims against eight defendants relating to the construction of a 34 unit residential apartment building known as Orewa Grand.   The factual background is taken from the third amended statement of claim.  This is the version of the claim containing the pleadings the architects seek to strike out.  I will refer to this as the new pleading.  It is to be compared with the second amended statement of claim which I will call the prior pleading.

[4]      The building was constructed between approximately November 2004 and

February 2006.

[5]      The architects were engaged by the developer to provide three categories of architectural services:

(a)      Preparation of drawings to obtain necessary consents and to enable construction of the building.

(b)      Assistance to the developer in obtaining building consents. (c)          On-site observation during the course of construction.

[6]      The relevant dates during which the architects carried out relevant services were:

(a)       Design drawings and specifications were prepared in 2004 and 2005.

(b)      Working  drawings  were  prepared  between  approximately  October

2004 and July 2005.

(c)       On-site observations were undertaken between approximately January

2005 and January 2006.

(d)      Post-construction defects inspections were carried out from December

2005 to February 2006.

(e)       The last alleged on-site attendance was on 16 August 2006.

[7]      This proceeding was commenced against the architects, and other defendants, on 20 December 2013. The second amended statement of claim was filed and served around 6 November 2014.   The current pleading was filed and served around 27

October 2016.

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Body Corporate 360683 v Auckland Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NZHC 1785
Decision Date

CaseChat Overview and Summary

Body Corporate 360683 and others brought claims against the Auckland Council, Woodhams Meikle Zhan Architects Limited and others in relation to the construction of an apartment building. The second defendants, the architects, sought to strike out allegations in the amended statement of claim which alleged that the architects negligently carried out on-site observations and inspections during the construction of the building. The central issues were whether the observation claim was a new cause of action or further particulars of a prior cause of action and, if the former, whether the observation claim was time barred. The court found that the observation claim was a new cause of action which introduced an area of factual enquiry that was different from that of the prior pleading. The court also found that the observation claim was time barred. The court granted the application to strike out the observation claim.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established