IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY

CIV-2012-425-000341 [2013] NZHC 559

BETWEEN  BODY CORPORATE 351522

First Plaintiff

ANDDAVID VICTOR CURRAN AND KIM NANCY CURRAN

CIRCLE PROPERTY INVESTMENTS LIMITED

ANUP NATHU AND SADHANA NATHU NOVACORP LIMITED

LYNETTE JANICE DONALDSON JENNIFER CHRISTINE HAY AND STEPHEN ALEXANDER GREER BRUCE DONN MCNALLY

MATTRIX INVESTMENTS LIMITED HAMISH IAN MUNRO AND MILLY MY LOI SIN and

HAYBU LIMITED

Second Plaintiffs

ANDQUEENSTOWN LAKES DISTRICT COUNCIL

First Defendant

ANDANDREW JOHN STEVENS Second Defendant

ANDMARK LAWRENCE HILLARY Third Defendant

ANDB F WHITHAM LIMITED Fourth Defendant

ANDPHILLIP STANLEY MORRISON Fifth Defendant

Hearing:         25 February 2013

with additional evidence received 7 March 2013 and memorandum received 11 March 2013

(Heard at Christchurch)

Appearances: A J Thorn for Plaintiffs/Respondent

H M Rice/A C Harpur for First Defendant/Applicant (Counsel for other parties not involved)

BODY CORPORATE 351522 V QUEENSTOWN LAKES DISTRICT COUNCIL HC INV CIV-2012-425-

000341 [20 March 2013]

Judgment:      20 March 2013

JUDGMENT OF ASSOCIATE JUDGE OSBORNE

[as to application for orders for inspection and testing of property]

Introduction

[1]      In this proceeding, the plaintiffs sue the defendants for weathertightness and other issues affecting a Queenstown apartment block.

[2]      The plaintiffs sue five defendants. Apart from suing the Council, they sue the two developers/project manager/builders, one designer and one structural engineer.

[3]      The  plaintiffs  allege  that  the  apartment  block  has  been  constructed  with design and/or construction and/or mechanical engineering defects.

[4]      This is a judgment in relation to two interlocutory applications –

(a)       The Council seeks orders as to inspection and testing of the property; (b)      Secondly, the Council seeks an order that the plaintiffs provide further

and better particulars.

[5] I deal first with the inspection and testing application (at [7]–[56], with the orders at [57]) and then with the further and better discovery (at [58]–[148]), with the order at [149].

[6]      I also deal at the conclusion of this judgment with the allocation of a trial date for this proceeding.  The Registrar had been directed on 27 November 2012 to allocate a trial date.  A date had not been allocated by the time of this hearing as counsel for the Council had opposed the offered date in September 2013 by reason of unavailability of counsel.  I heard from counsel on the issue of trial allocation at the commencement of this hearing.   I indicated that I was provisionally minded to allocate the trial to September 2013, but reserved my ruling on allocation until I heard  and  was  able  to  take  into  account  the  submissions  I  was  about  to  hear

particularly in relation to testing and inspection.  Formal directions as to trial appear at the conclusion of the judgment at [150]-[152].

Inspection and testing of the property

The jurisdiction

[7]      Rule 9.34 provides:

Order for inspection, etc

(1)       The court may, for the purpose of enabling the proper determination of any matter in question in a proceeding, make orders, on terms, for—

(a)      the inspection of any property:

(b)      the taking of samples of any property: (c)  the observation of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Body Corporate 351522 v Queenstown Lakes District Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] NZHC 559
Decision Date

CaseChat Overview and Summary

This case concerned a proceeding brought by a body corporate and six apartment owners against the Queenstown Lakes District Council, two developers/project managers/builders, a designer and a structural engineer. The plaintiffs alleged that the apartment block had been constructed with design and/or construction and/or mechanical engineering defects. This judgment concerns two interlocutory applications – the first related to an application by the Council for orders as to inspection and testing of the property; the second related to the Council's application for an order that the plaintiffs provide further and better particulars. The court first considered the inspection and testing application, noting that the parties agreed that an order should be made but disagreed as to the terms on which the order should be made. The court considered the evidence of the experts for both parties and decided that the testing and monitoring should run from 25 March 2013 to 31 October 2013. The court considered the specific terms and conditions of the order, and made an order in accordance with the submissions of the parties. The court then considered the application for further and better particulars. The court considered the submissions of the parties and made an order that the plaintiffs provide further and better particulars in relation to the defects, breach, damage and quantum. The court also ordered that the plaintiffs provide particulars in relation to their claim for exemplary damages. Finally, the court considered the allocation of a trial date and ordered that the trial should commence on 25 November 2013.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established