Body Corporate 207650 v Speck

Case

[2017] NZHC 966

12 May 2017

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2015-404-3079 [2017] NZHC 966

UNDER Section 74 Unit Titles Act 2010

BETWEEN

BODY CORPORATE 207650
Applicant

AND

KATY SPECK RYAN SPECK First Respondents

JILLIAN HOWARD GARY STEVENSON Second Respondents

FRANCIS MCKEAN Third Respondent

RUDRAKAGENDRAN SIVAPALAN AND POLIMA RUDRAKAGENDRAN Fourth Respondents

WAYNE PATRICK VAN EYSSEN, NATASHA ANN VAN EYSSEN, JAMES PETER COSSLETT and ANTONIONETTE MARIA COSSLETT Fifth Respondents

BACHAR EL-KHATIB and NAWAR ALWESH

Sixth Respondents

KARUNA CHAWLA and SAMIR CHAWLA

Seventh Respondents

LLEWELLYN NAIDOO and VALERIE NAIDOO

Eighth Respondents

MOHAMMED KHAN and ASHRAF KHAN

Ninth Respondents

BODY CORPORATE 207650 v KATY SPECK RYAN SPECK [2017] NZHC 966 [12 May 2017]

STEPHEN TELFER Tenth Respondent

FAQIANG WANG and BING LIANG Eleventh Respondents

ZOE FROST and ROB FROST Twelfth Respondents

EDITH BALUYUT and ARMANDO BALUYUT

Thirteenth Respondents

HENRY CHESTER FERALES DELA CRUZ

Fourteenth Respondent

DAO HUNG LY and NHI MAI CHU Fifteenth Respondents

CHERYL SINGH Sixteenth Respondent

YOON CHEE and MAY CHENG Seventeenth Respondents

YUNZHEN YI Eighteenth Respondent

VIKRANT CHAUDHARY Nineteenth Respondent

KWAI YIU LINDA LAM and KWAI YING JUDY LAM

Twentieth Respondents

EDWARD LINTON Twenty-First Respondent

MARK IJSSELDIJK Twenty-Second Respondent

MARY GILDER
Twenty-Third Respondent

GURBACHAN SINGH and INDERPREET KAUR Twenty-Fourth Respondents

KAHUERA NEPIA and SHARON NEPIA Twenty-Fifth Respondents

JENNIFER RANDONICH and AGNES RANDONICH

Twenty-Sixth Respondents

GEORGE DONNOLLY and AMY COLE Twenty-Seventh Respondents

LEELA NAIDU
Twenty-Eighth Respondent

ESTHA SIMPSON and EDWARD SIMPSON

Thirtieth Respondents

WESTPAC BANKING CORPORATION Thirty-Second Respondent

ANZ BANK NEW ZEALAND LIMITED Thirty-Third Respondent

BANK OF NEW ZEALAND Thirty-Fourth Respondent

ASB BANK LIMITED Thirty-Fifth Respondent

MORTAGE HOLDING TRUST COMPANY LIMITED

Thirty-Sixth Respondent

TSB BANK LIMITED Thirty-Seventh Respondent

Hearing: 2 and 3 May 2017

Appearances:

J McBride and D A Cowan for 16th and 30th
Respondents/Applicants
T J G Allan and S F Powrie for Body Corporate
207650/Respondent

Judgment:

12 May 2017

JUDGMENT OF LANG J

[on application for order declaring levies ultra vires]

This judgment was delivered by me on 12 May 2017 at 3.30 pm, pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Date……………

[1]      This   proceeding   concerns   30   residential   units   collectively  known   as Richmond Terraces.   The units are constructed in six separate blocks situated on Dawson and Chapel Roads, East Tamaki.  The affairs of the complex are conducted through a body corporate incorporated under the Unit Titles Act 2010 (the Act).  The body corporate comprises the owners of each of the units in the complex.

[2]      In or about 2009, weathertightness issues became apparent in relation to the complex.   The body corporate and  unit owners  then issued proceedings against persons they considered to have been responsible for failures associated with the construction of the complex.  They settled that litigation in 2013 and obtained a sum of money as a result.  They then resolved to repair the complex by way of a total reclad.

[3]      On 8 August 2016, this Court granted an application by the body corporate for orders under s 74 of the Act approving a scheme to carry out the necessary repairs on the complex.1   By that stage the repairs were well advanced, having been commenced in or about August 2015.

[4]      The unit owners originally believed that the repairs would cost less than $6 million to complete.  Very quickly, however, it became apparent that the final repair cost would be considerably greater.  The total cost of repairs may now be in excess of $13 million.

[5]      Twenty of the units have now been completed, and work is progressing in respect of the remaining ten.  The body corporate will not be able to apply for a code compliance certificate until the repairs to all units have been completed.

[6]      In order to meet the repair costs the body corporate first used the settlement monies raised through the litigation.  It then applied funds raised following a levy of all unit owners in or about June 2015. This raised the sum of $1.774 million.

[7]      In June 2015 the Committee appointed by the body corporate to oversee the repair  work  purported  to  impose a further levy on  all  unit  owners to meet  the

1      Body Corporate 207650 v Speck & Others [2016] NZHC 1826.

ongoing cost of repairs.  It transpired that the Committee did not have the power to impose a levy, and that this needed to be done by the body corporate itself.   In October and December 2015 the body corporate resolved to issue a second levy in respect of all units by which it anticipated raising a further sum of $4.982 million.2

[8]      The owners of two units in the complex, Ms Cheryl Singh (Unit 16) and Mr and  Mrs  Edward  and  Esther  Simpson  (Unit  30),  do  not  accept  that  the  body corporate had the power to raise the second levy.  They contend that much of the work that has resulted in the increased costs was not authorised by the scheme approved by the Court.  The scheme permitted the parties to the original application to return to the Court in the event that the implementation of the scheme gave rise to disputes.    They  have  therefore  filed  the  present  application  seeking  an  order declaring that the body corporate did not have the power to raise the second levy.

[9]      The body corporate opposes the application.  The application has been served on each of the unit owners but none has filed documents in support of or opposition to it.

The scheme approved by the Court

[10]     Those sections of the scheme that are relevant to the discussion that follows are set out for convenience in an appendix attached to this judgment.

[11]     Several  points  can  be  made  about  the  scheme.     The  first  is  that  it acknowledged that the actual scope of the works to be carried out under the scheme would not be known until remedial works were under way.3    It is now well known that even invasive testing cannot reveal the true extent of damage caused by water ingress.    For  that  reason  the  scheme  in  the  present  case  included  the  repairs necessary to remedy both defects that had already been identified and damage that

was discovered once remedial work commenced.  In each case the repair work was

2      During the hearing I was advised that a further levy in the sum of $2 million was discussed at a general meeting of the body corporate on 29 April 2017.

3      Clause 1.4.

to be carried out to a standard sufficient to enable the complex to obtain a code compliance certificate.4

[12]     Secondly, the cost of the repairs was to be met by unit owners in accordance with the actual costs incurred in repairing individual units.5    This scheme differed from others in which, for example, the cost of repairs is met according to unit entitlement.

[13]     Thirdly,  the  cost  of  repairs  was  to  be  met  by  using  the  settlement  sum obtained from the litigation supplemented by levies (Top Up Amounts) imposed on unit owners.6    Where a unit owner failed to pay a levy, the body corporate could recover it as a debt due by the unit owner.7    In that event the body corporate could meet  any  resulting  shortfall  by  imposing  a  further  levy  on  the  remaining  unit owners.8    Before doing so, however, the body corporate was required to consider

exercising its powers to borrow funds to make up the shortfall.9    In either case, the

funds raised or borrowed would be recovered from the unit owner in default.10

[14]     The scheme also contained provisions emphasising that the repairs had to be undertaken as a single project in order to be carried out in the most efficient and cost effective manner.11   The repairs were also to be undertaken in a co-ordinated manner, irrespective  of  whether  they were in  respect  of  common  property or individual units.12   Ordinarily, the body corporate would be responsible for work carried out to the common property and unit owners would be responsible for repairs required in respect  of  their  units.    To  deal  with  this  issue  the  body  corporate  was  to  be responsible for repairs to both the common property and individual units.13

[15]     To give effect to this arrangement the owners appointed the body corporate,

with the Court’s sanction, as the agent of the owners “to do any things required to

4      Clause 1.5.

5      Clauses 1.12, 3.2 and 6.2.

6      Clauses 1.12 and 6.1.

7      Clause 6.5.

8      Clause 6.4.

9      Clause 6.4(a).

10     Clauses 6.4 and 6.4(a).

11     Clause 1.7.

12     Clause 1.11.

13     Clause 2.1.

arrange, co-ordinate and complete the repairs”.14     Specific examples of the powers granted to the body corporate were then set out in Clause 3.1(a) to (i).  The scheme also acknowledged it would be impractical to stop the repair process once the body corporate had entered into contractual arrangements for the repair work to be carried out.15

[16]     The body corporate was permitted to delegate some of its powers and duties to the Body Corporate Committee.  It could not, however, delegate the decisions set out in Clause 3.4. These included the power to raise and enforce payment of levies.

[17]     Furthermore, the scheme ratified and confirmed all of the repair work the body corporate had already performed prior to the Court giving its sanction to the scheme.16   It also recorded that after obtaining tenders for the repair work the body corporate had resolved to appoint Focus Remedial Limited (Focus) as the preferred contractor  to  carry  out  repairs.17      It  also  stated  that  the  repair  costs  had  been estimated by a quantity surveyor, Kwanto Limited, and the estimate was set out in a Schedule annexed to the scheme.  This stated that the estimated cost of repairs was

$4.998 million.

The cost of the repairs increases

[18]     The owners quickly became aware that the initial estimated cost of repairs was well off the mark.   This was the result of several factors, some of which are interrelated.

Error in calculating provisional sums

[19]     The successful tender priced the repair work at $4,998,884.06 plus GST.  In part, this was a fixed sum tender.  The tender also, however, allocated provisional sums for aspects of the repair work.  A provisional sum is the tenderer’s estimate of the amount that an aspect of the repair work will cost.  It is subject to correction once

the actual cost of the work is known.  One of the items in respect of which the tender

14     Clause 3.1.

15     Clause 1.8.

16     Clause 4.1.

17     Clause 7.1.

contained provisional sums was the replacement of timber found to have been damaged by water ingress.  Those who submitted tenders were required to price this aspect of the repair costs on the basis that 80 per cent of the timber in each unit would need to be replaced.

[20]     The successful tender was quickly found to contain a major error in relation to this issue.  This occurred because the tender used an incorrect formula for pricing the replacement of damaged timber within the complex.  The tender had taken the estimated quantity of timber to be replaced in respect of each unit and priced it on the basis of $1 per metre.  By way of example, if a unit was estimated to require 48 metres  of replacement  timber,  the tender provided a provisional  sum of $48  in respect of the replacement timber for the unit.   Regrettably, the body corporate’s professional advisers did not pick up this major and seemingly obvious error until after the tender had been accepted.  This immediately increased the estimated repair costs by more than $1.2 million.

Intertenancy walls

[21]     Each of the blocks within the complex is constructed in a terrace house style with each unit sharing one or more common walls with adjoining units.  These are known as intertenancy walls.   Whilst carrying out the remedial work  the Body Corporate  Committee  discovered  that  the  intertenancy  walls  in  the  complex  no longer meet the current fire standards. This became apparent in late 2015. The Body Corporate Committee then obtained an amendment to its building consent to replace the existing intertenancy walls with walls that met current fire safety requirements.

[22]     This issue produced two consequences.  First, work on the repairs needed to stop between December 2015 and February 2016 whilst the body corporate obtained the necessary amendment to its building consent to enable the intertenancy walls to be replaced.  Secondly, the cost of repairs has increased by between approximately

$720,000 and $966,000.

Damage to roof trusses

[23]     It transpired that the water ingress damage to the two blocks in respect of which repairs are still in progress was much greater than anticipated.  In particular, the damage to roof trusses in these blocks required the roof of each block to be replaced.  It also created a delay between November 2016 and February 2017 as the body corporate obtained a further amendment to its building consent for this unanticipated aspect of the remedial work.

Extension of time claims

[24]     The issues that arose in respect of both the intertenancy walls and the roof trusses has led to claims by the contractor for extra payments totalling more than

$800,000 to reflect the delays that have occurred.  These are being disputed but may well require the body corporate to pay a significant sum.

Other variations

[25]     The cost has escalated further as a result of other variations to the original contract.  Although these have not been itemised, the amount involved is significant. Some of these items remain in dispute and are yet to be resolved.

The argument for the applicants

[26]     As I have already observed, the applicants contend that the scope of the remedial works has changed to the extent that it now goes well beyond the work that was subject to the scheme approved by the Court in August 2016.  For that reason they say the body corporate has no ability to impose levies in respect of those works in reliance on the scheme approved by the Court.

[27]     Before  dealing  with  that  submission  I  propose  to  refer,  albeit  relatively briefly, to other submissions advanced in support of the application.   For the applicants, Mr McBride made wide ranging submissions designed to persuade me that the Court needs to intervene at this stage to protect the interests of unit owners as a whole. First, he submitted that the Body Corporate Committee responsible for overseeing the repair work had failed miserably in its responsibility to ensure the

repair work was undertaken in a cost effective and economical manner.  In particular, he submitted that the Committee failed to impose adequate cost controls, and failed to adequately challenge or dispute claims for extra payment made by Focus.

[28]     It is difficult, however, to see what motive the Committee would have had to spend the unit owners’ money in a profligate manner. The Committee members were all unit owners themselves, and they stood to lose from such an approach in the same manner as the remaining owners.  The fact that many items remain the subject of a dispute with Focus also tells against this submission.

[29]     It is neither necessary nor appropriate for me to reach any conclusion in relation to these issues because they are not relevant to the present application. Furthermore, Clause 14.1 of the scheme leaves open the prospect that members of the Committee may be liable to unit owners for wilful misconduct or gross negligence.   The manner in  which  the Committee has  carried out  its  task  may therefore yet need to be tested in another forum.

[30]     Mr McBride also submitted that the Committee has failed to communicate with owners in an adequate manner.  This meant the owners were effectively left in the dark regarding the extent to which costs had increased and the reasons why that occurred.  Furthermore, Mr McBride suggested that unit owners may not even have been aware that the scheme was approved by the Court in August 2016.  He pointed out that the body corporate resolved to apply for orders under s 74 at its annual general meeting on 18 February 2015.  The Minutes of that meeting record that the body corporate also resolved to authorise the Body Corporate Committee and Body Corporate Chairperson “to take such further action as necessary and incidental to the above resolutions to enable the Body Corporate to make the said application to the Court”.

[31]     The application seeking orders under s 74 was filed by the body corporate’s solicitors on 18 December 2015.  There was then a delay caused by the need to serve the application on all unit owners.  Over the next six months it became increasingly obvious that the actual cost of repairs was  going to be well above the amount originally estimated in the successful tender.  At its meeting on 20 June 2016 the

Body Corporate Committee noted that the required top up for all units had increased from $1.77 million to $6.4 million. The Minutes of that meeting also record:

8.0      SECTION 74 ORDER

The hearing date for the Scheme had been enlarged as a result of difficulties effecting service.  In light of the progress on matters to date it was queried as to whether or not the Body Corporate needed to expend further funds in regards to the Section 74 Scheme.

RESOLVED

“That this be put on hold until further discussion with the owners.”

[32]     Unit owners were sent a copy of these Minutes together with a memorandum from the body corporate manager dated 28 June 2016.   As a result, Mr McBride suggested it was likely that unit owners would have been under the impression by July 2016 that the application for orders under s 74 was on hold.  They would also have been under the impression that the issue was to be discussed at a meeting of owners.  Despite this, the Minutes of the next general meeting of the body corporate on 10 July 2016 contain no reference to the s 74 application being discussed at that meeting.

[33]     I accept Mr McBride’s submission that unit owners may not have been aware in July 2016 that the Court was going to determine the s 74 application the following month.   I therefore draw no inference either way from the fact that the s 74 application was neither supported nor opposed by any of the unit owners.   However, minutes of meetings of the body corporate on 11 August 2016 and 5 December 2016 both refer to discussions relating to the orders the Court had made on 8 August 2016. Unit owners were therefore obviously aware that the orders had been made shortly after the event.

[34]     More importantly, however, the issue of whether or not unit owners were aware that the s 74 application was about to be determined by the Court has no relevance to the decisions I am required to make.   The orders made on 8 August

2016 remain in force until such time as they are set aside by this Court or the Court of Appeal.  As a result, the body corporate retains the ability to levy unit owners for the cost of repairs undertaken pursuant to the scheme.   It makes no difference for

present purposes whether or not the unit owners knew about the orders the Court made on 8 August 2016.  Furthermore, the more general issue of whether or not the Committee  communicated  adequately with  the  unit  owners  is  not  a  matter  that relates to the issue of whether or not the body corporate had the power to impose the second levy.

[35]     Mr McBride also submitted that unit owners have never had an informed opportunity to make a decision on what they should do once the repair costs began to escalate significantly.  He contended that if they had been given that opportunity at an early stage, they may have resolved to abandon the repairs and to demolish the complex.   That may have enabled them to emerge from the project with a more valuable asset and with much greater certainty as to cost.    Mr McBride asks the Court to craft a solution that will enable the unit owners to now have a discussion that ought to have occurred long ago.  This may result in the unit owners seeking further orders from the Court under s 74.  That would permit disaffected unit owners to find out why the repair costs have escalated so much.

[36]     Mr Allen for the body corporate disputes the alleged lack of opportunity for the  unit  owners  to  discuss  the  issues  that  have  arisen.    He  points  out  that  the escalating cost of repairs has been discussed at numerous general meetings of the body corporate held during 2015, 2016 and 2017.

[37]     Mr Allen also points out that Ms Singh was a member of the Body Corporate Committee throughout the period when the increases in costs were coming to light. In addition, Ms Singh had suggested to the other members of the Body Corporate Committee in February 2016 that some owners were interested in the possibility of halting  repairs  and  selling  the  land.   At  a  meeting  on  3 April  2016  the  Body Corporate Committee also gave consideration to halting work on one block “given the rapidly shrinking gap between the cost to repair and the cost to rebuild”.

[38]     I consider this issue is likely to have been laid to rest at an Emergency Extraordinary Meeting of the body corporate held on 10 July 2016.  The Minutes of that meeting show that Mr Paul Grimshaw, a solicitor whose firm specialises in leaky buildings litigation, told attendees that the owners should make it their priority “to

get on and get the complex fixed”.  Mr Grimshaw also “reinforced that you cannot suddenly stop” repairs, and that owners needed a code compliance certificate in order “to restore at least minimal value to the complex”.  I consider these comments are likely to  have  persuaded  unit  owners that  stopping the  repair  works and/or demolishing the units was not a realistic or viable prospect.

[39]     I  accept  Mr  Allen’s  submission  that  the  unit  owners  have  had  ample opportunity to consider their options.  More importantly, Mr McBride’s submission ignores  three  factors.    First,  the Court  can  only make a  decision  based  on  the application that the applicants have filed.  The present application does not seek an order that the unit owners attend a meeting to consider their options.  Secondly, it is now far too late for the unit owners to discuss what should happen to the complex. The repairs to  twenty of the units have now been  completed, and  those to the remaining units are well advanced.   Demolition and sale or rebuild are no longer viable options.  Thirdly, the unit owners retain the ability to call a meeting at any stage if a sufficient number of them believe this will provide a meaningful forum for discussions.  If those owners wish to file a new application for orders under s 74 they can also pass a resolution to that effect.

[40]     Mr McBride next asks me to consider the position of unit owners who do not have the means to meet the levies the body corporate has imposed.  I agree that this is likely to be a serious problem for some unit owners.  As unpalatable as it may be, however, the predicament in which these owners now find themselves is a product of two factors.  The first is that they agreed to enter into a form of property ownership in which the decisions made by a majority of unit owners can bind a dissenting minority.  The second is that the cost of repairing damage caused by water ingress to an apartment complex such as Richmond Terraces is often likely to be far in excess of initial estimates.

[41]     In reality, the only way in which this issue could now be addressed is for the remaining unit owners to assume responsibility for some or all of the costs incurred by unit owners who now cannot afford to meet their levies.  That is a decision the unit owners would need to make themselves, and is not an issue with which the

Court can become involved.  Furthermore, it would involve a different form of cost allocation than that to which all unit owners agreed at the outset.

[42]     I consider that all of these issues fall outside the scope of the sole issue before the Court.  This is whether the second levy relates to repairs or expenditure falling within the scope of the scheme approved by the Court.

Does the second levy relate to repairs or expenditure falling within the scope of the scheme approved by the Court?

[43]     The settlement monies obtained from the litigation and the first levy were sufficient to fund the original cost estimate contained in the successful tender.  The issue is whether the remaining expenditure to which the second levy relates was made in respect of work that fell within the scope of the scheme as sanctioned by the Court.

[44]     The increased expenditure necessary to compensate for the error relating to the provisional sums clearly falls within that description.   It relates directly to the quantities  of timber  needed  to  replace timber  that  had  been  damaged  by water ingress.   The error would always have been discovered eventually and the correct sum paid in accordance with the true value of the timber used in the remedial work.

[45]     The  position  is  not  necessarily  so  clear  in  respect  of  the  remaining expenditure.     By  way  of  example,  Mr  McBride  submits  that  the  increased expenditure in respect of the intertenancy walls fell outside the scope of the original works because it did not form part of the work referred to in the plan annexed to the scheme.  He also submits that it is impossible on the material presently available for the unit owners and the Court to know whether this aspect of the work was necessary and/or incidental to the repairs.  He suggests it may have been undertaken as a result of a decision by the Body Corporate Committee to voluntarily upgrade the complex to a current fire rating standard.

[46]     The  evidence  from  Mr  David  Clifton,  an  independent  building  surveyor engaged by the body corporate in October 2016, is that the Council required the building consent to be amended and the intertenancy walls rebuilt after it discovered

following stripout that the existing intertenancy walls did not comply with current fire safety standards.  Mr Clifton does not expressly say, however, that the work was part of the remedial measures necessary to repair damage caused by water ingress.

[47]     The   present   application   is   not   a   particularly   satisfactory   method   of determining factual disputes such as this because it has proceeded as a defended interlocutory application in which deponents have not been cross-examined.   This means it is difficult to assess the weight to be given to Mr McBride’s argument that the Body Corporate Committee should have refused to do the work because s 112 of the Building Act 1991 prevented the Council from requiring the body corporate to undertake work that was not directly related to the repair work it was undertaking to address weathertightness issues.

[48]     Whether the work fell  within  the scope  of the  scheme  depends  on  how broadly the scheme is to be interpreted.   If it is construed narrowly, the scheme would only sanction the work referred to in the Plan together with repairs in respect of damage discovered during the course of that work.  Two factors persuade me that this would not be a correct approach.   First, Clause 1.4 of the scheme expressly stated that the scope of works required to repair the complex will only become fully apparent once remedial works are actually commenced.  This makes it clear that the repair of defects that are discovered once remedial work has commenced will fall within the scope of the plan.   Secondly, Clauses 1.4 and 3.1(g) of the scheme demonstrate that the overall objective of the scheme was to ensure that the complex was restored to a state sufficient to achieve code compliance.   This was no doubt highly important to all unit owners because without code compliance the value of their units would remain severely impaired.   I therefore consider that the scheme extended to all work necessary to ensure that the complex reached a state where it could obtain a code compliance certificate.

[49]     A broad interpretation of the scheme accords with the approach taken by the courts in other cases.  In Wheeldon v Body Corporate 342525, for example, Muir J observed that the merits of one repair plan over another “are best determined by those who are affected by it and have to fund it, have personal knowledge of it, have participated in any discussions relating to it at a properly convened meeting of the

Body Corporate, and have decided accordingly”.18   In a similar vein, if the members of a body corporate decide upon a broadly worded scheme that reflects a desire to obtain a code compliant complex, the Court should interpret the scheme in a manner that accords with this purpose.   It should not adopt an approach that frustrates the clear purpose of the scheme.

[50]     This does not mean that the Body Corporate Committee was entitled to view the scheme as providing an open-ended authority to carry out work regardless of cost and regardless of whether it was necessary to deal with the weathertightness issues faced by the complex.  To take an extreme example that I raised with counsel during the hearing, the scheme did not authorise the body corporate to build a tennis court and swimming pool even though that may have enhanced the ultimate value of the complex.    Work  carried  out  for  those  purposes  could  not  have  been  recovered through the top up levies that have been imposed on unit owners under the scheme.

[51]     I consider the criterion to be used in determining whether work falls within the scope of the scheme is whether the work in question was necessary to bring the complex to a state of code compliance.   Applying that approach, if the Council required the intertenancy walls to be rebuilt to meet current fire safety standards it is likely that failure to take that step would result in the Council declining to issue a code compliance certificate.  The Body Corporate Committee was entitled to adopt a conservative approach in relation to issues such as this.  If it believed that failure to comply with  the  Council’s  directive  could  result  in  code  compliance  not  being achieved, it was entitled to err on the side of caution.   The unit owners would obviously not have welcomed the Body Corporate Committee saving money by not bringing the intertenancy walls up to current standard but thereby failing to achieve code compliance.   The cost of replacing the intertenancy walls is undoubtedly significant.  Present estimates are that it will cost between $720,000 and $966,000.  I consider, however, that this work falls within the scheme.

[52]     I take the same approach in respect of any expenditure the body corporate may be required to make as a result of the extension of time claims.   As I have

already  recorded,  these  arise  out  of  the  delays  caused  by  the  need  to  obtain

18     Wheeldon v Body Corporate 342525 [2015] NZHC 884 at [73].

amendments to the building consent.   These were required to authorise the work necessary to deal the issues arising out of the non-complying intertenancy walls and the replacement of damaged roof trusses.   Any failure by the Body Corporate Committee to obtain the required building consents was likely to have jeopardised code compliance.  The repairs to the roof trusses were also rendered necessary in any event because of damage caused by water ingress.   Expenditure in relation to the extension of time claims is therefore within the scope of the works covered by the scheme.

[53]     On balance I consider the increased costs caused by the remaining variations also form part of the work undertaken to ensure that the complex is restored to a standard sufficient to bring the complex to a state of code compliance.  There is no suggestion in the evidence that the Body Corporate Committee has elected to voluntarily undertake work that will result in the overall upgrading or betterment of the complex.  It has not, for example, installed double glazing or new ranch sliders to

bedroom suites as was the case in Wheeldon v Body Corporate 342525.19

[54]     Instead, the tenor of the evidence for the body corporate is that it has been required to deal with a seemingly endless flow of problems that have emerged as it has undertaken the remedial work.   By way of example, it became necessary to spend approximately $281,000 on drainage works.  Although drainage works may not have related directly to repair damage caused by water ingress, drainage issues are nevertheless subject to strict regulatory oversight.   There are a range of other similar works that have also required further I am therefore satisfied that such works fall within the scheme because they are necessary to bring the complex to a state in which it will be not only weathertight but also code compliant.

Conclusion

[55]     With the benefit of hindsight, it may have been better for the unit owners in this particular complex to have decided at the outset, or shortly after they realised the likely scope of repairs, to demolish the complex and sell the land or rebuild.  Once

they committed to the repair project, however, it no doubt became extremely difficult

19     Wheeldon v Body Corporate 342525 [2015] NZHC 884 at

for unit owners to ignore the wasted costs that would result from a decision to demolish the complex.

[56]     For the reasons I have given, however, I am satisfied on the balance of the probabilities that all of the work the body corporate has carried out has been directed towards the objective of ensuring that the remediated complex is constructed to a standard that will result in code compliance.  As a result, it falls within the rubric of the scheme approved by the Court, and the body corporate is entitled to levy unit owners to meet the cost of the work.

Result

[57]     The application for orders declaring the second levy imposed by the body corporate on unit owners is dismissed.

Costs

[58]     The body corporate has succeeded and is entitled to costs.   If the parties cannot reach agreement on this issue counsel for the body corporate is to file a brief memorandum (ie no more than five pages in length) dealing with costs and I will

then give directions for the filing of memoranda in response and reply.

Lang J

Solicitors:

Grove Darlow & Partners, Auckland

Doug Cowan, Auckland
Counsel:

J McBride, Auckland

APPENDIX

SCHEME UNDER SECTION 74 UNIT TITLES ACT 2010

1.        Preamble

1.1This is a Scheme governing remedial works to the buildings that have been built on the base land for Body Corporate 207650 (“the Body Corporate) and known as Richmond Terraces (“the Building”).

1.2An  assessor’s report prepared in  or  around  2009 by an  assessor contracted by the Chief Executive of the Department of Building and Housing for the Weathertight  Services  Group  confirmed  that  the Building was built with design and construction defects.  The report sets out the necessity of extensive repairs to the Building.

1.3The scope of works that will ultimately be required to repair the Building will only become fully apparent when remedial works are actually commenced.

1.4Subsequent  to  the Assessor’s  Report,  CoveKinloch  has  prepared plans for the proposed remedial works (“the Plan”), a copy of which is annexed hereto marked “A”.  The remedial works outlined in the Plan,   along   with   any   works   required   to   repair   any   as   yet undiscovered damage sufficient to obtain a Code Compliance Certificate  for  the  Building  (together,  “the  Repairs”),  are  those works intended to be governed by this Scheme.

1.5The repairs will require work to be done to common property and all of the units (including principal and accessory units) in the Building.

1.6In order for the Repairs to be conducted in the most efficient and cost effective manner they must be undertaken as a single project and, as such, require the sanction of the Court pursuant to this Scheme.

1.7Once  the  Body  Corporate  has  entered  into  a  contract  for  the completion of the Repairs in accordance with the provisions of this Scheme and this Scheme is sanctioned by the Court, it will be impractical to stop the process as the Body Corporate will be committed to having the Repairs completed.

1.8The cost of the Repairs, subject to the determination of the cost of any as yet undiscovered damage, has been determined by a tender process and will be funded by the settlement sum, and additional funds required (“the Top-Up Amount”).

1.9It will; be necessary to raise the Top-Up Amount for the Repairs from each of the registered proprietors of the units in the Body Corporate (“the Owners”).

1.10This Scheme is intended to ensure the Repairs proceed in a co- ordinated manner, irrespective of whether such Repairs are to common property or to unit property.

1.11The Body Corporate has resolved that the fairest way of allocating the costs of the Repairs authorised by this Scheme is for Owners to contribute the whole of the settlement sum held on their behalf by the Body Corporate and then contribute a proportion of the Top-Up Amount that represents the quantity survey or assessed actual unit cost of such Repairs to that Owner’s unit as a proportion of the total Repairs.

2.        The Body Corporate to repair the entirety of the Building

2.1The Body Corporate is, subject to the provisions of this Scheme, to carry out the Repairs irrespective of whether the Repairs are to Common Property or to the Principal Units or Accessory Units as designated in Deposited Plan DP207650 (“DP207650”), a copy of which is annexed hereto marked “B”.

2.2The Repairs are to be completed in accordance with the Plan or any amendment of the same that the Body Corporate may approve, as permitted below.

3.        Powers

3.1The  Body  Corporate  is  granted  by  the  Owners,  on  the  Court’s sanction, the general power to act as the agent of the Owners to do any things required to arrange, co-ordinate and completion the Repairs, including but not limited to:

(a)       Engage  appropriately  qualified  persons  to  identify  and quantify the extent of the Repairs both now and from time to time  in  the  future  until  such  time  as  the  Repairs  are complete;

(b)       Instruct  appropriately  qualified  advisors  to  develop  plans and specifications for the work required to be carried out to complete the Repairs, together with such variations or additions as may be required from time to time;

(c)       Approve any amendments to the Plan as may be necessary to complete the Repairs;

(d)       Instruct appropriately qualified advisors to view tenders and recommend the contractor to be involved in the Repairs;

(e)       Contract  any  such  contractor(s)  as  the  Body  Corporate resolves to engage and to sign all necessary contracts and other documents to carry out the Repairs;

(f)       Employ appropriately qualified project manager(s) to: (i)   oversee the Repairs carried out by contractors;

(ii)      certify progress payments; and

(iii)     attend  payments  of  the  cost  of  the  Repairs  as required;

(g)       Apply for and obtain any consents and local body approvals and certificates of compliance required to complete the Repairs and do all things necessary to obtain a Building Consent for the Repairs (or such further defects and damage to the Building as may be identified during the course of the Repairs), complete the Repairs in accordance with the terms of any such Building Consent so as to obtain a Code Compliance Certificate for the Repairs;

(h) Borrow funds on such terms as the Body Corporate considers appropriate to pay for all or any part of the Repairs.   For the avoidance of doubt, the Body Corporate may borrow to pay any costs incurred by it under this Scheme where it is unable to pay those costs as they fall due because any Owner has failed (for whatever reason) to pay levies raised under Section 121 of the Unit Titles Act 2020 (“The Act”) to meet costs under this Scheme.   The exercise of this power to fund a shortfall as a result  of  non-payment  shall  not  affect  the  defaulting  unit Owner’s obligation to pay those levies (together with interest and penalties) or any subsequent owner of the unit’s obligation to pay those levies (together with penalties and interest) pursuant to Section 124 of the Act;

(i)        Carry  out  all  additional  matters  or  actions  necessary  to enable the Body Corporate  to progress and complete the Repairs.

3.2The costs of Repairs have been estimated by a quantity surveyor, Kwanto, and that estimate is set out in the Schedule attached hereto marked “C” (“the Estimate”).   The estimate provides that actual unit cost that may be levied and collected from the Owners in accordance with the provisions of this Scheme.

3.3Where the Body Corporate exercises the power under this Scheme to fund any shortfall in required funds arising from the non-payment of levies by the owner(s) of any unit, the Body Corporate shall be entitled to levy the owner of that unit for all costs and expenses associated with borrowing those funds (including any penalties arising from or any interest paid by the Body Corporate).

3.4The Body Corporate may delegate all or any of its powers and duties to the Body Corporate Committee (“the Committee”).  Nonetheless, the Committee must refer all major decisions in connection with the Scheme for decision to a general meeting of the Body Corporate, and may, in its discretion, elect to refer any matter in relation to the Scheme for decision to a general meeting of the Body Corporate. Major decisions shall include:

(a)       Any decisions to engage contractors or consultants pursuant to the terms of the Scheme;

(b)      Any decision to engage a project manager; (c)      Any decision to alter the Plan; and

(d)       All decisions to raise and enforce payment of levies or to borrow funds to pay for the costs incurred pursuant to this Scheme.

4.        Work already done ratified

4.1All investigation and repair work the Body Corporate has already undertaken in furtherance of the obligations imposed under this Scheme are ratified and confirmed as forming part of this Scheme and are deemed to have been undertaken in accordance with this Scheme.

6.        Levies

6.1The  Body  Corporate  is  authorised  to  raise  a  levy  to  meet  its obligations pursuant to this Scheme and such a levy shall take effect as if it was a levy raised pursuant to section 121 of the Act (“a Scheme Levy”).

6.2Scheme Levies shall be calculated according to a proportion of the costs represented by the quantity survey or assessed actual unit cost of such Repairs to that Owner’s unit as a proportion of the total Repairs.

6.4If, for whatever reason, there are insufficient funds to meet the Body Corporate’s obligations under this Scheme as they fall due, then the Body Corporate may raise additional Scheme Levies pursuant to this Scheme in order to meet those obligations.  It is recognised that the most likely reason for such additional Scheme Levy will be the failure of one or more Owners to pay their Scheme Levies owed.  In raising such additional Scheme Levies the Body Corporate shall:

(a)       Consider exercising its power to borrow funds to make up the shortfall under this Scheme and recovering the cost of such from the defaulting unit owner under Section 127 of the Act;

(b)       If it considers it appropriate to raise a Scheme Levy to make up the shortfall rather than borrowing the funds to do so, raise sufficient funds to ensure (as far as foreseeable at the time the Scheme Levy is raised) that the monies actually collected from the Scheme Levy will be sufficient to meet the obligations of the Body Corporate under the Scheme as they fall due.

6.5If an owner or owners fail to pay all or any part of a Scheme Levy the day it is due, the full amount of that Owner’s Scheme Levies owed  shall  become  payable  immediately  and  if  not  paid  in  full within seven working days it shall be recovered as a debt due by the owner(s) in default to the Body Corporate.

7.        Decision to enter into the construction contract for the Repairs

7.1The Body Corporate has obtained tendered prices for the Repairs and the Body Corporate has resolved to appoint Focus Remedial Limited as the preferred contractor (“the Contract”).

7.2      The Repairs has been divided into stages (“the Repair Stages”).

The dates for the Repair Stages have been set to meet the expected

work  schedule  and  the  Body  Corporate’s  obligations  to  pay  the

contractor(s) for the remedial works.

7.3The Body Corporate is authorised to raise Scheme Levies necessary to meet its obligations under the Contract in accordance with the Scheme.

9.        Reporting

9.1The Body Corporate will keep each Owner fully informed of details of the Repairs and progress of same over the period of the scheme by reporting every three months.

11.      Obligations of Owners

11.1     Owners  obliged  to  cooperate  with  the  Body  Corporate  or  the Committee in respect of the implementation of this Scheme and the progression and completion of the Repairs.

11.2     Owners are required to provide access to their unit property and vacate their unit as may be necessary, as well as comply with all health and safety directions.  For the avoidance of doubt the Body Corporate, and its contractors appointed pursuant to this Scheme who are carrying out obligations and work pursuant to this Scheme, are  permitted  to  access  at  all  reasonable  hours  any  unit  in  the Building necessary in order to carry out such obligations or work.

13.      Leave is reserved

13.1Leave is reserved to any party affected by the Scheme to apply to the Court for further orders in respect of any disputes arising under this Scheme, or in the event that the Body Corporate does not proceed with the Repairs, leave is to be granted to any party to bring the

matter back before this Court for such further orders as may be appropriate.

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

12

Gu v Body Corporate 211747 [2018] NZCA 396
Cases Cited

2

Statutory Material Cited

1