IN THE HIGH COURT OF NEW ZEALAND TAURANGA REGISTRY
I TE KŌTI MATUA O AOTEAROA TAURANGA MOANA ROHE
CIV-2022-470-000084
[2024] NZHC 1539
BETWEEN DANIEL WILLIAM KELLY ANDREWS and GLENDA LORRAINE ANDREWS
Appellants
AND
AHS CONSTRUCTION LIMITED
Respondent
CIV-2019-470-000068 BETWEEN
AHS CONSTRUCTION LIMITED
(Formerly Advanced Housing Systems New Zealand Limited)Applicant
AND
DANNY WILLIAM KELLY ANDREWS and GLENDA LORRAINE ANDREWS
Respondents
Hearing: On the Papers at Auckland Judgment:
13 June 2024
JUDGMENT OF POWELL J
[Costs]
This judgment was delivered by me on 13 June 2024 at 12.00 pm.
Pursuant to R 11.5 of the High Court Rules.
…………………..
Registrar/Deputy Registrar
DANIEL WILLIAM KELLY ANDREWS and GLENDA LORRAINE ANDREWS v AHS CONSTRUCTION LIMITED [2024] NZHC 1539 [13 June 2024]
[1] On 26 April 2024, I dismissed Mr and Mrs Andrews appeal against a decision of Judge K D Kelly (“the appeal”).1 In dismissing the appeal I determined that the respondent, AHS Construction Ltd (“AHS”), was entitled to costs and set out a timetable for the parties to file submissions in the event that costs could not be agreed.2
[2] Both parties have filed submissions as directed. As well as calculating the costs sought in respect of the appeal, Mr Elsmore for AHS has also sought costs on separate High Court proceedings involving the parties, namely AHS’s application for charging orders prior to judgment in the District Court and a subsequent application for enforcement of those orders (“the charging order proceedings”).3 There is no objection on the part of Mr and Mrs Andrews to determining costs on the charging order applications and this judgment therefore deals with the cost issues in both proceedings.
[3] With regard to the appeal, Mr Elsmore has calculated costs on a 2B basis totalling $11,472 but submits that these should be uplifted by 50 per cent as none of the grounds of appeal had a chance of succeeding and the appeal had attempted to raise issues that were not argued in pleadings or at the District Court hearing, meaning that a full day’s hearing for the appeal was required rather than the half day set down. With regard to the charging order proceedings, Mr Elsmore has sought costs on a 2B basis in the sum of $11,950.
[4] In response, Mr Refoy-Butler, on behalf of the appellants, submits that costs on a 2B basis are appropriate. With regard to the appeal, Mr Refoy-Butler takes no issue with AHS’s calculation of the scale costs payable but submits that there is no basis for increased costs. With regard to the charging proceedings, Mr Refoy-Butler submits that AHS’s calculation of costs for the charging order is incorrect and that the appropriate figure is $7,648.
1 Andrews v AHS Construction Ltd [2024] NZHC 937.
2 At [66].
Discussion
[5] Having reviewed the files and considered the calculations provided by counsel, I am satisfied that costs on a 2B basis are appropriate in respect of both proceedings. Although I accept…
Continue reading Andrews v AHS Construction Limited
Sign in free to access the full text
- AGLC
- Andrews v AHS Construction Limited [2024] NZHC 1539
- Case
- [2024] NZHC 1539
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included determining the appropriate basis for awarding costs in both the appeal and the charging order proceedings. AHS Construction Limited argued for an uplift in costs due to the lack of merit in the appeal and the need for a full day’s hearing. In contrast, the Andrews argued for costs on a standard 2B basis and challenged the accuracy of the calculations for the charging order proceedings. The court had to assess whether the costs sought by AHS were justified and whether there were errors in the calculation of costs for the charging order proceedings.
In assessing the costs, the court determined that while the appeal was ultimately without merit, the points raised by the Andrews were able to be dealt with expeditiously within the context of the appeal hearing. The court found no basis for increased costs beyond the 2B basis for the appeal. Regarding the charging order proceedings, the court identified errors in the calculation by AHS, specifically the inclusion of items that were not applicable. Instead, the court found that the correct items from the schedule of costs should be applied, resulting in a different total for the charging order proceedings. The court concluded that costs on a 2B basis were appropriate for both proceedings, with a corrected total for the charging order proceedings.
The final orders of the court were that Daniel William Kelly Andrews and Glenda Lorraine Andrews are to pay AHS Construction Limited $11,472 in respect of the appeal and $9,799 in respect of the charging order proceedings. This decision was made on the basis of the costs calculations provided and the court’s assessment of the merit and complexity of the proceedings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.