Alaska Construction + Interiors Auckland Limited

Link copied
Case Copied 19 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2020-404-000587

[2020] NZHC 1056

UNDER Judicial Review Procedure Act 2016

IN THE MATTER

of an application for Judicial Review

BETWEEN

ALASKA CONSTRUCTION +

INTERIORS AUCKLAND LIMITED
Applicant

AND

CHRISTOPHER JAMES LAHATTE

First Respondent

LOVICH FLOORS LIMITED

Second Respondent

Hearing: 1 May 2020

Appearances:

C T Patterson for the Applicant

B Rooney for the Second Respondent

Judgment:

20 May 2020


JUDGMENT OF WOOLFORD J


This judgment was delivered by me on Wednesday, 20 May 2020 at 12:30 pm pursuant to r 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Solicitors:Hornabrook MacDonald Lawyers, Auckland, (M Hornabrook) for the Applicant Lovegroves, Auckland, (T Hibbitt) for the Second Respondent

Counsel:C T Patterson and E J Grove (Chris Patterson Barrister Ltd), Auckland B Rooney, Auckland, for the Second Respondent

ALASKA CONSTRUCTION + INTERIORS AUCKLAND LIMITED v LAHATTE & ANOR [2020] NZHC 1056 [20 May 2020]

[1]    Alaska Construction + Interiors Auckland Ltd (Alaska) applies for judicial review of a determination dated 10 April 2020 by an adjudicator appointed under the Construction Contracts Act 2002 (CCA), Mr Christopher LaHatte, in favour of Lovich Floors Ltd (Lovich). A statement of claim and statement of defence have both been filed.   Neither side adduced further evidence than what was before Mr LaHatte.    Mr LaHatte abides the decision of the Court.

Factual background

[2]    Alaska was the head contractor on construction works for an apartment complex at 33 Henderson Valley Road, Auckland. Alaska contracted some of the construction works to Lovich under a subcontract comprising Alaska’s invitation to tender, Lovich’s tender and an exchange of emails between Alaska and Lovich on  17 and 18 January 2019. The price agreed was $350,000 plus GST.

[3]    The subcontracted works did not proceed smoothly. Difficulties arose over scheduling of the works, availability of work surfaces, capacity to undertake the works and quality of the works. Each party thought the other was to blame.

[4]    Alaska engaged additional contractors alongside Lovich to help complete the works. They were paid by Alaska. The subcontracted works were also varied, which led to further costs by Lovich. Repairs were undertaken to bathroom ceilings and carpet tiles. That led to yet further costs.

[5]    On 25 July 2019, Lovich delivered payment claim number four to Alaska (the July payment claim). It claimed for 82.65 per cent of the subcontracted works and  75 per cent of the variations, which had been itemised following the construction issue drawings. On 22 August 2019, Lovich received a payment schedule from Alaska which allowed for 80 per cent of the subcontracted work and zero per cent for the variations which had been claimed by Lovich. The schedule also included contra charges for work completed by other contractors and for some remedial work on bathroom ceilings.

[6]    On 28 August 2019, Alaska sent a revised payment schedule to Lovich in which the contras were increased. The subcontracted works were completed in

September. The last payment Lovich…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Alaska Construction + Interiors Auckland Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NZHC 1056
Decision Date

CaseChat Overview and Summary

Alaska Construction + Interiors Auckland Limited sought judicial review of an adjudicator's determination in favour of Lovich Floors Limited. The central issue was whether Alaska was required to pay Lovich $113,443.71 or an alternative amount, as well as whether Alaska was liable for the adjudicator's costs and Lovich's costs in the adjudication. Alaska contended that the adjudicator had failed to address all issues relevant to the determination, which amounted to a breach of natural justice and an unreasonable exercise of statutory power. The court found that the adjudicator's determination did not suffer from any jurisdictional error or unreasonableness. The dispute had not been unilaterally modified by Lovich, and the statutory scheme governing payment claims and schedules was not suspended by the adjudication process. Additionally, the adjudicator provided adequate reasons for awarding Lovich full solicitor client costs. The application for judicial review was dismissed. If the parties could not agree on costs, they were to file memoranda of no more than three pages within ten working days of the decision.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.