79 Manners Street Limited v BJ Pye Sheet Metals Limited HC Wellington CIV 2008-485-1907

Case

[2010] NZHC 255

10 February 2010

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND

WELLINGTON REGISTRY

CIV-2008-485-1907

BETWEEN  79 MANNERS STREET LIMITED

Plaintiff

ANDBJ PYE SHEET METALS LIMITED Defendant

Hearing:         2 February 2010

Appearances:  M. Singleton - Counsel for Applicant

No appearance for Respondent

Judgment:      10 February 2010 at 3.15 pm

JUDGMENT OF ASSOCIATE JUDGE D.I. GENDALL

This judgment was delivered by Associate Judge Gendall on 10 February 2010 at

3.15 pm pursuant to r 11.5 of the High Court Rules.

Solicitors:            DLA Phillips Fox, Solicitors, PO Box 2791, Wellington

79 MANNERS STREET LIMITED V BJ PYE SHEET METALS LIMITED HC WN CIV-2008-485-1907  10

February 2010

Introduction

[1]       This is an application to set aside  a statutory demand issued  by  the respondent,   BJ   Pye   Sheet   Metals   Limited   (“BJ   Pye”),   seeking   the   sum   of

$32,146.59.  The  statutory  demand  is  based  on  a  debt  alleged  to  be  due  from  the applicant, 79 Manners Street Limited (“79 Manners”), for structural steel and metal work supplied to it by BJ Pye.

[2]       79 Manners contends that the demand should be set aside on the basis that there  is  a  genuine  and  substantial  dispute  in  respect  of  the  debt,  that  it  has  a counterclaim against BJ Pye and that BJ Pye’s claim is time-barred.

Background Facts

[3]       79 Manners is the registered proprietor of apartments in Tory Street, Wellington  (“the  apartments”). On  3  May  2002,  the  parties entered  into  an agreement whereby BJ Pye was to supply 79 Manners with structural steel and metal work for the apartments. It was agreed that BJ Pye would submit a monthly progress report and invoice to 79 Manners for work completed during that month. The work would  then  be  certified  by  Gill  Consultants  Limited  to  confirm  that  it  had  been completed and, upon certification, BJ Pye would be paid.

[4]       In July 2002, BJ Pye commenced the structural steel and metal works on the apartments. Progress claims were issued monthly. In July 2003, it issued its last progress report and invoice for work completed up  to  this  point,  setting  out  what work had been completed, the relevant cost, and what work remained outstanding. The work claimed for in this progress report was certified as being completed on 25

July  2003.  BJ  Pye  has  not  undertaken  any  further  work  on  the  project  since.  In particular, it is alleged that BJ Pye failed to install an important bond beam.

[5]       On 12 August 2008, BJ Pye issued the statutory demand claiming $32,146.59 against 79 Manners under s 289 of the Companies Act 1993. The statutory demand was stated to be for structural steel and metal work supplied to 79 Manners.

[6]       On 28 August 2008, 79 Manners filed and served the present application to have the statutory demand set aside. On 21 November 2008, BJ Pye filed a notice of opposition, together with an affidavit of its director.  79 Manners advised BJ Pye that issuing the statutory demand was improper and an abuse of the Court’s process.

[7]       On  16  February  2009,  79  Manners  made  an  offer  that  the  proceeding  be discontinued, with costs to lie where they fall.

[8]       79 Manners has since filed two amended applications, dated 2 April 2009 and

24 August 2009 respectively.  BJ Pye has filed a notice of opposition but only to the earlier amended application on 27 April 2009.

[9]       On  31  July  2009,  counsel  for  BJ  Pye  sought  leave  to  withdraw.  That application was granted.

[10]     Following numerous adjournments, the matter was set to proceed to hearing

on  2  February 2010,  regardless  of  whether  or  not  first  BJ  Pye  had  appointed  new representation or secondly, it would be in attendance at the hearing. When the matter was  called  before  me  on  2  February,  there  was  no  appearance  for  BJ  Pye  but  the hearing proceeded.

The Application

[11]     79 Manners brings this application pursuant to s 290 of the Companies Act

1993, which sets out the basis on which a statutory demand may be set aside:

290 Court may set aside statutory demand

(1)     The Court may, on the application of the company, set aside a statutory demand.

(4)     The Court may grant an application to set aside a statutory demand if it

is satisfied that—

(a)     There is a substantial dispute whether or not the debt is owing or is due; or

(b)     The  company  appears  to  have  a  counterclaim,  set-off,  or  cross- demand and the amount specified in the demand less the amount of the   counterclaim,   set-off,   or   cross-demand   is   less   than   the prescribed amount; or

(c)      The demand ought to be set aside on other grounds.

[12]     The principal grounds relied upon by 79 Manners in bringing this application are that BJ Pye’s cause of action is statute barred under s 4(1)(a) of the Limitation Act 1950, that there is a substantial dispute as to the debt under s 290(4)(a), and that

79 Manners has a counterclaim for an amount exceeding the amount specified in the demand under s 290(4)(b).

Is BJ Pye’s cause of action statute barred?

[13]     79 Manners submits that, because it is now over six years since the alleged breach of the contract in question here occurred, any claim BJ Pye has to recover the alleged debt is statute barred. This submission is made in reliance on s 4(1)(a) of the Limitation Act 1950, which provides that actions founded on simple contract shall not be brought after the expiration of 6 years from the date on which the cause of action accrued.

[14]     BJ Pye’s statutory demand was issued on 12 August 2008 which is only five years after the alleged breach of contract, so it would appear on its face to have been filed  within  the  limitation  period.  79  Manners  however,  submits  that  a  statutory demand is not an “action” for the purposes  of the  Limitation Act 1950,  but that it merely confers a right to bring  insolvency  proceedings  to  recover  a  debt  upon expiration  of  the  demand.  In  other  words,  79  Manners  argues  that  the  statutory demand was issued in respect of an alleged debt that has now ceased to be due and owing,  as  the  cause  of  action  accrued  more  than  six  years  ago  and  the  statutory demand itself does not qualify as an “action”.

[15]     The word “action”  is  defined  in  s  2  Limitation  Act  1950  as  meaning  “any proceeding in a Court of law other than a criminal proceeding”. Rule 1.3 of the High Court Rules defines the term “proceeding” as “any application to the Court for the exercise of the civil jurisdiction of the Court, other than an interlocutory application”.  In  my  view,  there  is  nothing  in  the  wording  of  these  definitions  to suggest that an application for a statutory demand is not an “action” for the purposes of the Limitation Act 1950.

[16]     Limitation principles clearly embody a tension  between  finality  in  civil litigation, and the difficulty of disproving stale claims, on the one hand, and justice being done in an individual case on the other: Amaltal Corporation Ltd v Maruha Corporation [2007] 1 NZLR 608 at [147]. Based on these principles, it would seem

to me to be inconsistent to  accept  79  Manners  proposition  here  that  issuing  a statutory  demand  is  not an  action  for  the  purposes  of  the  Limitation  Act  1950, although  the  respondent  of  such  demand  has  received  adequate  notice  of  an applicant’s claim and the grounds upon which it is made.

[17]     Although it is true that a statutory demand is not in itself strictly speaking a vehicle to enforce a debt, this does not appear to be a statutory requirement, as s. 4

Limitation Act 1950 merely refers  to  “actions  founded  on  simple  contract”  (my

emphasis).  Moreover,  a  successful  liquidation  application  based  upon  a  statutory demand  amounts  to  judicial  recognition  of  the  existence  of  the  debt,  providing  a basis for such an application, and thus should not be regarded as without effect.

[18]     Based on these considerations, it is my view that issuing a statutory demand may  well  constitute  an  “action”  for  the  purposes  of  the  Limitation  Act  1950.  It follows therefore that BJ Pye’s claim for the alleged debt cannot be considered to be time-barred in the present circumstances.

Is there a substantial dispute or a sufficient counterclaim as to the debt?

[19]     79 Manners submits that there is a genuine and substantial dispute as to the existence of the debt because BJ Pye never completed the work it was contracted to carry out. It claims that only part of the work contracted for was completed when BJ Pye finished work on the apartments in July 2003, and that the balance of the work remains incomplete to date.

[20]     Moreover, 79 Manners contends that the work that was completed by BJ Pye was substandard, as it failed to meet the manufacturer’s specifications, did not meet common trade practices, and left much of the building in an unsafe and dangerous condition.

[21]     The approach the Court is to adopt when considering applications relying on

s 290(4)(a) requires an applicant to show a fairly arguable basis upon which it is not liable for the amount claimed in the  statutory  demand:  Forge  Holdings  Limited  v Kierney Finance (NZ) Limited HC Christchurch N149/95, 20 June 1995 and Queen City Residential Limited v Patterson Co Partners Architects (No. 2) [1995] 3 NZLR

307. This formulation was approved by the Court of Appeal in United Homes (1988) Limited v Workman [2001] 3 NZLR 447 at 451-2.

[22]     In other words, it must be shown that there is a genuine and substantial dispute as to the existence of the debt, and further that it would be unfair to allow that dispute to be resolved through the liquidation provisions of the Companies Act

1993 rather than by actions in the  usual  way:  Taxi  Trucks  Limited  v  Nicholson

[1989] 2 NZLR 297 and Pink Pages Publications Limited v Team Communications

Limited (1986) 3 NZCLC 99, 764.

[23]     In determining whether there is  a  genuine  and  substantial  dispute  as  to  the existence of the debt, it is not usually appropriate to resolve disputed questions of

fact on affidavit evidence alone,  particularly  when  issues  of  credibility  arise:

Androcles Investments Ltd v Highway Publications Ltd HC Christchurch M455/00,

14 February 2001 at [6]; Carpet Plus 2003 Ltd v A Team Flooring Specialist Ltd HC Auckland CIV-2008-404-4725, 19 January 2009 at [4].

[24]     To succeed in setting aside a statutory demand on the basis of a counterclaim pursuant to s 290(4)(b), the applicant has only to show a “fairly arguable basis”, and must provide some material short of proof: United Homes (1988) Ltd v Workman, Te Uenga Limited v R. Kendell & Co Limited HC Auckland M286-IM99, 11 May 1999.

[25]     In  Covington  Railways  Ltd  v  Uni-Accommodation  Ltd [2001] 1 NZLR 272 the Court of Appeal gave guidance as to what an applicant seeking to set aside a statutory demand must prove in dealing with a set-off or counterclaim (at 274-5):

“Where a company which is the subject of a liquidation application is indisputably in debt to the applicant creditor, it may nonetheless be able to show that it has a claim against  the  applicant  which  reduces  the  net  balance  owing  to  the  creditor or  even offsets it altogether. Where there are liquidated sums due each way, that is simply an arithmetical  exercise. It is more difficult if, on the applicant’s side, there is an indisputable liquidated sum, but the other party’s claim is for an unliquidated sum with liability and/or  quantum in  dispute. Then, in order to impeach the statutory demand and overcome the presumption in s287(a) that the company is unable to pay

its debts when it has failed to comply with the demand, it must be able to do more than  merely  assert  that  there  is  an  available  set-off.  It  must  be  able  to  point  to evidence before the Court showing that it has a real basis for the claimed set-off and that accordingly the applicant’s claim to be a creditor is, to the extent of the set-off, seriously in doubt. In the words of Buckley LJ in Bryanston Finance Ltd v de Vries (No.  2)  [1976] Ch 63 at p 78, it must show that there are ‘clear and persuasive grounds’ for the set-off claim. Where this can be done, the party who has issued the statutory demand against the company will be shown to be using the statutory demand and liquidation procedures improperly because there is a ‘genuine and substantial dispute about the net amount of the company’s indebtedness (Taxi Trucks Ltd  v Nicholson  [1989] 2 NZLR 297 [(CA)] at p 299. The dispute should then be resolved in the ordinary way – except as to any undisputed balance – rather than upon the hearing of a liquidation application.”

[26]     It appears that BJ Pye’s statutory  demand  here  comprises  the  sum  of

$10,538.28, which was allegedly owed on the balance of its invoices to 79 Manners and  the  sum  of  $21,608.31,  based  on  a  10%  retention  from  progress  payments pursuant  to  the  parties’  contract.  The  contract  provides  that  “10%  of  the  progress payment will be held as retentions until the entire completion of the tendered works”.

[27]     In its Notice of Opposition, BJ Pye appears to accept that there is a dispute as

to quantum, with a sum of $11,346.73 remaining in dispute. BJ Pye now appears to claim a 10% retention payment of the sum of $10,261.58 and outstanding progress payments it is said amounting to $10,538.28 for completed work. It further contends,

however,  that  there  is  no  substantial  dispute  between  the  parties  in  respect  of  this remaining sum of $20,799.86. In his affidavit, Mr Pye refers to the certification by Gill  Consultants  Limited  as  evidence  that  the  works  which  his  company  had invoiced 79 Manners  for  had in  fact been completed. Annexed to his affidavit are copies of ten progress claims for the period from June 2002 to July 2003.

[28]     In response, Mr Hawker, who is 79 Manners’ construction and project manager, contends that Gill Consultants Limited was only certifying that the work had been completed for the purpose of certifying progress payments, but that it was not certifying the sufficiency or quality of  the  works  undertaken. He says  that  79

Manners incurred significant costs as a result of BJ Pye’s failure to install the bond beam, as the beam had to be removed and stored at another location. In addition, Mr Hawker  maintains  that  the  cost  of  installing  the  beam  will  now  be  significantly greater.  It  is  said  that  the  total  amount  claimed  in  respect  of  the  inadequate  or incomplete installation of the bond beam may amount to about $100,000.00.

[29]     Mr Pye contends that it was the responsibility of 79 Manners to demolish a brick wall prior to the installation of the bond beam, but that it failed to undertake the work despite several requests from him. As time was said to be of the essence, Mr Pye alleges that 79 Manners breached the terms of the contract by delaying the completion of these works.

[30]     Mr Pye does accept that  79  Manners  requested  a  quote  for  the  demolition work, but says that he never received the letter from 79 Manners accepting the quote.

As a result of this, BJ Pye contends  it  was  unable  to  install  the  bond  beam,  and deducted the costs of the installation work from its final invoice dated 18 November

2005. It appears that later, in July 2006, BJ Pye inquired of 79 Manners whether it intended BJ Pye to remedy the work in order to complete the contract, but the parties apparently failed to reach an agreement.

[31]     In response to 79 Manners’ claim that it was forced to incur significant costs

by instructing another firm to carry out the demolition work, BJ Pye asserts that the costs of the demolition and installation work would have been significantly lower if

79 Manners had completed the demolition work – or accepted its quote -  in a timely manner. In addition, Mr Pye says that the claimed storage costs allegedly incurred by

79 Manners are unsubstantiated, and that it would not have been required to incur the storage costs if the demolition work had been completed as required.

[32]     79 Manners in turn makes the further claim that BJ Pye’s metal work on the external balconies and handrails  at  the  apartments  was  substandard  and  defective,

and that it left the building in an unsafe condition. Mr Hawker says that the cost of rectifying these problems is estimated to be between $5000 and $7000.

[33]     Mr Pye disputes the claim that the work was of substandard quality.  He says

79 Manners failed to provide a normal maintenance list despite several requests from

BJ  Pye  between  May 2005  to  May 2007.  In  addition,  Mr  Pye  says  that  no  safety issues were ever raised during the Council’s inspection of the apartments, and that in July 2008 the Council issued 79 Manners with a Code Compliance Certificate.

[34]     In my view, the applicant has done enough here to show on a fairly arguable basis that there is a substantial dispute as to the debt. Based on the affidavit evidence available to me, it is clearly disputed whether BJ Pye completed the entire tendered works and  therefore became  entitled  to  the  10%  retention  payment  of  $10,261.58. Mr  Hawker  denies  that  it  is  79  Manners  which  is  to  blame  for  the  incomplete installation  of  the  bond  beam,  and  clearly  it  is  impossible  and  inappropriate  to resolve the dispute within the context of the present application.

[35]     In addition, I conclude that 79 Manners would appear to have a counterclaim within the meaning of s 290(4)(b) if BJ Pye did fail in its obligation to install the bond beam. Since the initial quote by BJ Pye for the installation work was provided

in 2002, gas pipes and fittings and an extractor  fan  had  been  installed  behind  the columns. Because these pipes and fittings would now have to be removed prior to the demolition and installation work being commenced, the installation costs would have increased significantly. A qualified quantity surveyor has estimated the cost of carrying out the installation work to be $65,000. This contrasts with approximately

$10,000 at the time of the parties’ agreement. And it should be noted here that the Construction Contracts Act 2002 is not applicable to the present proceeding, as the contract was entered into before 1 April 2003.

[36]     Moreover,  I  accept  that  79  Manners  has  done  enough  here  to  raise  a  valid question as to whether BJ Pye’s work may have been substandard. While BJ Pye’s evidence  may  suggest  that  79  Manners’  claims  could  in  the  end  turn  out  to  be unfounded, it is not appropriate for this Court on the present application to make a finding to this effect.

[37]     It follows, therefore, that there is sufficient  doubt  whether  BJ  Pye  was entitled to the outstanding sum claimed of $20,799.86, given that it is alleged to have failed in its contractual obligations, and that the statutory demand must be set aside

on that basis.  79 Manners has been able to put before the Court enough here to show

there  is  a  genuine  and  substantial  dispute  as  to  the  debt  claimed  and  also  a  fairly arguable basis for its stated counter-claim.

Result

[38]   For the reasons outlined above, the present application succeeds.

[39]     79  Manners  submits  that  it  is  entitled  to  indemnity  costs  here  because  the statutory   demand   was   improperly   issued,   and   that   the   issue   of   the   demand constituted an abuse of the Court’s process.  No argument on costs was advanced for BJ Pye.

[40]      Under  all  the  circumstances  here,  I  am  of  the  view  that  this  is  not  one  of those  clear  situations  where  indemnity costs  are  warranted.   BJ  Pye’s  claims  may well have merit when thoroughly explored in some venue other than this companies’ Court.  79  Manners  is,  however,  entitled  to  costs  here  on  a  2B  basis  which  are awarded together with disbursements as fixed by the Registrar.

‘Associate Judge D.I. Gendall’

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

1