IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2022-404-770
[2022] NZHC 2246
IN THE MATTER OF an application to set aside a statutory
demand under section 290 of the Companies Act 1993
BETWEEN
69 GREENLANE EAST LIMITED
Applicant
AND
ORIENT CONSTRUCTION LIMITED
Respondent
Hearing: 10 August 2022 Appearances:
N Perera for Applicant
P Shanahan-Pinker for Respondent
Judgment:
5 September 2022
JUDGMENT OF ASSOCIATE JUDGE JOHNSTON
This judgment was delivered by me on 5 September 2022 at 4.00 pm, pursuant to r 11.5 of the High Court Rules
Registrar/Deputy Registrar
Introduction
[1] This is an application for an order setting aside a statutory demand. The statutory demand, dated 4 May 2022, was served on the applicant, 69 Greenlane East Ltd (Greenlane), by the respondent, Orient Construction Limited (Orient), on or about that date. Orient demanded $47,774.05 plus GST, said to be payable following service of a payment claim under the Construction Contracts Act 2002.
69 GREENLANE EAST LIMITED v ORIENT CONSTRUCTION LIMITED [2022] NZHC 2246
[5 September 2022]
[2] Greenlane’s application is made pursuant to s 290(4)(a) of the Companies Act 1993, which provides that the Court may set aside a statutory demand if satisfied that there is a substantial dispute as to whether or not the alleged debt is due.
[3] For Greenlane’s application to succeed, it must show that there is arguably a genuine and substantial dispute as to the existence of the debt.1
[4] In its originating application, Greenlane states that such a dispute exists on the following grounds:
a)The Respondent’s own records show there was no agreement for the fixed price.
b)The Applicant has never owed the Respondent the sum of [$47,774.05] plus GST; and
c)The Applicant has advised the Respondent in writing on numerous times before the Statutory Demand was issued that the debt was in dispute; and
d)The basis of the dispute is the Respondent had to submit to the Applicant a fixed price agreement as per the tender submitted and accepted on 9 September 2021;
e)The Respondent has not submitted any fixed price agreement to be executed between the Respondent and the Applicant for the construction project to commence operations despite many requests being made by the Applicant to the Respondent.
The factual background
[5] Greenlane is a property developer. Orient is a building contractor. In September 2021, Greenlane was considering a major development involving a five-storey apartment building at 69 Greenlane East, Remuera, Auckland. It approached Orient and invited it to tender for the project as the head contractor.
[6] As Mr Perera observed in the course of his submissions, matters may have progressed more smoothly had the parties elected to seek advice from their solicitors before entering into complex contractual arrangements.
1 AAI Ltd v 92 Lichfield Street Ltd (in rec and in liq) [2015] NZCA 559 at [19] and [22]; and
West Village Capital Partners Ltd v Acrow Ltd [2019] NZHC 1035.
[7] The sequence of events leading up to…
Keep reading for free
Create a free CaseChat account to read 69 Greenlane East Limited v Orient Construction Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NZHC 2246
- Decision Date
CaseChat Overview and Summary
The court held that a valid construction contract existed between the parties as at 6 December 2021. The contract was not contingent on the parties agreeing to a fixed price contract within a specified timeframe. Instead, the contract remained in effect, and Orient's 6 December 2021 payment claim was issued in accordance with the statutory requirements of the Construction Contracts Act. However, the court ruled that Orient was not entitled to issue the payment claim because the parties had agreed that Orient could only charge for work once specific milestone dates were agreed upon, which had not occurred. As a result, Orient's payment claim was void ab initio, and Greenlane demonstrated a substantial dispute regarding the debt's existence.
Accordingly, the court set aside Orient's statutory demand. Greenlane, as the successful party, was entitled to its costs on a standard basis, subject to any agreement between the parties' counsel or further submissions if necessary.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi