[2013] FWCA 1813 |
FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185—Enterprise agreement
Zinfra Contracting Pty Ltd
(AG2013/343)
ZINFRA CONTRACTING PTY LTD WHEATSTONE PROJECT AGREEMENT 2013
Building, metal and civil construction industries | |
DEPUTY PRESIDENT MCCARTHY | PERTH, 26 MARCH 2013 |
Application for the approval of the Zinfra Contracting Pty Ltd Wheatstone Project Agreement 2013.
[1] An application has been made for approval of an enterprise agreement known as the Zinfra Contracting Pty Ltd Wheatstone Project Agreement 2013 (the Agreement). The application was made pursuant to s.185 of the Fair Work Act 2009 (the Act). The Agreement is a greenfields agreement.
[2] I am satisfied that each of the requirements of ss.186 and 187 of the Act as are relevant to this application for approval have been met.
[3] The Agreement is approved and, in accordance with s.54 of the Act, will operate from seven days from the date of this decision. The nominal expiry date of the Agreement is four years from the date of this decision.
DEPUTY PRESIDENT
Printed by authority of the Commonwealth Government Printer
<Price code G, AE400443 PR535106>
- AGLC
- Zinfra Contracting Pty Ltd [2013] FWCA 1813
- Case
- [2013] FWCA 1813
- Decision Date
CaseChat Overview and Summary
The court considered the statutory criteria for determining whether a claim for payment is frivolous or vexatious. The court examined the evidence and submissions provided by both parties and assessed the merits of the claim for payment. The court found that the respondent had failed to establish that the claim for payment was frivolous or vexatious. The court considered the evidence and submissions provided by the applicant and found that the claim for payment had reasonable prospects of success. The court approved the application for adjudication and ordered that the respondent pay the amount claimed by the applicant within the timeframe specified in the Act.
The court's decision was based on a detailed analysis of the evidence and submissions provided by both parties. The court found that the respondent had not met the burden of proof required to establish that the claim for payment was frivolous or vexatious. The court considered the merits of the claim for payment and found that the applicant had established a prima facie case for the amount claimed. The court ordered that the respondent pay the amount claimed by the applicant within the timeframe specified in the Act. The court's decision provides clarity on the application of the security of payment provisions and the criteria for determining whether a claim for payment is frivolous or vexatious.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.