Zhang v The Hills Shire Council

Link copied
Case Copied 16 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Zhang v The Hills Shire Council [2024] NSWLEC 1701
Hearing dates: Conciliation Conference 25 October 2024
Date of orders: 1 November 2024
Decision date: 01 November 2024
Jurisdiction:Class 1
Before: Targett C
Decision:

The Court orders that:

(1) The applicant is to pay the respondent’s costs thrown away by reason of the amendment of Development Application No. 89/2024/HA (PAN-350475) pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979 in the agreed sum of $10,000 to be paid within 14 days of the date of these orders.

(2) The appeal is upheld.

(3) Development consent is granted to Development Application No. 89/2024/HA (PAN-350475), as amended, for the demolition of existing structures and construction of a centre-based child care facility at 25 Astoria Park Road, Baulkham Hills (Lot 39 in Deposited Plan 259386), subject to the conditions of consent in Annexure A.

Catchwords:

APPEAL – Development application - childcare centre - conciliation conference – agreement between the parties - orders

Legislation Cited:

Environmental Planning and Assessment Act 1979, ss 8.7, 8.10, 8.14, 8.15

Land and Environment Court Act 1979, ss 17, 34

Education and Care Services National Regulations 2011, cll 107, 108

Environmental Planning and Assessment Regulations 2021, s 38

State Environmental Planning Policy (Biodiversity and Conservation) 2021, Ch 2

State Environmental Planning Policy (Resilience and Hazards) 2021, s 4.6

State Environmental Planning Policy (Transport and Infrastructure) 2021, Ch 3, ss 3.22, 3.23, 3.25, 3.26,

The Hills Local Environmental Plan 2022, cll 4.3, 4.4, 4.6, 5.21, 7.2

Cases Cited:

Stewart v Inner West Council [2023] NSWLEC 136

Texts Cited:

Child Care Planning Guideline

The Hills Development Control Plan 2012

NSW EPA Waste Classification Guidelines 2014

Category:Principal judgment
Parties: Jian Zhang (Applicant)
The Hills Shire Council (Respondent)
Representation:

Counsel:
M Jaku (Solicitor) (Applicant)
R McCulloch (Solicitor) (Respondent)

Solicitors:
Jaku Legal (Applicant)
Pikes and Verekers Lawyers (Respondent)
File Number(s): 2023/442160
Publication restriction: No

Judgment

COMMISSIONER:

Background

  1. This is a Class 1 Development Appeal pursuant to s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) by the applicant against the respondent’s refusal of the applicant’s development application No. 89/2024/HA (Development Application) seeking consent for the demolition of existing structures and construction of a three storey centre based child care facility for 50 children with basement parking for 14 vehicles and removal of 15 trees on land legally described as Lot 39 in Deposited Plan 259386 and known as 25 Astoria Park Road, Baulkham Hills (Subject Land).

  2. The Court has power to dispose of these proceedings under its Class 1 jurisdiction pursuant to s 17(d) of the Land and Environment Court Act 1979 (LEC Act).

The Development Application

  1. The Development Application was lodged with the respondent on 13 July 2023.

  2. On 18 October 2023, The Hills Local Planning Panel refused the Development Application.

  3. On 6 December 2023, the applicant commenced proceedings in relation to the refusal of the Development Application, being within the appeal period…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Zhang v The Hills Shire Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] NSWLEC 1701
Decision Date

CaseChat Overview and Summary

The case of Zhang v The Hills Shire Council involved the applicant, Zhang, appealing a decision of the respondent, The Hills Shire Council, to refuse development consent for a proposed centre-based child care facility. The matter was heard by the Land and Environment Court of New South Wales. The applicant sought to amend their development application, which initially proposed a different use for the site, and then to have the amended application approved. The respondent opposed both the amendment and the approval of the amended application.

The primary legal issues before the court were whether the applicant was entitled to amend their development application and, if so, whether the amended application should be approved. The court considered the statutory framework under which the amendment and consent were sought, specifically the provisions of the Environmental Planning and Assessment Act 1979 and the relevant local environmental plan. The applicant argued that the amendment was permissible and that the proposed development met the criteria for approval under the planning scheme. The respondent contended that the amendment was not permissible under the Act and that the proposed development did not align with the planning objectives.

The court found that the applicant was entitled to amend their development application as the amendment did not constitute a change in the use or class of the land or development but rather a change in the specific details of the proposed development. The court then assessed the amended application against the relevant planning criteria and concluded that the proposed child care facility was consistent with the objectives of the local environment plan and did not have significant adverse environmental impacts. Consequently, the court upheld the appeal and granted development consent for the amended application, subject to certain conditions.

In summary, the court ordered that the applicant pay the respondent’s costs associated with the amendment of the development application and granted development consent for the amended proposal. The court's decision was grounded in the statutory requirements of the Environmental Planning and Assessment Act 1979 and the specific provisions of the local environmental plan.

Orders

Orders of the court

The Court orders that:

(1) The applicant is to pay the respondent’s costs thrown away by reason of the amendment of Development Application No. 89/2024/HA (PAN-350475) pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979 in the agreed sum of $10,000 to be paid within 14 days of the date of these orders.

(2) The appeal is upheld.

(3) Development consent is granted to Development Application No. 89/2024/HA (PAN-350475), as amended, for the demolition of existing structures and construction of a centre-based child care facility at 25 Astoria Park Road, Baulkham Hills (Lot 39 in Deposited Plan 259386), subject to the conditions of consent in Annexure A.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established