Z R International Holding Pty Ltd v Canterbury Bankstown Council

Case

[2017] NSWLEC 1472

31 August 2017

No judgment structure available for this case.

Land and Environment Court


New South Wales

Medium Neutral Citation: Z R International Holding Pty Ltd v Canterbury Bankstown Council [2017] NSWLEC 1472
Hearing dates: Conciliation conference on 28 July 2017
Date of orders: 31 August 2017
Decision date: 31 August 2017
Jurisdiction:Class 1
Before: Dickson C
Decision:

See [5] below

Catchwords: DEVELOPMENT APPEAL under s97(1) against refusal of a modification application for a residential flat building - amended design- agreement between the parties - orders
Legislation Cited: Land and Environment Court Act 1979
Environmental Planning and Assessment Act 1979
Category:Principal judgment
Parties: Z R International Holding Pty Ltd (Applicant)
Canterbury Bankstown Council (Respondent)
Representation: Solicitors:
Mills Oakley (Applicant)
Marsdens Law Group (Respondent)
File Number(s): 2017/00060170
Publication restriction: No

Judgment

  1. COMMISSIONER: This is an appeal, under s96(2) of the Environmental Planning and Assessment Act 1979, against Council’s refusal of development application number DA-165/2012/C. The application seeks approval for the modification of the consent to modify the unit layouts, increase the number of units and the unit mix with subsequent amendments to the building façade and basement car park. The development is proposed at 6 Broughton Street, Canterbury.

  2. In this matter, at or after a conciliation conference, an agreement under s 34(3) of the Land and Environment Court Act 1979 (the Court Act) was reached between the parties as to the terms of a decision in the proceedings that was acceptable to the parties. As the presiding Commissioner, I was satisfied that the decision was one that the Court could have made in the proper exercise of its functions (this being the test applied by s 34(3) of the Court Act). As a consequence, s 34(3)(a) of the Act required me to “dispose of the proceedings in accordance with the decision”.

  3. The Court Act also required me to “set out in writing the terms of the decision” (s 34(3)(b)). The orders made to give effect to the agreement constitute that document.

  4. In making the orders to give effect to the agreement between the parties, I was not required to, and have not, made any merit assessment of the issues that were originally in dispute between the parties.

  5. The final orders to give effect to the parties’ agreement are:

  1. Leave is granted to substitute the following plans for the plans and documents that are the subject of Modification Application No. DA-165/2012/C:

Drawing No.

Name

Revision

Drawn By

Date

S96000

Cover Sheet

C

CD Architects

8 August 2017

S96001

Compliance Sheet

C

CD Architects

8 August 2017

S96002

Site Plan

C

CD Architects

8 August 2017

S96003

Site Plan and Site Analysis

B

CD Architects

20 June 2017

S96100

Lower Basement Floor Plan

C

CD Architects

8 August 2017

S96101

Upper Basement Floor Plan

C

CD Architects

8 August 2017

S96102

Ground Floor Plan

C

CD Architects

8 August 2017

S96103

Level 01 Floor Plan

C

CD Architects

8 August 2017

S96104

Level 02 Floor Plan

C

CD Architects

8 August 2017

S96105

Level 03 Floor Plan

C

CD Architects

8 August 2017

S96106

Level 04 Floor Plan

C

CD Architects

8 August 2017

S96107

Level 05 Floor Plan

C

CD Architects

8 August 2017

S96108

Roof Level Plan

C

CD Architects

8 August 2017

S96200

East & West Elevations

C

CD Architects

8 August 2017

S96201

North & South Elevations

C

CD Architects

8 August 2017

S96300

Sections

C

CD Architects

8 August 2017

S96301

Sections

C

CD Architects

8 August 2017

S96500

Pre + Post adaptable unit layout

B

CD Architects

20 June 2017

S96600

Shadow Diagrams

C

CD Architects

8 August 2017

S96601

Shadow Diagrams

C

CD Architects

8 August 2017

S96602

Shadow Diagrams

C

CD Architects

8 August 2017

S96603

Solar Access to Common Open Space – 9AM – 11AM

B

CD Architects

8 August 2017

S96604

Solar Access to Common Open Space – 12PM & 1PM

B

CD Architects

8 August 2017

S96605

Solar Access to Common Open Space – 2PM & 3PM

B

CD Architects

8 August 2017

S96700

GFA Calculation

C

CD Architects

8 August 2017

S96701

GFA Calculation Approved DA

A

CD Architects

20 June 2017

S96702

Solar Access Plan

C

CD Architects

8 August 2017

S96702-1

Solar Study Unit 504 – Sheet 1

A

CD Architects

8 August 2017

S96702-2

Solar Study Unit 504 – Sheet 2

A

CD Architects

8 August 2017

S96703

Ventilation Diagrams

B

CD Architects

8 August 2017

S96704

3D Views

B

CD Architects

8 August 2017

S96707

Common Open Space

A

CD Architects

20 June 2017

S96708

Approved DA – Common Open Space

A

CD Architects

20 June 2017

S96710

Photomontage

A

CD Architects

July 2016

S96730

Finishes Schedule

A

CD Architects

July 2016

S96740

Sun View at 9am

B

CD Architects

8 August 2017

S96741

Sun View at 10am

B

CD Architects

8 August 2017

S96741-1

Sun View at 10:30

A

CD Architects

8 August 2017

S96742

Sun View at 11am

B

CD Architects

8 August 2017

S96742-1

Sun View at 11:30am

A

CD Architects

8 August 2017

S96743

Sun View at 12pm

B

CD Architects

8 August 2017

S96743-1

Sun View at 12:30pm

A

CD Architects

8 August 2017

S96744

Sun View at 1pm

B

CD Architects

8 August 2017

S96745

Sun View at 2pm

B

CD Architects

8 August 2017

S96746

Sun View at 3pm

B

CD Architects

8 August 2017

S0100

Shoring and Bulk Excavation Plan and Details

H

Australian Consulting Engineers

8 August 2017

S0101

Shoring Elevations

D

Australian Consulting Engineers

7 August 2017

S0102

Shoring Details

E

Australian Consulting Engineers

7 August 2017

S0200

Footing Plan and Details

B

Australian Consulting Engineers

8 August 2017

S0300

Basement B2 Slab Plan Sections and Details

C

Australian Consulting Engineers

8 August 2017

S0400

Basement B1 Slab Plan Sections and Details

C

Australian Consulting Engineers

8 August 2017

S0500

Ground Floor Slab Plan Sections and Details

D

Australian Consulting Engineers

8 August 2017

Document reference

Document Name

Prepared by

Dated

735964M_03

BASIX Certificate

Outsource Ideas P/l

8 August 2017

GS6246-2A

Addendum Geotechnical Investigation Report

Aargus

8 August 2017

16350

Letter regarding Basement Car Parking Layout

Varga Traffic Planning

8 August 2017

  1. The appeal is upheld;

  2. Modification Application No. DA-165/2012/C to modify Development Consent No. DA-165/2012 (as modified) for the construction of a 6 storey residential flat building containing 28 units (1x studio, 4x 1 bedroom, 21x 2 bedroom and 2x3 bedroom units) over 2 levels of basement car parking containing 41 car parking spaces at Lot 5 DP 828270 (6 Brought on Street, Canterbury), by amending unit layouts and increasing the number of units to 32, changing the unit mix to 4 x 1 bedroom and 22 x 2 bedroom units and 6 x 3 bedroom units, amending the layout of the basement car park and increasing the number of car parking spaces to 49, and adjusting the facade, is determined by approving the modification as set out in Annexure "A"

  3. As a consequence of order (3), Development Consent No. DA-165/2012 is subject to the consolidated, modified conditions of consent as set out in Annexure "B".

…………….

D M Dickson

Commissioner of the Court

60170.17 Dickson (C) Annexure A (159 KB, pdf)

60170.17 Dickson (C) Annexure B (247 KB, pdf)

60170.17 Dickson - Plans (6.51 MB, pdf)

Decision last updated: 31 August 2017

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

2