Supreme Court
New South Wales
Medium Neutral Citation: Wyong Shire Council v Jenbuild [2012] NSWSC 720 Hearing dates: 19/06/2012 Decision date: 19 June 2012 Jurisdiction: Equity Division - Commercial List Before: McDougall J Decision: Summons dismissed with costs.
Catchwords: [COMMERCIAL ARBITRATION] - contracts - whether contracts made between the plaintiff and the first defendant constitute a valid arbitration agreement for the purposes of s 7 of the Commercial Arbitration Act 2010 (NSW) - whether contract ancillary to the principal contracts governed the dispute resolution process.
[ESTOPPEL] - estoppel in pais - convention; estoppel by - whether sufficient detriment that parties are estopped from denying their contractual relationship is governed by a dispute resolution clause.Legislation Cited: Commercial Arbitration Act 2010 (NSW) Cases Cited: Moratic Pty Ltd v Lawrence James Gordan & Anor [2007] NSWSC 5
Noon v Bondi Beach Astra Retirement Village Pty Ltd [2010] NSWCA 202Category: Principal judgment Parties: Wyong Shire Council (Plaintiff)
Jenbuild Pty Limited (First Defendant)Representation: Counsel:
F C Corsaro SC (Plaintiff)
I G Roberts SC (Defendant)
Solicitors:
HWL Ebsworth (Plaintiff)
Herbert Geer (Defendant)
File Number(s): 2012/134485
Judgment
HIS HONOUR: The question for decision is whether, in four contracts made between the plaintiff (the Council) and the first defendant (Jenbuild), there is a valid arbitration agreement for the purposes of s 7 of the Commercial Arbitration Act 2010 (NSW) (the Act).
The contracts
On 10 March 2008, some four contracts were made between the Council and Jenbuild. Each contract related to a particular holiday park within the control of the Council. Each called for Jenbuild to perform what were, in effect, works upgrading and improving the facilities at the subject park.
In the usual manner of things, each contract was constituted by a multitude of documents. Those documents included (but by no means are limited to) the general conditions of contract AS2124-1992. They also included what purported to be the annexure part A to those general conditions of contract, completed to make provision for the various alternatives and choices for which the general conditions from time to time provide. In each case, the completed annexure part A was part of the request for tender documents and hence, by definition, part of the contract documents.
Although the provisions of the general conditions of contract are well known, it will be helpful to set them out so far as they are relevant.
The principal source of dispute arises from cl 47, which deals with dispute
resolution. By cl 47.1, any dispute is to be the subject of a notice of dispute. However, according to cl 47.2, there are further steps to be taken before proceedings, by way of arbitration or litigation, can be commenced in relation to the dispute the subject of the notice. Clause 47.2 provides for two alternatives. The first requires the parties to confer either to resolve the dispute or to explore its resolution by other means. If those attempts to fail, the dispute can be referred to arbitration or litigation.
Alternative 2 takes…
Keep reading for free
Create a free CaseChat account to read Wyong Shire Council v Jenbuild and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] NSWSC 720
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the contracts between the parties constituted a valid arbitration agreement under section 7 of the Commercial Arbitration Act 2010 (NSW). Additionally, the court had to determine if a contract ancillary to the principal contracts governed the dispute resolution process. The defendants argued that the contracts did not provide for arbitration and that any dispute resolution clause was not binding due to the absence of sufficient detriment to apply estoppel.
The court found that the contracts did indeed constitute a valid arbitration agreement as they clearly outlined the dispute resolution process. It ruled that the ancillary contract, which contained the arbitration clause, was binding and enforceable. The court also determined that the parties were estopped from denying their contractual relationship as governed by the dispute resolution clause, as the plaintiff had suffered sufficient detriment. The court held that the arbitration clause was valid and enforceable, and the dispute should be resolved through arbitration.
The final orders included a declaration that the arbitration agreement was valid and enforceable, and the court directed the parties to proceed with arbitration in accordance with the terms of the contracts.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.