DISTRICT COURT OF SOUTH AUSTRALIA
(Civil)
WUNDA PROJECTS AUSTRALIA P/L v KYREN P/L
[2010] SADC 96
Judgment of His Honour Judge Herriman
29 July 2010
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - PERFORMANCE OF WORK - REMEDIES FOR BREACH OF CONTRACT - DAMAGES - OTHER MATTERS
Construction of city apartment building – principal removes works from contractor - contractor’s claim against principal for unpaid works, variations and lost profit based upon principal's unlawful repudiation of AS 2124 contract – principal’s cross claim for breach of contract, costs of completion and liquidated damages – disputes over variations of terms, construction program, superintendence, delay, time extensions, variation claims, notices to show cause, works removed from contract, termination of contract - assessment of damages and interest – consideration of prevention principle. Judgment for plaintiff and cross claim dismissed.
Trade Practices Act 1974 (Cth) s 52, referred to.
FPM Constructions v Council of the City of Blue Mountains [2005] NSWCA 340; Dixon v The South Australian Railways Commissioner (1923) 34 CLR 71; Perini Corporation v Commonwealth [1969] 2 NSWR 530; Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd (2002) 18 BCL 322; Roberts v Bury Commissioners (1870) LR 5 CP 310; Ottawa Northern and Western Railway Co. v Dominion Bridge Co. (1905) 36 SCR 347; SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] VR 391; Peak Construction (Liverpool) Ltd v McKinney Foundation Ltd (1970) 1 BLR 111; Multiplex Constructions (UK) v Honeywell Control Systems [2007] BLR 195; Kane Constructions Pty Ltd v Sopov (2006) 22 BCL 92; McAlpine Humberoak Ltd v McDermott International Inc (No 1) (1992) 58 BLR 1; 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491; Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 63 ALJR 37, applied.
Turner Corporation (In Provisional Liquidation) v Co-Ordinated Industries Pty Ltd & Ors (1995) 11 BCL 202; Gaymark Investments Pty Ltd v Walter Construction Group Pty Ltd (2000) 16 BCL 449, not followed.
Turner Corporation Limited (Receiver and Manager Appointed) v Austotel Pty Ltd (1997) 13 BCL 378, considered.
WUNDA PROJECTS AUSTRALIA P/L v KYREN P/L
[2010] SADC 96CONTENTS
A. Introduction
B. General Observations
C. Observations as to Witnesses
D. The Issues
1. The Contract
2. Variation of Contract Terms
3. Construction Programs
4. The Superintendent
5. Minutes of Site Meetings
6. The Progress of Works
7. Asserted Causes of Delay
8. Liquidated Damages and the Prevention Principle
9. Extensions of Time
10. Variation Claims
11. The Notices to Show Cause
12. Termination of the Contract
13. Actions Taken by Kyren after Termination
14. Wunda’s Profit Margin
15. Works Removed from the Contract
E. Summary and Damages
F. The Cross Action
G..... Conclusion......................................................................................................... 150
A. Introduction
In June 2006 the plaintiff, Wunda Projects Australia Pty Ltd (‘Wunda’), a building contractor, contracted with the defendant, Kyren Pty Ltd (‘Kyren’), to carry out certain internal finishing works on a multistorey apartment building being constructed by Kyren on…
Keep reading for free
Create a free CaseChat account to read Wunda Projects Australia P/L v Kyren P/L and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] SADC 96
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court encompassed whether the principal had effectively repudiated the contract, thereby justifying the contractor’s claim for lost profit and variations. Additionally, the court had to determine whether the principal's cross claim for breach of contract and associated costs was valid. Another key issue was the calculation of damages and interest in light of the prevention principle, which may limit the contractor’s recovery for losses that could have been avoided by reasonable efforts.
The court found that the principal had indeed repudiated the contract, thereby justifying the contractor’s claim for lost profit and variations. The court held that the principal's cross claim was unsubstantiated and dismissed it. In assessing damages and interest, the court applied the prevention principle, which resulted in a reduction of the contractor's claim for losses that could have been reasonably mitigated. The judgment ultimately favoured the contractor, awarding damages for the unpaid works, variations, and lost profit while dismissing the principal’s cross claim. The court also directed the parties to resolve outstanding issues through mediation.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.