FEDERAL MAGISTRATES COURT OF AUSTRALIA

WOTHERSPOON v CFMEU & ORS [2010] FMCA 184
INDUSTRIAL LAW – Penalties for unlawful industrial action – whether within permissible range.
Building and Construction Industry and Improvement Act 2005, ss.37, 38, 49, 59, 69
Federal Magistrates Court Rules 2001, r.15.03
Crimes Act 1914 (Cth), s.4AA
Veen v The Queen (No 2) (1988) 164 CLR 465
CFMEU v Coal and Allied Operation (No 2) (1999) 94 IR 231
Applicant: JOHN MARK WOTHERSPOON
First Respondent: CONSTRUCTION, FORESTRY, MINING, & ENERGY UNION
Second Respondent: GARETH STEPHENSON
Third Respondent: HAROLD IAN SLATER
File Number: MLG 575 of 2009
Judgment of: Turner FM
Hearing date: 10 February 2010
Date of Last Submission: 10 February 2010
Delivered at: Melbourne
Delivered on: 22 March 2010

REPRESENTATION

Counsel for the Applicant: Mr Snaden
Solicitors for the Applicant: Freehills
Counsel for the Respondents: Mr Bandt
Solicitors for the Respondents: CFMEU

ORDERS

  1. That the penalties agreed between the parties are within the permissible range.

  2. That a penalty of $25,000.00 be imposed on the CFMEU for its contravention of s.38 of the Building and Construction Industry and Improvement Act 2005 (“the BCII Act”) on 30 April 2008;

  3. That a penalty of $5,000.00 be imposed on the second Respondent Stephenson for his of contravention of s.38 of the BCII Act on 30 April 2008;

  4. That a penalty of $1,000.00 be imposed on the third respondent Slater (wholly suspended for a period of 12 months from the date it is imposed, such that it shall only become payable in the event that he is declared, by a Court, to have contravened the BCII Act, or a Court imposes another penalty upon him on account of such a contravention in relation to conduct engaged in within that period) for his contravention of s.38 of the BCII Act on 30 April 2008; and

  5. That the penalties imposed on the first, second and third respondents be paid into the Consolidated Revenue Fund.

  6. That the Respondent within 28 days of 10 February 2010 pay the Applicant’s costs fixed at $4,400.00.

FEDERAL MAGISTRATES
COURT OF AUSTRALIA AT
MELBOURNE

MLG 575 of 2009

JOHN MARK WOTHERSPOON

Applicant

And

CONSTRUCTION, FORESTRY, MINING, & ENERGY UNION

First Respondent

GARETH STEPHENSON

Second Respondent

HAROLD IAN SLATER

Third Respondent

REASONS FOR JUDGMENT

  1. This matter involves an application by John Wotherspoon (an inspector appointed pursuant to s.59 of the Building and Construction Industry and Improvement Act 2005 (“the BCII Act”) against the Construction, Forestry, Mining and Energy Union (“the CFMEU”), and Gareth Stephenson (“Stephenson”) an employee and officer of the CFMEU and Harold Slater (“Slater”) a member of the CFMEU and an employee of Fulton Hogan Pty Ltd (“FHPL”).

  2. The Application alleges that FHPL is a constitutional corporation that was at all relevant times engaged in widening the Monash Freeway.

  3. The Application alleges that the respondents engaged in meetings and stoppages on an FHPL site on 30 April 2008 as a result which, employees of FHPL and others withdrew their labour and failed to perform their work…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Wotherspoon v CFMEU and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2010] FMCA 184
Decision Date

CaseChat Overview and Summary

Wotherspoon v CFMEU is a case before the Supreme Court of New South Wales. The dispute involves the applicant, Wotherspoon, who seeks penalties against the Construction, Forestry, Maritime, Mining and Energy Union (CFMEU), and two of its officials, Stephenson and Slater, for breaches of section 38 of the Building and Construction Industry and Improvement Act 2005. The specific incident giving rise to the case occurred on 30 April 2008, where the respondents were found to have contravened the Act.

The court was required to determine several legal issues, including whether the penalties proposed by the parties fell within the permissible range under the BCII Act, and if so, whether they should be confirmed by the court. Additionally, the court needed to decide if the respondents had indeed breached section 38 of the BCII Act, and if so, what the appropriate penalties should be. The court also had to consider whether the penalties imposed were proportionate to the breaches committed.

The court found that the penalties agreed upon by the parties were within the permissible range. It confirmed the penalties of $25,000.00 for the CFMEU, $5,000.00 for Stephenson, and a wholly suspended penalty of $1,000.00 for Slater, with the latter only becoming payable if Slater was found to have contravened the Act again within the specified period. The court emphasised the importance of deterrence and compliance with the BCII Act and ruled that the penalties imposed should be paid into the Consolidated Revenue Fund. Lastly, the court ordered the respondent to pay the applicant's costs of $4,400.00 within 28 days of the judgment date.

Orders

Orders of the court

1.

That the penalties agreed between the parties are within the permissible range.

2.

That a penalty of $25,000.00 be imposed on the CFMEU for its contravention of s.38 of the Building and Construction Industry and Improvement Act 2005 (“the BCII Act”) on 30 April 2008;

3.

That a penalty of $5,000.00 be imposed on the second Respondent Stephenson for his of contravention of s.38 of the BCII Act on 30 April 2008;

4.

That a penalty of $1,000.00 be imposed on the third respondent Slater (wholly suspended for a period of 12 months from the date it is imposed, such that it shall only become payable in the event that he is declared, by a Court, to have contravened the BCII Act, or a Court imposes another penalty upon him on account of such a contravention in relation to conduct engaged in within that period) for his contravention of s.38 of the BCII Act on 30 April 2008; and

5.

That the penalties imposed on the first, second and third respondents be paid into the Consolidated Revenue Fund.

6.

That the Respondent within 28 days of 10 February 2010 pay the Applicant’s costs fixed at $4,400.00.