Wooli River Harbour Works Act 1967 (NSW)

Case
No judgment structure available for this case.

WOOLI RIVER HARBOUR WORKS ACT.

ANNO SEXTO DECIMO

ELIZABETHE II REGINE

Act No. 74, 1967.

An Act to sanction and to provide for the carrying out of works for the Wooli River Harbour ; and for purposes connected therewith. [Assented to, 7th December, 1967.]

Works Act, 1967".
BE it enacted by the Queen's Most Excellent Majesty, by
and with the advice and consent of the Legislative
Council and Legislative Assembly of New South Wales in
Parliament assembled, and by the authority of the same, as
follows: —

1. This Act may be cited as the "Wooli River Harbour

2. (1) (a) The carrying out of the work described in the Schedule to this Act is hereby sanctioned.

(b) The said work shall be deemed to be an authorised work within the meaning of the Public Works Act, 1912, as amended by subsequent Acts.

(c) The Minister for Public Works is empowered to carry out the said work and shall be the Constructing Authority for the same within the meaning of the said Act, as so amended, and shall enter into such contracts and take all such necessary steps for the proper execution thereof as such Authority may think proper.

(d) The provisions of the Public Works Act, 1912, as amended by subsequent Acts, sections thirty-four, thirty-five, thirty-six and thirty-seven excepted, shall apply to and in respect of the said work.

(2) Without prejudice to the generality of subsection one of this section the provisions of section thirty-eight of the Public Works Act, 1912, as amended by subsequent Acts, shall apply to and in respect of any contracts referred to in paragraph (c) of subsection one of this section.

The plan of the said work is the plan marked "Wooli River Entrance Improvement" signed by the Minister for Public Works and countersigned by the Director of Public

3.

Works and deposited in the public office of the said Minister. 4. The cost of carrying out the said work (exclusive of land resumptions) is estimated at six hundred and eighty-one thousand dollars and such estimated cost shall not, under any circumstances, be exceeded by more than ten per centum.

SCHEDULE.

SCHEDULE.

(1) Works for the Wooli River Harbour comprising:—

(a)

The construction of a breakwater on the northern side of the Wooli River entrance extending in a north-easterly direction a distance of approximately one thousand one hundred and nineteen feet from the existing foreshore.

(b)

The construction of a breakwater on the southern side of the Wooli River entrance extending in a north-easterly direction a distance of approximately six hundred and twenty-four feet from the existing foreshore.

(c)

The construction of two associated training walls on the southern side of the Wooli River and its entrance, having a combined length of approximately one thousand one hundred and twenty feet.

(d)

Other associated works as may be deemed necessary or desirable by the Constructing Authority.

( 2 ) The whole of the works hereinbefore described to be subject

to such modifications as may be deemed necessary or desirable by

the Constructing Authority.