Reported Decision: 138LGERA 165
Land and Environment Court
of New South Wales
CITATION: Williams v Director-General Department Environment and Conservation and Ors. [2005] NSWLEC 165
PARTIES: APPLICANT:
WilliamsRESPONDENTS:
Director-General Department Environment and Conservation and Ors.FILE NUMBER(S): 40251 of 2005
CORAM: Bignold J
KEY ISSUES: Injunctions and Declarations :- Aboriginal objects-Permit consent granted in respect of Aboriginal objects-challenge to validity on administrative law and other legal issues
CASES CITED: Minister for Aboriginal Affairs v Peko Wallsend Ltd (1986) 162 CLR 24;
Stocklands (Constructions) Pty Ltd v Carriage (2002) 56 NSWLR 636;
Weal v Bathurst City Council (2000) 111 LGERA 181;
Williams v County Energy [2004] NSWLEC 613;
Williams v Director-General National Parks and Wildlife Service (2003) 127LGERA 354;
Williams v the Director General National Parks and Wildlife Service [2002] NSWLEC 154DATES OF HEARING: 04/04/2005
DATE OF JUDGMENT:
04/05/2005LEGAL REPRESENTATIVES: APPLICANT:
Mr A Oshlack, Agent
SOLICITORS
N/AFIRST RESPONDENT:
Mr A Galasso, Barrister
2ND TO 4TH RESPONDENTS:
Mr N Williams SCSOLICITORS
FIRST RESPONDENT:
Solicitor for Department of Environment2ND TO 3RD RESPONDENTS:
Blake Dawson Waldron
JUDGMENT:
THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
BIGNOLD J
5 April 2005
JUDGMENT40251 of 2005 NEVILLE WILLIAMS v DIRECTOR-GENERAL DEPARTMENT OF ENVIRONMENT AND CONSERVATION; COUNTRY ENERGY; COLIN PARDOE; SCOTT CANE
: HIS HONOUR
1 By class 4 application filed on 23 March 2005 the Applicant claims declaratory and consequential injunctive belief in relation to the grant by the first Respondent, the Director-General of the Department of Environment and Conservation, of a consent under s 90 of the National Parks and Wildlife Act 1974 and a related permit issued under s 87 of that Act, on 16 March 2005 in relation to Aboriginal objects located within the boundaries of an electricity transmission line proposed from the town of Temora to service the approved Gold Mine at Lake Cowal.
2 By Motion filed the next day the Applicant claimed an urgent order restraining the fourth Respondent, Dr Cane, one of the archaeologists to whom the s 87 permit was jointly issued, from carrying out any activity as set out in par 9 of the originating process, and an order against the second Respondent, Country Energy, restraining it on an interlocutory basis from carrying out work as set forth in par 10 of the originating process.
3 When the claim for interlocutory relief came before me last Friday the parties agreed that in the circumstances of the case, having regard to the nature of the claims made and the Respondents’ attitude to those claims (which was to resist all claims and deny all bases of liability) that it would be a more efficient use of resources for the claim to final relief to be heard in lieu of the hearing of the claim to interlocutory relief. On the face of it that proposition was somewhat surprising, but as was explained and agreed by all parties to the litigation it was commonly agreed that the hearing of the claims…
Keep reading for free
Create a free CaseChat account to read Williams v Director-General Department Environment and Conse... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] NSWLEC 165
- Decision Date
CaseChat Overview and Summary
The court heard arguments from both sides and considered extensive documentary evidence, including affidavits from the applicant and two consultant archaeologists. The key issues revolved around the validity of the consent and permit under the National Parks and Wildlife Act 1974 and the associated regulations. The court examined several grounds for invalidity, including the timeliness of the consent decision, the amendment of the permit application, the property status of the Aboriginal objects, the Director-General's adherence to statutory objects, the fulfilment of legitimate expectations, the application of natural justice, the consideration of relevant matters, and the reasonableness of the decision.
Bignold J dismissed the application, finding that none of the grounds for invalidity had been substantiated. The court held that the Director-General's power to grant consent was not temporally limited by the regulatory provisions, that the amendment of the permit application did not invalidate it, and that the Aboriginal objects were property of the Crown. The court also rejected claims regarding breaches of statutory duties, disappointment of legitimate expectations, denial of natural justice, failure to consider relevant matters, and manifest unreasonableness of the decision. The court concluded that the decision to issue the permit and consent was not infected by any error of fact and was within the statutory powers conferred upon the Director-General. Consequently, the application was dismissed, and the consent and permit were upheld as valid.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.