FEDERAL COURT OF AUSTRALIA
Williams v Automotive, Food, Metals, Engineering, Printing Kindred Industries Union [2009] FCA 86
ANDREW WILLIAMS v AUTOMOTIVE, FOOD, METALS, ENGINEERING, PRINTING KINDRED INDUSTRIES UNION, CONSTRUCTION FORESTRY ENERGY AND MINING UNION and MICK POWELL
VID 83 of 2009
JESSUP J
6 FEBRUARY 2009
MELBOURNE
IN THE FEDERAL COURT OF AUSTRALIA
VICTORIA DISTRICT REGISTRY
VID 83 of 2009
BETWEEN: ANDREW WILLIAMS
ApplicantAND: AUTOMOTIVE, FOOD, METALS, ENGINEERING, PRINTING KINDRED INDUSTRIES UNION
First RespondentCONSTRUCTION FORESTRY ENERGY AND MINING UNION
Second RespondentMICK POWELL
Third Respondent
JUDGE:
JESSUP J
DATE OF ORDER:
6 FEBRUARY 2009
WHERE MADE:
MELBOURNE
THE COURT ORDERS THAT:
1.Until 4:30pm on 12 February 2009, the respondents be restrained, whether by themselves, their servants or agents, from:
(a)preventing or hindering the access of any person or vehicle to the Hyde Street Depot site of the West Gate Bridge Strengthening Alliance Project at Hyde Street, Spotswood;
(b)counselling or procuring any person not to enter the said site;
(c)counselling or procuring any employee or agent of, or person contracted to, John Holland Pty Ltd or Civil Pacific Services (Vic) Pty Ltd, not to work upon the said site;
(d)placing or leaving any vehicle, trailer, apparatus, equipment or thing within 100 metres of any entrance to the said site; and
(e)attending, or organising or procuring any person or persons to attend, within 100 metres of any entrance to the said site, save for such entry to the site as may be authorised by law, for the purpose of using a public road for reasons unconnected with the said site or for the purpose of complying with these orders.
- The further hearing of the applicant’s claim for interim relief be adjourned to 10.15am on 12 February 2009.
- Each party have liberty to apply on two hours’ written notice to each other party.
- Costs be reserved.
Note:Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.
The text of entered orders can be located using eSearch on the Court’s website.
IN THE FEDERAL COURT OF AUSTRALIA
VICTORIA DISTRICT REGISTRY
VID 83 of 2009
BETWEEN: ANDREW WILLIAMS
ApplicantAND: AUTOMOTIVE, FOOD, METALS, ENGINEERING, PRINTING KINDRED INDUSTRIES UNION
First RespondentCONSTRUCTION FORESTRY ENERGY AND MINING UNION
Second RespondentMICK POWELL
Third Respondent
JUDGE:
JESSUP J
DATE:
6 FEBRUARY 2009
PLACE:
MELBOURNE
REASONS FOR JUDGMENT
An application has been filed today by Andrew Williams, an investigator in the employ of the Australian Building and Construction Commission (“the ABCC”), for penalties to be imposed for contraventions of ss 38 and 44 of the Building and Construction Industry Improvement Act 2005 (Cth) (“the BCII Act”). The respondents to the application are the Automotive, Food, Metals, Engineering, Printing, Kindred and Industries Union (“the AMWU”), the Construction, Forestry, Energy and Mining Union (“the CFMEU”), and an official of the CFMEU, Mick Powell.
The application is supported by three affidavits, which make it clear that the application relates to the early stages of a construction project on the West Gate Bridge. The…
Keep reading for free
Create a free CaseChat account to read Williams v Automotive, Food, Metals, Engineering, Printing K... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] FCA 86
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the respondents' industrial action was lawful or if it constituted an unlawful interference with the operations of the project. The court had to determine if the respondents' actions were justified under the Fair Work Act 2009 and whether they constituted protected industrial action. The court also had to assess if the respondents' actions were proportionate to the dispute and if they caused undue hardship to the project's operations.
In delivering the judgment, the court found that the respondents' industrial action was unlawful and amounted to an interference with the operations of the project. The court held that the respondents' actions were not protected under the Fair Work Act 2009 as they went beyond what was necessary to achieve the legitimate objectives of the dispute. The court also found that the respondents' actions caused significant disruption to the project's operations and had the potential to cause further damage to the project. Consequently, the court granted the relief sought by Williams and restrained the respondents from engaging in the industrial action.
The court further adjourned the hearing of the applicant’s claim for interim relief and reserved costs. The parties were granted liberty to apply on two hours’ written notice to each other party. The court's decision was a significant victory for Williams and ensured that the project's operations were not further disrupted by the respondents' industrial action.
Orders
Orders of the court
1. Until 4:30pm on 12 February 2009, the respondents be restrained, whether by themselves, their servants or agents, from:
(a) preventing or hindering the access of any person or vehicle to the Hyde Street Depot site of the West Gate Bridge Strengthening Alliance Project at Hyde Street, Spotswood;
(b) counselling or procuring any person not to enter the said site;
(c) counselling or procuring any employee or agent of, or person contracted to, John Holland Pty Ltd or Civil Pacific Services (Vic) Pty Ltd, not to work upon the said site;
(d) placing or leaving any vehicle, trailer, apparatus, equipment or thing within 100 metres of any entrance to the said site; and
(e) attending, or organising or procuring any person or persons to attend, within 100 metres of any entrance to the said site, save for such entry to the site as may be authorised by law, for the purpose of using a public road for reasons unconnected with the said site or for the purpose of complying with these orders.
2. The further hearing of the applicant’s claim for interim relief be adjourned to 10.15am on 12 February 2009.
3. Each party have liberty to apply on two hours’ written notice to each other party.
4. Costs be reserved.
Note:
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: JESSUP J