Wilkinson v Bostock

Link copied
Case Copied 68 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Wilkinson v Bostock [2023] NSWCATCD 150
Hearing dates: 15 May 2023
Date of orders: 11 September 2023
Decision date: 11 September 2023
Jurisdiction:Consumer and Commercial Division
Before: G Sarginson, Senior Member
Decision:

(1) The proceedings are dismissed.

(2) The issue of costs are to be determined as follows:

(a) Respondent to file and serve costs submissions and documents by 7 days from the date of this decision.

(b) Applicant is to file and serve costs submissions and documents by 14 days from the date of this decision.

(c) Respondent to file and serve costs submissions in reply by 21 days from the date of this decision.

(d) The costs submissions of the parties are to include whether they consent to the issue of costs being determined without a further oral hearing in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW) and if not, why not.

(e) Subject to consideration of the parties submissions the Tribunal may determine the issue of costs without a further oral hearing.

(f) Either party may seek an extension of the timetable to file and serve costs submissions. However, any application for an extension must be made by the date of compliance with the particular timetable obligation.

Catchwords:

BUILDING AND CONSTRUCTION---Home building---Residential building work---Oral contract---Terms of agreement---Whether breach established

Legislation Cited:

Australian Consumer Law 2010 (NSW)

Civil and Administrative Tribunal Act 2013 (NSW)

Fair Trading Act 1989 (NSW)

Home Building Act 1989 (NSW)

Home Building Regulation 2014 (NSW)

Cases Cited:

Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613

Dare v Pulham [1982] HCA 70; (1982) 148 CLR 658

DB Homes Australia Pty Ltd v Kes [2019] NSWCATAP 221

Dyjecinska v Step-Up Renovations (NSW) Pty Ltd; Step-Up Renovations (NSW) Pty Ltd v Dyjecinska [2023] NSWCATAP 36

In the Matter of Hillsea Pty Limited [2019] NSWSC 1152

Intelligent Building Pty Ltd v Ibrahim [2023] NSWCATAP 170

Khan v Kang [2014] NSWCATAP 48

Middleton v Wrona [2023] NSWCATAP 158

Pollock v NSW Trustee & Guardian [2022] NSWSC 923

SDL Project Solutions Pty Ltd v Kim; Kim v SDL Project Solutions Pty Ltd [2022] NSWCATCD 10.

Vujica v TNM Roofing Pty Ltd [2022] NSWCATAP 305

Texts Cited:

None cited

Category:Principal judgment
Parties: Marie Wilkinson (Applicant)
Peter Clarence Bostock (Respondent)
Representation:

Counsel:
None

Solicitors:
Commins Hendriks Pty Ltd (Applicant)
Fredlieb Fox McLeod (Respondent)
File Number(s): HB 22/16764
Publication restriction: Nil

REASONS FOR DECISION

  1. This is a dispute under the Home Building Act 1989 (NSW) (HB Act) where the applicant seeks an order for damages in respect of allegedly defective and incomplete residential building work. The applicant also seeks consequential loss damages in respect of loss of rental income.

  2. The dispute arises from renovation of a bathroom and other areas in the residential premises owned by the applicant.

  3. There is a significant factual dispute as to what was the contractual scope of works agreed by the parties; the precise…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Wilkinson v Bostock and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2023] NSWCATCD 150
Decision Date

CaseChat Overview and Summary

Wilkinson v Bostock involved a dispute between a homeowner and a contractor concerning a home building contract. The homeowner, Mr Wilkinson, alleged that the contractor, Mr Bostock, breached an oral agreement to build a home in Sydney. The matter was heard by the Civil and Administrative Tribunal in New South Wales.

The central legal issue was whether Mr Wilkinson could establish the terms of an oral agreement with Mr Bostock, and if so, whether there was a breach of that agreement. The court had to consider the evidence presented by both parties and determine the validity of the oral contract, the specific terms agreed upon, and whether there was a breach of those terms.

The Tribunal found that Mr Wilkinson failed to establish the existence of an oral agreement with Mr Bostock or its specific terms. As a result, the Tribunal dismissed the proceedings. The court further directed the parties to provide detailed submissions on costs, with a specific timetable for filing and serving these submissions. The Tribunal retained the discretion to determine the costs without a further oral hearing, subject to the parties' consent or the reasons provided for not consenting.

The final orders of the Tribunal dismissed the proceedings and set out a detailed timetable for the parties to file and serve their costs submissions. This included specific deadlines for the filing of initial and reply submissions, and the option for the Tribunal to determine the costs without a further hearing, based on the parties' submissions.

Orders

Orders of the court

(1) The proceedings are dismissed.

(2) The issue of costs are to be determined as follows:

(a) Respondent to file and serve costs submissions and documents by 7 days from the date of this decision.

(b) Applicant is to file and serve costs submissions and documents by 14 days from the date of this decision.

(c) Respondent to file and serve costs submissions in reply by 21 days from the date of this decision.

(d) The costs submissions of the parties are to include whether they consent to the issue of costs being determined without a further oral hearing in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW) and if not, why not.

(e) Subject to consideration of the parties submissions the Tribunal may determine the issue of costs without a further oral hearing.

(f) Either party may seek an extension of the timetable to file and serve costs submissions. However, any application for an extension must be made by the date of compliance with the particular timetable obligation.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established