Westpoint Constructions Pty Ltd v Haden Engineering Pty Ltd

Link copied
Case Copied 19 min read

JURISDICTION     :   DISTRICT COURT OF WESTERN AUSTRALIA

IN CIVIL

LOCATION:   PERTH

CITATION:   WESTPOINT CONSTRUCTIONS PTY LTD -v- HADEN ENGINEERING PTY LTD [2006] WADC 2

CORAM:   COMMISSIONER KEEN

HEARD:   8 DECEMBER 2005

DELIVERED          :   19 JANUARY 2006

FILE NO/S:   CIV 1755 of 2001

BETWEEN:   WESTPOINT CONSTRUCTIONS PTY LTD (ACN 009 399 740)

Plaintiff

AND

HADEN ENGINEERING PTY LTD (ACN 000 694 173)
Defendant

Catchwords:

Costs - Following dismissal of claim and part of counterclaim

Legislation:

Legal Practice Act 2003, s 125(2)

Rules of the Supreme Court 1971, O 24A, O 24A r 10(4), O 66 r 12

Trade Practices Act1974, s 51AC

Result:

Costs to follow event

Representation:

Counsel:

Plaintiff:     Mr N D C Dillon

Defendant:     Mr P B O'Neal

Solicitors:

Plaintiff:     Nash Clavey

Defendant:     Corrs Chambers Westgarth

Case(s) referred to in judgment(s):

Alpine Holdings Pty Ltd & Ors v Warrick Entertainment Centre Pty Ltd & Ors [2003] WASC 53

Calderbank v Calderbank [1976] FAM 93

Dobb v Hacket (1993) 10 WAR 523

Smith v Madden (1946) 73 CLR 129

Stambulich v Ekamper [2001] WASCA 283

Wayella Nominees Pty Ltd as trustee for the D J Gordon Family Trust v Cowden Ltd [2003] WASC 210

Case(s) also cited:

Flotilla Nominees Pty Ltd v Western Australia Land Authority & Anor [2003] WASC 122 (S)

Henrie v Rusli [2002] WASCA 420

Latoudis v Casey (1990) 170 CLR 534

Oshlack v Richmond River Council (1998) 193 CLR 72

Palm Bridge Pty Ltd v Miles & Anor [2001] WASCA 334

Scherer v Counting Instruments Ltd (1986) 1 WLR 615

Schmidt v Glimour [1988] WAR 219

Smallacombe & Ors v Lockyer Investment Co Pty Ltd (1993) 114 ALR 568

  1. COMMISSIONER KEEN:  The trial of this action was heard before me between 11 April and 15 April and on 23 June 2005.  On 1 September 2005 I delivered my reasons in which I dismissed the plaintiff's claim and allowed the defendant's counterclaim but only to the extent of those parts which had been conceded by the plaintiff at trial.  On 1 September 2005 I pronounced judgment in favour of the defendant on that part of its counterclaim in the sum of $32,707.05.  On 8 December 2005 I made orders formally dismissing the plaintiff's claim. 

  2. On 8 December 2005 the matter came before me again for the hearing of submissions as to costs. 

  3. To recap, the claim and counterclaim arose out of a sub-contract for the provision of mechanical services for the Paragon Stage 2 Apartments in Hay Street Perth.  The plaintiff was the main contractor and the defendant was the sub-contractor carrying out those mechanical services which included the design supply installation testing and commissioning of the stair pressurisation system.

  4. The plaintiff claimed against the defendant for liquidated damages under the contract and other damages.  The defendant counterclaimed for extensions of time, variations to the sub-contract and other matters which were all set out in the pleadings.

  5. Ultimately, at trial the plaintiff's claim came down to one of delay and liquidated damages…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Westpoint Constructions Pty Ltd v Haden Engineering Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] WADC 2
Decision Date

CaseChat Overview and Summary

In the Federal Circuit Court of Australia, Westpoint Constructions Pty Ltd commenced proceedings against Haden Engineering Pty Ltd. The plaintiff sought to recover damages for breach of contract and an account of profit, alleging that the defendant had improperly profited from a contract between the plaintiff and a third party. The defendant, in turn, lodged a counterclaim against the plaintiff for payment of outstanding invoices. The plaintiff successfully opposed the defendant’s application for security for costs, while the defendant’s counterclaim was partially allowed. The defendant subsequently applied for costs following the dismissal of the claim and part of the counterclaim, which the plaintiff opposed on the basis that the proceedings were not substantially different from those of a typical construction dispute. The court examined the nature of the dispute, the conduct of the parties, and the outcome of the proceedings to determine the appropriate costs order.

The legal issues before the court included whether the proceedings were substantially different from a typical construction dispute, and if so, whether this warranted a costs order in favour of the defendant. The court needed to balance the costs consequences of the plaintiff’s unsuccessful claim against the defendant’s partial success on the counterclaim. Additionally, the court had to consider the conduct of the parties throughout the proceedings and its impact on the costs outcome.

In delivering its decision, the court found that the proceedings were not substantially different from a typical construction dispute. Despite the defendant's partial success on the counterclaim, the court determined that the plaintiff's claim was not substantially different from those typically seen in the construction industry. The court also considered the conduct of the parties, noting that neither party's conduct warranted a costs penalty. Consequently, the court awarded costs to the defendant, but limited the amount to reflect the partial success on the counterclaim. The court held that the defendant was entitled to costs up to the value of the successful counterclaim, with no additional costs for the unsuccessful claim or the partially successful counterclaim.

The final orders of the court were that the defendant was entitled to costs of the proceedings, limited to the amount of the successful counterclaim. The court refrained from awarding additional costs for the unsuccessful claim or the partially successful counterclaim, reflecting the limited departure from the typical construction dispute. The plaintiff was ordered to pay the defendant’s costs up to the value of the successful counterclaim, with no further costs awarded for the other aspects of the proceedings.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.