Westfield Design & Const P/L v LR & M Const P/L No. Scgrg-96-1550 Judgment No. S6796

Link copied
Case Copied 11 min read

WESTFIELD DESIGN AND CONSTRUCTION PTY LTD  V  LR & M CONSTRUCTIONS PTY LTD

ACTION NO 1550 OF 1996

[1998] SASC S6796

Judge Burley

  1. By application dated 17 April 1998 the defendant seeks the following order:-

    “1..... That the plaintiff’s points of claim in the arbitration proceedings commenced by a reference to arbitration on the 22 May 1997 ... be struck out by reason of the plaintiff having failed to refer the disputes or differences to arbitration within the period of limitation prescribed for such an action under the provisions of the Limitation of Action [sic] Act 1936-1994.”

  1. By making that application the defendant, with the consent of the plaintiff, sought, pursuant to Section 39(1)(b) of the Commercial Arbitration Act 1986 (CAA), to have determined a point of law, namely whether or not a six year period of limitation contained in s35(a) of the Limitation of Actions Act (LAA) applied to arbitral proceedings. The parties also sought to have determined whether or not, if the six year period of limitation did apply, the arbitration had been commenced within the relevant six year period.

  2. The application arises out of a contract between the parties dated 22 November 1998 for the construction of the North-East Busway interchange and carpark.  The construction work was to be carried out by the defendant.  The defendant was required to supply dolomite fill material for part of the construction work.  Disputes arose between the parties in relation to the suitability of the dolomite for the contract works.  The defendant maintains that the problem first arose at a site inspection on 8 May 1989.  It was submitted by the defendant that the “cause of action” accordingly arose on 8 May 1989.  Because the contract between the parties provided for the arbitration of disputes which arose in relation to the contract works, it may not be appropriate to use the expression “cause of action” in this context.  However, it is clear that the defendant argued that any applicable period of limitation was to be defined by reference to a starting point of 8 May 1989.  The defendant contended that the dispute was not referred to arbitration until, at the very earliest, 28 June 1996.  Consequently, it was argued, the plaintiff was out of time and could not proceed with the arbitration.

  3. It was initially argued by the defendant that because the dispute had not been referred to arbitration within the six year period, the plaintiff could not proceed at all with the arbitration, but it was later conceded, correctly in my view, that, if a limitation period of six years applied, it would be open to the plaintiff to apply for an extension of time under Section 48 of the Limitation of Actions Act if there were factual basis for same. In other words, it was conceded that the plaintiff could apply to amend the points of claim in the arbitration so as to plead the appropriate application for an extension.

  4. The defendant contended that arbitration proceedings were…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Westfield Design & Const P/L v LR & M Const P/L No. Scgrg-96... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[1998] SASC 6796
Decision Date

CaseChat Overview and Summary

Westfield Design & Construction Pty Ltd (the plaintiff) sought to bring an arbitration against LR & M Constructions Pty Ltd (the defendant) concerning disputes over the suitability of dolomite fill material provided by the plaintiff for the construction of the North-East Busway interchange and carpark. The defendant argued that the arbitration was commenced beyond the six-year limitation period prescribed by the Limitation of Actions Act 1936-1994 (LAA). The primary legal issue before the court was whether the six-year limitation period applied to arbitral proceedings and, if so, whether the arbitration had been commenced within this period. The court was required to determine whether the arbitration clause in the contract constituted a condition precedent to the accrual of a cause of action, and if not, whether the arbitration was initiated within the limitation period.

The court first considered whether the statutory limitation period applied to arbitral proceedings. The defendant argued that arbitration was an "action" under the LAA and thus subject to the six-year limitation period. The plaintiff, however, contended that no cause of action arose until an award was handed down, relying on the case of Board of Trade v Cayzer, Irvine and Company Limited. The court held that while the Board of Trade case did establish that a cause of action does not arise until an award is handed down if the arbitration clause so provides, this was not the case here. The court concluded that the statutory limitation period did apply to arbitrations, aligning with the approach taken in Baulderstone Hornibrook Engineering Pty Ltd v State Constructions Pty Ltd. The court then examined whether the arbitration had been commenced within the six-year period. The plaintiff argued that the arbitration was effectively commenced on 28 June 1996, while the defendant argued that the arbitration did not commence until 22 May 1997 when the security deposit was paid. The court held that the arbitration was effectively commenced on 28 June 1996, as the notice of dispute was sufficient to trigger the arbitration clause, irrespective of the failure to provide evidence of the security deposit at that time.

The defendant's application to have the points of claim struck out was dismissed. The court noted that the plaintiff could apply for an extension of time under Section 48 of the LAA if there were a factual basis for such an application. The court concluded that the arbitration was effectively commenced within the six-year limitation period, and therefore the defendant's application was dismissed. The court reserved costs for later determination.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established