Land and Environment Court
New South Wales
Medium Neutral Citation: Wechsler v Sydney City Council (No 2) [2015] NSWLEC 35 Hearing dates: 9 March 2015 Date of orders: 09 March 2015 Decision date: 09 March 2015 Jurisdiction: Class 1 Before: Craig J Decision: (1) Appeal upheld.
(2) Set aside the decision Morris C delivered on 3 July 2013, insofar as that decision refused the modification sought in the proceedings before her.
(3) Remit the matter for rehearing and determination by a Commissioner of the Court appointed by the Chief Judge pursuant to s 31(1) of the Land and Environment Court Act 1979 (NSW).
(4) Costs of the appeal are reserved.Catchwords: APPEAL - s 56A of the Land and Environment Court Act 1979 - modification of development consent - refusal by Commissioner to allow the Applicant to give evidence - Applicant’s participation at hearing confined to making submissions - leave to amend application refused but amendment determined without hearing evidence from Applicant in respect of it - denial of procedural fairness - appeal upheld Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW)
Land and Environment Court Act 1979 (NSW)Cases Cited: Botany Bay City Council v Pet Carriers International Pty Ltd [2013] NSWLEC 147; 201 LGERA 116
Wechsler v Sydney City Council [2013] NSWLEC 1116
Wechsler v Sydney City Council [2014] NSWLEC 201Category: Principal judgment Parties: Robert Wechsler (Applicant)
Sydney City Council (Respondent)Representation: Counsel:
Solicitors:
Self-represented (Applicant)
Submitting appearance (Respondent)
Self-represented (Applicant)
N/A
File Number(s): 10816 of 2014
EX TEMPORE Judgment
-
Robert Wechsler is the owner of a residential flat building at 5 Tusculum Street, Potts Point. That building was erected pursuant to a development consent granted in 1962. The consent and the building have been modified on a number of occasions since.
-
On 13 December 2012, Mr Wechsler made application to the Council of the City of Sydney (the Council) pursuant to s 96 of the Environmental Planning and Assessment Act 1979 (NSW) (the EPA Act) to further modify the development consent in a number of respects. On 11 January 2013, the consent of the Council was given to some of those modifications sought but the remainder were refused. Being dissatisfied with that decision, Mr Wechsler appealed to the Court pursuant to s 97AA of the EPA Act.
-
That appeal was heard by Morris C on 18 June 2013. In a reserved decision delivered on 3 July 2013 the appeal was upheld in part (Wechsler v Sydney City Council [2013] NSWLEC 1116). The part upheld allowed modification of the development consent by deletion of Condition 12. The other modifications then sought by Mr Wechsler included modification of elements of the built form that were not upheld by the Commissioner.
-
Mr Wechsler now appeals pursuant to s 56A(1) of the Land and Environment Court Act 1979 (NSW) (the Court Act) from so much of the decision of the Commissioner as did not sustain the modifications that he had…
Keep reading for free
Create a free CaseChat account to read Wechsler v Sydney City Council (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] NSWLEC 35
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether the Land and Environment Court had correctly exercised its discretion in refusing the modification sought by Wechsler and whether the process followed by the court was procedurally fair. Specifically, the court examined whether the refusal was based on proper consideration of the relevant statutory criteria and whether Wechsler had an adequate opportunity to present his case.
In addressing the appeal, the court found that the decision of Morris C was flawed. The court determined that the refusal of the modification was not based on a proper application of the statutory criteria, and there were procedural deficiencies in the hearing process. The court was critical of the failure to consider certain relevant evidence and the lack of adequate procedural fairness. Consequently, the appeal was upheld, and the decision was set aside. The matter was remitted for rehearing by a Commissioner appointed by the Chief Judge, ensuring a fresh and unbiased assessment in compliance with the relevant legislative framework. The costs of the appeal were reserved for further determination.
Orders
Orders of the court
(1) Appeal upheld.
(2) Set aside the decision Morris C delivered on 3 July 2013, insofar as that decision refused the modification sought in the proceedings before her.
(3) Remit the matter for rehearing and determination by a Commissioner of the Court appointed by the Chief Judge pursuant to s 31(1) of the Land and Environment Court Act 1979 (NSW).
(4) Costs of the appeal are reserved.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.