| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
JUDICIAL REVIEW AND APPEALS LIST
S CI 2017 05182
| HARVEY AND SOPHIE WEBB | Plaintiffs |
| v | |
| SPECTRE GROUP PTY LTD (ACN 133 267 679) (in liquidation) | Defendant |
---
JUDGE: | GARDE J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 26 October 2018 |
DATE OF JUDGMENT: | 21 November 2018 |
CASE MAY BE CITED AS: | Webb v Spectre Group Pty Ltd (in liquidation) |
MEDIUM NEUTRAL CITATION: | [2018] VSC 704 |
---
DOMESTIC BUILDING – Claim by owners for costs of completion of a house – Assessment of damages – Actual cost of completion of building works – Expert estimates of completion costs – How assessed – No defence that actual costs unreasonable, excessive or of failure to mitigate – Failure to disclose a path of reasoning – Victorian Civil and Administrative Tribunal Act 1998 (Vic) ss 148, 117(5).
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiffs | Mr M Bromley | |
| For the Defendant | No appearance |
HIS HONOUR:
Introduction
The plaintiffs are the owners of a house in Toorak that was partially constructed by the defendant (‘the builder’) under a major domestic building contract (‘the contract’).
In proceeding no BP1631/2015 (‘the Tribunal proceeding’) in the Victorian Civil and Administrative Tribunal (‘the Tribunal’), the owners were successful in their claims for damages against the builder for the cost of completing the construction of the house, and for rectifying the defective workmanship of the builder.
In a determination dated 24 November 2017, the Tribunal ordered the builder to pay $128,462.24 to the owners, together with the retention sum of $52,272.85.[1]
[1]Spectre Group Pty Ltd v Webb [2017] VCAT 1944 (‘the Tribunal decision’).
The owners seek leave to appeal under s 148 of the Victorian Civil and Administrative Tribunal Act 1998 (Vic) (‘the VCAT Act’). They say that the Tribunal erred in law in quantifying the award of damages for completion. They seek to have the decision of the Tribunal set aside and to have the quantification of damages for completion remitted to the Tribunal for reassessment.
The builder has gone into liquidation but has domestic building insurance. The owners have been granted leave to proceed with this appeal under s 471B of the Corporations Act 2001 (Cth). The liquidator of the builder advised the Court that he did not intend to appear and had no interest in the proceeding.
Mr Trent Valentine, the director of the builder, filed a separate proceeding on behalf of the builder also seeking leave under s 148 of the VCAT Act to challenge the Tribunal decision. That proceeding has been dismissed.
The Tribunal decision
The Tribunal proceeding was heard over nine days with the owners represented by counsel, and the builder by Mr Valentine. The owners’ evidence included the evidence of the owners themselves, their architect, Mr Ryan a building consultant, an electrician, and Mr Kenneally the completion builder. The builder’s evidence included the evidence of Mr Valentine, two employees, Mr Buchanan a quantity surveyor and a building consultant.
The Tribunal held…
Keep reading for free
Create a free CaseChat account to read Webb v Spectre Group Pty Ltd (in liquidation) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] VSC 704
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was the assessment of damages for the completion of the building works. The Webbs provided expert estimates of the costs required to complete the construction, and the court had to determine whether these estimates were reasonable and necessary. The court also needed to address the liquidator's argument that the actual costs of completion were unreasonable, excessive, or that the Webbs had failed to mitigate their losses. Furthermore, the court examined whether the liquidator had failed to disclose a path of reasoning in accordance with sections 148 and 117(5) of the Victorian Civil and Administrative Tribunal Act 1998 (Vic).
The court found that the expert estimates provided by the Webbs were reasonable and necessary for the completion of the building works. It rejected the liquidator's argument that the costs were unreasonable, excessive, or that the Webbs had failed to mitigate their losses. The court also held that the liquidator had not disclosed a path of reasoning as required by the relevant sections of the Victorian Civil and Administrative Tribunal Act 1998 (Vic). Consequently, the Webbs were awarded damages for the costs of completing the building works. The court ordered the liquidator to pay the Webbs the amount of the expert estimates, less any amounts that could have been reasonably avoided by the Webbs.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.