CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - PERFORMANCE OF WORK - GENERAL
Building contract - action brought by builder to recover from owner the sum of $32,216.85 for unpaid variations to contract - whether claim related to items included in the contract prices, as asserted by the owner - judgment entered for the builder in the amount of $15,691.50 (inclusive of interest) - judgment amount less than that sought by the builder on account of concessions made by the builder in relation to certain items and builder's failure to prove certain other items.
Cross-action brought by owner for damages in the amount of $2,583,074.00 for alleged economic loss arising from alleged breaches of contract/negligence - claim dismissed except in respect of two minor items resulting in an award of damages in the amount of $599.00, included as an offset in amount awarded to the builder.
Development Act 1993 s 32, referred to.
Browne v Dunn (1893) 6 R 67; Bulstrode v Newton [1970] VR 840; MWJ v The Queen (2005) ALJR 329, considered.
WCK PTY LTD v FOWLER; FOWLER v DANIELS & ANOR
[2016] SADC 142INTRODUCTION
Mr Keith Daniels is the Managing Director of WCK Pty Ltd (‘WCK’) a licensed builder which trades as Keith Daniels Building Co (‘KBDC’). Mr Glen Fowler was, at the time of the relevant events, the registered proprietor of Lot 27, 89 Mortlock Terrace (‘the property’) and Trustee for Draig-Teine Trust (‘DTT’).
On 15 March 2006 a written agreement (‘the Contract’) was executed in which KBDC (nominated as the Builder) agreed to construct commercial premises on the property for DTT (nominated as the Owner). The works performed under the Contract involved the construction of a building and carpark. They were completed in late 2006.
The proceedings comprise of an action brought by WCK against Mr Fowler (Action No 2010 of 2008) for the payment of variations to the Contract and a cross-action brought by Mr Fowler, as Trustee for DTT, against Mr Daniels as First Defendant and, in the alternative, against WCK as Second Defendant (Action No 599 of 2014) seeking damages primarily for economic loss due to breach of contract and/or negligence.
PROCEEDINGS: BACKGROUND
This matter has an unfortunately long and vexed pre-trial history. The following is a sufficient summary of that history.
On 13 August 2007 WCK commenced proceedings against Mr Fowler by filing a claim in the Magistrates Court of South Australia for unpaid costs of variations to the Contract totalling $32,216.85 plus interest.
On 2 October 2007 Mr Fowler filed a Defence and Cross Action (Counterclaim) in which he pleaded: (i) that he could not be sued by WCK because he had not executed the Contract in his own right but as Trustee for DTT, accordingly no privity of contract existed between them; and, (ii) that no money was owed…
Keep reading for free
Create a free CaseChat account to read WCK Pty Ltd v Fowler; Fowler v Daniels and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2016] SADC 142
- Decision Date
CaseChat Overview and Summary
The court examined the contract between the parties and the work performed, determining that the builder's claim was valid in part. The court found that the builder had made certain concessions in relation to specific items, and that there were other items that the builder had failed to prove. As a result, the judgment entered in favour of the builder was for the amount of $15,691.50, inclusive of interest. This amount was less than that originally sought by the builder. The court also dismissed Fowler's cross-action for damages, except in respect of two minor items, which resulted in an award of damages in the amount of $599.00.
The court's reasoning was based on a careful examination of the contract, the work performed, and the evidence presented by both parties. The court found that the builder had established a valid claim for unpaid variations to the contract, but that the amount sought was excessive due to the concessions made and the failure to prove certain items. The court also found that Fowler's cross-action for damages was not supported by the evidence, except in respect of the two minor items. The final orders of the court were that judgment be entered in favour of the builder for the amount of $15,192.50, with an offset of $599.00 for the two minor items in favour of Fowler.