>
Land and Environment Court
of New South Wales
CITATION: Waverley Council v Ligertwood and Others [2003] NSWLEC 172 PARTIES: APPLICANT
Waverley CouncilFIRST RESPONDENT
Georgina LigertwoodSECOND RESPONDENT
Crackwell and Lonergan Architects Pty LimitedTHIRD RESPONDENT
FOURTH RESPONDENT
Fourway Constructions Pty Limited
Bernie Cohen & Associates Pty Ltd t/as Essential Certifiers LiverpoolFILE NUMBER(S): 40550 of 2003 CORAM: Talbot J KEY ISSUES: Interlocutory Relief :- serious question to be tried - delay by council in bringing proceedings LEGISLATION CITED: Environmental Planning and Assessment Act 1979 s 81A(5)
Environmental Planning and Assessment Regulation 2000 s 142(2), s 147(1)(e)
Noise Control Act 1975CASES CITED: DATES OF HEARING: 05/06/2003 EX TEMPORE
JUDGMENT DATE :
06/05/2003LEGAL REPRESENTATIVES: RESPONDENTS
APPLICANT
Mr S J Brockwell (Barrister)
SOLICITORS
M E McMahon & Associates
Mr J Doyle (Solicitor)
SOLICITORS
Cowley Hearne Lawyers
JUDGMENT:
IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
40550 of 2003
5 June 2003Talbot J
- Applicant
- First Respondent
- Second Respondent
- Third Respondent
- Fourth Respondent
Introduction
1 HIS HONOUR: Development consent was granted by the Court in Matter No. 10851 of 2001 following a hearing before Commissioner Murrell. The conditions of the development consent contain some inconsistencies. With due respect to the parties who drafted the conditions, there is a real capacity for there to be a lack of understanding about just exactly, first of all, what was approved, and secondly, the conditions under which it was approved.
2 I assume, nevertheless, that the set of plans before the Court amount to the plans approved by the Commissioner. My attention has been drawn to condition 40, which deals with the Noise Control Act 1975 and the provisions of an Australian Standard in relation to all sound-producing plant.
3 Conditions 60 through to condition 63 particularly deal with the mechanical ventilation system proposed. There is provision for the design of that system to be certified by a person competent to do so prior to the issue of the construction certificate.
4 The issue that now arises is in relation to the location of an exhaust cowl shown in the plans as located adjacent to a stairway, but not above the stairway. The question is whether it has been located in a place that can be accepted as consistent with the development consent granted by the Court.
5 A construction certificate was issued on 9 September 2002. The certifier stated that if the work is completed in accordance with plans and specifications attached to the certificate, it will comply with the requirements of s 81A(5) of the Environmental Planning and Assessment Act 1979 (“the EP&A Act) and s 147(1)(e) of the Environmental Planning and Assessment Regulation 2000 (“the EP&A Regulation”).
6 Attached to the certificate are plans which have been tendered in the council’s case. Those plans clearly and distinctly show the location of the…
Keep reading for free
Create a free CaseChat account to read Waverley Council v Ligertwood and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] NSWLEC 172
- Decision Date
CaseChat Overview and Summary
The court examined the inconsistency between the approved plans and the actual installation, noting that the construction certificate issued on 9 September 2002, which the council had in its possession since then, did not reflect the approved plans. The court found that although there was a serious question to be tried, the council's lack of diligence and delay in bringing the proceedings, coupled with the minimal remaining work required to complete the installation, influenced the decision. The court held that the balance of convenience did not favour granting interlocutory relief at that stage, as the public interest would not be severely affected by further delay until the final hearing.
The court refused to grant interlocutory relief, emphasizing the importance of not assisting parties who have delayed in taking action when the opportunity to act was available. The court directed the matter to proceed with the formal particularisation of the claims and reserved the question of costs for the final outcome of the proceedings.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi