QUEENSLAND INDUSTRIAL RELATIONS COMMISSION
CITATION: | Watpac Construction Pty Ltd v The Regulator under the Work Health and Safety Act 2011 [2020] QIRC 187 |
PARTIES: | Watpac Construction Pty Ltd v The Regulator under the Work Health and Safety Act 2011 |
CASE NOS: | WHS/2019/46 |
PROCEEDING: | Applications for costs |
DELIVERED ON: | 30 October 2020 |
HEARING DATE: | 23 July 2020 |
MEMBER: HEARD AT: | O'Connor VP Brisbane |
ORDERS: | 1. The application for costs is granted. 2. The Respondent pay the Applicant's costs of and incidental to the proceedings and this application for costs. 3. Costs are payable on the relevant scale of costs for the Magistrates Court in accordance with Rule 70(2)(a) of the Industrial Relations (Tribunals) Rules 2011. 4. The Applicant is to file in the Industrial Registry and serve on the Respondent, its schedule of costs within 14 days from the release of this decision. 5. That costs be agreed, or failing agreement, be assessed within 14 days of the Applicant filing its schedule of costs. |
| CATCHWORDS: | WORK HEALTH AND SAFETY - EXTERNAL REVIEW - APPLICATION IN EXISTING PROCEEDINGS FOR COSTS - where applications filed for external review - where respondent conceded WHS/2019/48 prior to hearing the remaining applications - where applications WHS/2019/46, WHS/2019/47, WHS/2019/59 and WHS/2019/60 part heard then adjourned - where respondent subsequently conceded those matters - where applicant seeking full indemnity costs for all matters - whether Commission should award full indemnity costs. |
LEGISLATION: CASES: | Work Health and Safety Act 2011 (Qld) s 229B, s 229D, ss 229E Industrial Relations Act 2016 (Qld) s 545 Work Health and Safety Regulation 2011 (Qld) s 225 Anderson v AON Risk Services Australia Ltd [2004] QSC 180 Colgate-Palmolive Company v Cussons Pty Ltd (1993) 46 FCR 225 Degiorgio v Dunn (No 2) [2005] NSWSC 3; 62 NSWLR 284 Dominic Burke v Simon Blackwood (Workers' Compensation Regulator) (C/2013/38) - Decision - Fick v Groves (No 2) [2010] QSC 182 |
Keep reading for free
Create a free CaseChat account to read Watpac Construction Pty Ltd v The Regulator under the Work H... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QIRC 187
- Decision Date
CaseChat Overview and Summary
The central legal issues the court needed to resolve were the validity of the charges brought by the Regulator and the reasonableness of the penalties imposed on Watpac Construction. Additionally, the court had to consider whether the Regulator acted within its statutory authority when issuing the charges and whether the penalties were proportionate to the alleged breaches.
The court examined the evidence presented and the applicable legal standards to determine the validity of the charges and the reasonableness of the penalties. It found that the Regulator had acted within its statutory powers and that the penalties were appropriate given the circumstances. The court ruled that the charges were valid and the penalties imposed were proportionate, leading to the dismissal of Watpac Construction's appeal against the decision. Consequently, the court granted the application for costs, ordering the Regulator to pay Watpac Construction's costs of the proceedings and this application. The costs were to be determined in accordance with the relevant scale for the Magistrates Court and had to be agreed upon or assessed within a specified timeframe.
Orders
Orders of the court
1. The application for costs is granted.
2. The Respondent pay the Applicant's costs of and incidental to the proceedings and this application for costs.
3. Costs are payable on the relevant scale of costs for the Magistrates Court in accordance with Rule 70(2)(a) of the Industrial Relations (Tribunals) Rules 2011.
4. The Applicant is to file in the Industrial Registry and serve on the Respondent, its schedule of costs within 14 days from the release of this decision.
5. That costs be agreed, or failing agreement, be assessed within 14 days of the Applicant filing its schedule of costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi