SUPREME COURT OF QUEENSLAND
[2006] QSC 269
CIVIL JURISDICTION
FRYBERG J
No 7802 of 2006
| WATPAC AUSTRALIA PTY LTD (ACN 010 462 816) | Applicant |
| and | |
| SPRING HILL DEVELOPMENTS (No 1) LIMITED (ACN 103 062 826) | Respondent |
BRISBANE
..DATE 14/09/2006
ORDER
HIS HONOUR: This is an application for an interlocutory injunction by a builder against the owner, or principal, as I shall call it, in relation to a building contract for a non-domestic building.
The contract was due to reach practical completion in April last year and reached practical completion in September last year. The defects maintenance period of 12 months will shortly expire and shortly after that, by the operation of the mechanism for a final certificate, the principal will become required to release the security provided in the form of a bond by the builder.
The principal matter in dispute for present purposes is whether the delay in the practical completion entitles the principal to charge liquidated damages. The builder contends that it is entitled to extensions of time for the period between the date for practical completion and the date of practical completion, a proposition denied by the principal and negated by the most recent certificate issued by the supervisor.
The principal claims that an amount of the order of $1.3 million is owing by way of liquidated damages. The security which has been provided is in a sum slightly in excess of $1 million and it is provided by an insurance company in the form of a bond. The contract permits the principal to have access to the proceeds of the bond effectively at any time.
The builder seeks the injunction pursuant to the provisions of s 67J of the Queensland Building Services Authority Act 1991,
as amended prior to 2004. That section provides:
"67J Set-offs under building contracts
(1) The contracting party for a building contract may reduce an amount payable under the contract by an amount owed under the contract, or use a security for the building contract, wholly or partly, to obtain an amount owed under the contract, only if-
(a) the reduction of the amount payable or the use of
the security is permitted under the contract; and
(b) the contracting party has given-
(i) written notice (the "first notice") to the
contracted party for the contract advising of the
proposed reduction or use and, if the amount owed
can be quantified when the first notice is given,
of the amount owed; and
(ii) if the amount owed can not be quantified when
the first notice is given, a further written notice
(the "second notice") to the contracted party
advising of the amount owed.
(2) The first notice must be given within 28 days after
the contracting party becomes aware, or ought reasonably
to have become aware, of the contracting party's right to
obtain the amount owed.
(3) If the second notice is required to be given, it
must be given within 3 business days after the contracting party becomes…
Keep reading for free
Create a free CaseChat account to read Watpac Australia Pty Ltd v. Spring Hill Developments (No 1)... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] QSC 269
- Decision Date
CaseChat Overview and Summary
The builder argued that the principal had not provided the notice required by the Queensland Building Services Authority Act 1991. The builder contended that the principal must have been aware of its entitlement to liquidated damages when the practical completion was certified to both parties. The principal argued that the reference in s 67 J(1) to an amount owed under the contract was effectively a reference to the final amount payable under the contract and that the obligation lies upon the superintendent in issuing certificates under clause 42.1.3 of the contract to adjust the amount payable to account for the amount of any liquidated damages. The principal also sought to rely upon the second part of clause 5.6 to assert that the builder was prohibited from taking steps to restrain the owner from making a demand under the security or receiving payment under it. The principal argued that the requirement in subsection (2) for the notice to be given within 28 days was not a requirement the breach of which invalidated a notice under subsection (1). The builder submitted that failure to comply with the time requirement did not invalidate the notice but might be a factor in considering whether, by reason of breach of the statutory provision, an injunction ought to be issued to restrain the realisation of the security. The court found that the better construction of the section was that failure to comply with the time requirement did not invalidate the notice but might be a factor in considering whether, by reason of breach of the statutory provision, an injunction ought to be issued to restrain the realisation of the security.
The court found that the balance of convenience clearly favoured the grant of the injunction. The builder offered to consent to the principal retaining the security pending the determination of the proceedings and to provide $50,000 for security for interest payable under the contract. The builder also submitted that its reputation as a builder would be damaged if the bond was called-up. The court found that the balance of convenience clearly favoured the grant of the injunction.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.