Water Agencies Amendment By-laws 2000 (WA)
29 June 2000] GOVERNMENT GAZETTE, WA 3365
Water Agencies (Powers) Act 1984
Water Agencies Amendment By-laws 2000
Made by the Minister under section 34(1) of the Act.
Part 1 — Preliminary
1. Citation
These by-laws may be cited as the Water Agencies Amendment
By-laws 2000.
2. Commencement
These by-laws come into operation on 1 July 2000.
3. Application
Nothing in these by-laws affects the application after
1 July 2000 of a by-law in force before that day in so far as that
by-law relates to a fee or charge for a period commencing
before that day or to a fee or charge for any matter or thing done
before that day.
| 3366 | GOVERNMENT GAZETTE, WA | [29 June 2000 |
Water Agencies Amendment By-laws 2000
Part 2 Carnarvon Irrigation District By-laws amended bl. 4
Part 2 — Carnarvon Irrigation District By-laws
amended
4. The by-laws amended
The amendments in this Part are to the Carnarvon Irrigation
District By-laws*.
[* Published in Gazette 2 July 1962, pp. 1695-8.For amendments to 23 June 2000 see 1999 Index to
Legislation of Western Australia, Table 4, pp. 314-6.]
5. Schedule 1 replaced
Schedule 1 is repealed and the following Schedule is inserted instead —
“ Schedule 1 — Minimum fee for testing a meter
[bl. 19(3)(a)]
Meter Size Fee $
20-25 mm........................................................................ 54.00 40-50 mm........................................................................ 114.00 75 mm and over .............................................................. 220.50
”.
29 June 2000] GOVERNMENT GAZETTE, WA 3367 Water Agencies Amendment By-laws 2000
Country Areas Water Supply By-laws 1957 amended Part 3
bl. 6
Part 3 — Country Areas Water Supply By-laws 1957
amended
6. Schedule 2 replaced
Schedule 2 to the Country Areas Water Supply By-laws 1957* is repealed and the following Schedule is inserted instead —
“
Schedule 2 — Fees
[bll. 49, 58A, 66, 66A, 77, 83, 87F, 87G, 96, 97, 98, 100, 101, 104C]
$
2. Meter testing —
Meter size
20 or 25 mm............................................................... 54.00 40 or 50 mm............................................................... 114.00 75 mm and over ......................................................... 220.50
3. Minimum fee in respect of turning or cutting off or
reduction of the water supply and the restoration of the
water supply....................................................................... 4. (a) Reading of meter........................................................
76.50
7.50
(b) Urgent reading of meter............................................. 13.00 (c) Electronic lodgment of a combined request for a single statement, reading of meter and orders and requisitions................................................................. 21.50 (d) Electronic lodgment of a combined request for a single statement, urgent reading of meter and orders and requisitions ............................................... 27.00 (e) Lodgment other than under paragraph (c) of a combined request for a single statement, reading of meter and orders and requisitions .............................. 27.00 (f) Lodgment other than under paragraph (d) of a combined request for a single statement, urgent reading of meter and orders and requisitions............. 32.00 (g) Provision of information other than under paragraphs (a) to (f) involving research or investigation of 15 minutes or more — per hour or part of an hour............................................................ 27.00 5. Fee under section 43A in respect of land on which it is proposed to —
(a) construct a new single residential building................ 57.50
| 3368 | GOVERNMENT GAZETTE, WA | [29 June 2000 |
Water Agencies Amendment By-laws 2000
Part 3 Country Areas Water Supply By-laws 1957 amended bl. 6 $
(b) alter an existing single residential building at a cost, as assessed by the Corporation, of over
$22 500 — per $1 000 of the cost so assessed, up
to a maximum of $57.50 ............................................ 1.15 (c) construct or alter a building other than a single residential building, the cost of which construction
or alteration the Corporation assesses to be over $22 500, an amount for each $1 000 of the cost assessed —
up to $1 000 000 ........................................................ 1.30 over $1 000 000 but not over $10 000 000 ................ 0.85 over $10 000 000 but not over $50 000 000 .............. 0.45 over $50 000 000 ....................................................... 0.20
6. (a) Supply of copy of, or extract from, records or plans (other than those stored in digital format) under section 102(3) of the Water Agencies (Powers) Act 1984 —
A1 film....................................................................... 13.20 A1 paper..................................................................... 10.45 A2 paper..................................................................... 8.25 A3 paper..................................................................... 7.15 A4 paper..................................................................... 7.15
(b) Additional fee (A4 only) for facsimile transmission . 4.40 7. Re-sealing of private fire service connection under
by-law 98(5) ...................................................................... 62.15 8. Fee for relocation of water supply connection (less than 500 mm) —
(a) where the connection size is —
20 mm ........................................................................ 108.00 25 mm ........................................................................ 128.00 40 mm ........................................................................ 168.00 50 mm ........................................................................ 218.50
(b)
other sizes, an amount equal to the actual cost of relocation.
9. (a) Fee for fixing a meter under by-law 77(3)................. 227.00 (b) Fee for assessing a meter under by-law 77(5) ........... 162.00 (c) Fee for assessing a meter and fixing a new meter under by-law 77(6)..................................................... 211.00
29 June 2000] GOVERNMENT GAZETTE, WA 3369 Water Agencies Amendment By-laws 2000
Country Areas Water Supply By-laws 1957 amended Part 3
bl. 6
$
10.Fee for installation of temporary building standpipe......... 95.70 11.Fee for inspection of work under by-law 87F —
(a) single residential building.......................................... 41.25
(b) other than single residential building — single
storey.......................................................................... 63.25
(c) other than single residential building — more than
one storey — fee per floor ......................................... 105.05 12.Fee for book of forms of —
(a) notice and certificate of completion and
compliance................................................................. 19.25
(b) multi-entry plumbing certificate ................................ 7.15 13.Fees for authorisation of materials, fittings and fixtures —
(a) application —
(i) first item of product type.................................... 400.40
(ii) each additional item of product type.................. hour or part of an hour)..............................................
55.55
(b) examination, testing, inspection or evaluation (per
93.50
14.Minimum fee for application for disconnection or
reconnection of water supply under by-law 96 — on
redevelopment or subdivision............................................ 108.50
”.
[* Reprinted as authorised 1 May 1968.
For amendments to 23 June 2000 see 1999 Index to
Legislation of Western Australia, Table 4, pp. 307-13 and
Gazette 14 April 2000.]
| 3370 | GOVERNMENT GAZETTE, WA | [29 June 2000 |
Water Agencies Amendment By-laws 2000
Part 4 Country Towns Sewerage By-laws 1952 amended bl. 7
Part 4 — Country Towns Sewerage By-laws 1952
amended
7. Schedule C replaced
Schedule C to the Country Towns Sewerage By-laws 1952* is repealed and the following Schedule is inserted instead —
“
Schedule C — Fees
Part I — Plumbing fees
[bll. 18F(6) and 29(2)(a)]
$
1. For works to be connected to the sewer —
(a) single residential building —
(i) one major fixture ................................................ (iii) reinspection ........................................................
74.50
(ii) each additional major fixture ............................. 18.50 41.25
(b)
other than single residential building — single storey —
(i) one major fixture ................................................ (iii) reinspection ........................................................
115.00
(ii) each additional major fixture ............................. 38.50
63.25
(c)
other than single residential building — more than one storey — fee per floor —
(i) one major fixture on floor .................................. (iii) reinspection ........................................................
190.50
(ii) each additional major fixture on floor................ 63.50
105.05
2. For works to be connected to a septic tank —
(a) one major fixture........................................................ 45.00 (b) each additional major fixture ..................................... 22.50 3. For inspection of work under by-law 18F —
(a) single residential building........................................ .. 41.25
(b) other than single residential building — single
storey.......................................................................... 63.25
(c) other than single residential building — more than
one storey — fee per floor ......................................... 105.05
29 June 2000] GOVERNMENT GAZETTE, WA 3371 Water Agencies Amendment By-laws 2000
Country Towns Sewerage By-laws 1952 amended Part 4
bl. 7
Part II — Fees under section 41A
[bl. 29(1a)]
$
In respect of land on which it is proposed to —
(a) construct a new single residential building................ 57.50 (b) alter an existing single residential building at a cost, as assessed by the Corporation, of over $22 500 — per $1 000 of the cost so assessed, up to a maximum of $57.50 ............................................ 1.15 (c) construct or alter a building other than a single residential building, the cost of which construction or alteration the Corporation assesses to be over $22 500, an amount for each $1 000 of the cost assessed —
up to $1 000 000 ........................................................ 1.30 over $1 000 000 but not over $10 000 000 ................ 0.85 over $10 000 000 but not over $50 000 000 .............. 0.45 over $50 000 000 ....................................................... 0.20 Part III — Fees for copies of records, plans and
diagrams
[bl. 225]
$
1. Supply of copy of, or extract from, records or plans
(other than those stored in digital format) under section 102(3) of the Water Agencies (Powers) Act 1984 —
A1 film ............................................................................ 13.20 A1 paper ............................................................................ 10.45 A2 paper ............................................................................ 8.25 A3 paper ............................................................................ 7.15
A4 paper ............................................................................ 2. Property sewer diagram (per A4 copy)..............................
7.15
7.15 3. Additional fee (A4 only) for facsimile transmission ......... 4.40
| 3372 | GOVERNMENT GAZETTE, WA | [29 June 2000 |
Water Agencies Amendment By-laws 2000
Part 4 Country Towns Sewerage By-laws 1952 amended bl. 7
Part IV — Statements and information
[bl. 224]
$
1. Electronic lodgment of a combined request for a copy of any portion of the records kept under s. 69A of the Water Agencies (Powers) Act 1984 and answers to
orders and requisitions in relation to land ......................... 21.50 2. Lodgment other than under item 1 of a combined
request for a copy of any portion of the records kept
under s. 69A of the Water Agencies (Powers) Act 1984
and answers to orders and requisitions in relation to
land .................................................................................... 27.00 3.
Provision of information other than under items 1 or 2 that involves research or investigation of 15 minutes or more — per hour or part of an hour................................... 27.00
Part VI — Fees for books of forms
[bl. 18G(1)]
$
1. Book of forms of notice and certificate of completion
and compliance.................................................................. 2. Book of forms for multi-entry plumbing certificate ..........
19.25
7.15 Part VII — Fees for authorisation of materials,
fittings and fixtures
[bl. 49(3)(c) and (7)]
$
1. Application fee —
(a) for first item of product type...................................... 400.40 (b) for each additional item of product type .................... 55.55 2. Examination, testing, inspection or evaluation (per hour
or part of an hour).............................................................. 93.50
29 June 2000] GOVERNMENT GAZETTE, WA 3373 Water Agencies Amendment By-laws 2000
Country Towns Sewerage By-laws 1952 amended Part 4
bl. 7
Part VIII — Fees for the provision of plan sheets
for preparation of diagrams of property
sewer installations
[bl. 18B(1)(a)]
$
1. A4 size (per pad of 25 sheets) .......................................... 4.40 2. A3 size (per pad of 25 sheets) ........................................... 8.25 3. A1 size (per sheet) ............................................................ 1.65
Part IX — Minimum fees for installation of
sewer junction
[bl. 230(1)]
$
1. 100 mm sewer junction ..................................................... 281.00 2. 150 mm sewer junction ..................................................... 348.50
”.
[* Reprinted as at 17 September 1996.
For amendments to 23 June 2000 see 1999 Index to Legislation of Western Australia, Table 4, pp. 46-8.]
| 3374 | GOVERNMENT GAZETTE, WA | [29 June 2000 |
Water Agencies Amendment By-laws 2000
Part 5 Metropolitan Water Authority (Miscellaneous) By-laws 1982
amendedbl. 8 Part 5 — Metropolitan Water Authority (Miscellaneous)
By-laws 1982 amended
8. The by-laws amended
The amendments in this Part are to the Metropolitan Water
Authority (Miscellaneous) By-laws 1982*.
[* Reprinted as at 9 April 1996.For amendments to 23 June 2000 see 1999 Index to
Legislation of Western Australia, Table 4, p. 313.]
9. Schedule 2 replaced
Schedule 2 is repealed and the following Schedule is inserted instead —
“
Schedule 2 — Charges
[bll. 9(1), (2) and (6) and 11(2)]
$
1. Meter testing deposit — Meter size —
20-25 mm .................................................................... 54.00 40-50 mm .................................................................... 114.00 75 mm and over........................................................... 220.50
2. Charges for fixing water supply and firefighting connections —
(a) fix water supply connection — (i) where the connection size is —
20 mm.................................................................. 547.50 25 mm.................................................................. 798.00 40 mm.................................................................. 1 219.00
50 mm.................................................................. 1 486.00(ii) other sizes, an amount equal to the actual cost of fixing the connection;
(b) fix firefighting connection —
(i) described in Schedule 3 —
not within the central business districts as 150 mm................................................................ 5 692.50
29 June 2000] GOVERNMENT GAZETTE, WA 3375 Water Agencies Amendment By-laws 2000
Metropolitan Water Authority (Miscellaneous) By-laws 1982 Part 5 amended
bl. 10
$
(ii) within the central business districts as described in Schedule 3, an amount equal to the actual cost of fixing the connection.
3. Charge for —
disconnection ......................................................... 76.50 reconnection ........................................................... 76.50
4. Charge for relocation of water supply connection (less than 500 mm) —
(a) where the connection size is —
20 mm .................................................................... 108.00 25 mm .................................................................... 128.00 40 mm .................................................................... 168.00 50 mm .................................................................... 218.50 (b)
other sizes, an amount equal to the actual cost of relocation.
”.
10. Schedule 6 replaced
Schedule 6 is repealed and the following Schedule is inserted instead —
“ Schedule 6 — Fees
[bll. 9(5) and (5a), 17(2), 21, 22 and 24(1) and (2)]
$
1. (a) Reading of meter........................................................ 7.50
(b) Urgent reading of meter............................................. 13.00 (c)
Electronic lodgment of a combined request for a single statement, reading of meter and orders and requisitions.................................................................
21.50
(d) Electronic lodgment of a combined request for a single statement, urgent reading of meter and orders and requisitions ............................................... 27.00
| 3376 | GOVERNMENT GAZETTE, WA | [29 June 2000 |
Water Agencies Amendment By-laws 2000
Part 5 Metropolitan Water Authority (Miscellaneous) By-laws 1982
amendedbl. 10 $
(e) Lodgment other than under paragraph (c) of a combined request for a single statement, reading of
meter and orders and requisitions .............................. 27.00 (f) Lodgment other than under paragraph (d) of a combined request for a single statement, urgent
reading of meter and orders and requisitions............. 32.00 (g) Provision of information other than under paragraphs (a) to (f) involving research or investigation of 15 minutes or more — per hour or
part of an hour............................................................ 27.00
2. (a) Supply of copy of, or extract from, records or plans (other than those stored in digital format) under section 102(3) of Water Agencies (Powers) Act 1984 —
A1 film....................................................................... 13.20 A1 paper..................................................................... 10.45 A2 paper..................................................................... 8.25 A3 paper..................................................................... 7.15 A4 paper..................................................................... 7.15
(b) Property sewer diagram (per A4 copy) ...................... 7.15 (c) Additional fee (A4 only) for facsimile transmission . 4.40 3. Hydrant standpipes —
(a) application fee............................................................ 71.50
(b) hire fee for month or part of month —
small standpipe .......................................................... 95.50 large standpipe — low volume (not metered).......................................... 115.00 medium volume (not metered)................................... 305.50
high volume (metered)............................................... 4. (a) Reconnection .............................................................
537.50
76.50
(b) Restoration of water supply ....................................... 76.50 5. Fee under section 148 of Metropolitan Water Supply, Sewerage, and Drainage Act 1909 in respect of land on which it is proposed to —
(a) construct a new single residential building................ 57.50
29 June 2000] GOVERNMENT GAZETTE, WA 3377 Water Agencies Amendment By-laws 2000
Metropolitan Water Authority (Miscellaneous) By-laws 1982 Part 5 amended
bl. 10
$
(b) alter an existing single residential building at a cost, as assessed by the Corporation, of over
$22 500 — per $1 000 of the cost so assessed, up
to a maximum of $57.50 ............................................ 1.80 (c) construct or alter a building other than a single residential building, the cost of which construction
or alteration the Corporation assesses to be over $22 500, an amount for each $1 000 of the cost assessed —
up to $1 000 000 ........................................................ 1.60 over $1 000 000 but not over $10 000 000 ................ 1.05 over $10 000 000 but not over $50 000 000 .............. 0.55
over $50 000 000 ....................................................... water supply under by-law 9(5a) — on redevelopment 0.25 6. Fee for application for disconnection or reconnection of
or subdivision .................................................................... 108.50
”.
| 3378 | GOVERNMENT GAZETTE, WA | [29 June 2000 |
Water Agencies Amendment By-laws 2000
Part 6 Metropolitan Water Supply, Sewerage and Drainage By-laws
1981 amendedbl. 11
Part 6 — Metropolitan Water Supply, Sewerage and
Drainage By-laws 1981 amended
11. Schedule C replaced
Metropolitan Water Supply, Sewerage and is inserted instead —
Schedule C to the
“
Schedule C — Fees
$
1. Fees to be paid in respect of proposals to carry out plumbing works —
(a) for works to be connected to the sewer — (i) single residential building —
(I) one major fixture......................................... 74.50 (II) each additional major fixture ...................... 18.50
(III) reinspection .............................................. ... 41.25 (ii) other than single residential building — single storey —
(I) one major fixture......................................... 115.00 (II) each additional major fixture ...................... 38.50
(III) reinspection ................................................. 63.25 (iii) other than single residential building — more than one storey — fee per floor —
(I) one major fixture on floor ........................... 190.50 (II) each additional major fixture on floor......... 63.50
(III) reinspection ................................................. 105.05
(b) for works to be connected to a septic tank —
(i) one major fixture................................................... 45.00 (ii) each additional major fixture ................................ 22.50 2. Fee for installation of sewer junction —
100 mm sewer junction .............................................. 281.00 150 mm sewer junction .............................................. 348.50
3. Fees for authorisation of materials, fittings and fixtures —
(a) application —
(i) first item of product type ...................................... 400.40
29 June 2000] GOVERNMENT GAZETTE, WA 3379 Water Agencies Amendment By-laws 2000
Metropolitan Water Supply, Sewerage and Drainage By-laws Part 6 1981 amended
bl. 11
$
(ii) each additional item of product type .................... hour or part of an hour) ..............................................
55.55
(b) examination, testing, inspection or evaluation (per
93.50
5. (a) Fee for installing a meter under by-law 6.7.1A.1......... 227.00 (b) Fee for assessing a meter under by-law 6.7.1A.3....... 162.00 (c) Fee for assessing a meter and installing a new meter under by-law 6.7.1A.4................................................ 211.00 6. Fee for installation of temporary building standpipe ........... 95.70 7. Fee for inspection of work under by-law 30.9.4 — (a) single residential building .......................................... 41.25 (b) other than single residential building — single storey 63.25 (c) other than single residential building — more than one storey — fee per floor.......................................... 105.05 8. Fee for book of forms of —
(a) notice and certificate of completion and compliance 19.25 (b) multi-entry plumbing certificate................................. 7.15 9. Fees for the provision of plan sheets for preparation of diagrams of property sewer installations —
(a) A4 size (per pad of 25 sheets) .................................... 4.40 (b) A3 size (per pad of 25 sheets) .................................... 8.25 (c) A1 size (per sheet)...................................................... 1.65
”.
[* Reprinted as at 19 May 1997.
For amendments to 23 June 2000 see 1999 Index to
Legislation of Western Australia, Table 4, pp. 186-9.]
K. D. HAMES, Minister for Water Resources.