Warrandyte High School Council v Ian Delbridge Pty Ltd
[1991] HCATrans 146
..
, "" . '
~
•
IN THE HIGH COURT OF AUSTRALIA
Office of the Registry
Melbourne No M49 of 1990 B e t w e e n -
WARRANDYTE HIGH SCHOOL COUNCIL
Applicant
and
IAN DELBRIDGE PTY LTD
Respondent
Application for special leave
to appeal
MASON CJ
DAWSON J
McHUGH J
| Warrandyte | 1 | 7/6/91 |
TRANSCRIPT OF PROCEEDINGS
AT MELBOURNE ON FRIDAY, 7 JUNE 1991, AT 3.57 PM
Copyright in the High Court of Australia
MR G.H. GOLVAN: If the Court pleases, I appear with my
learned friend, MR J. NAYAR, on behalf of the
applicant. (instructed by Wainwright Ryan)
MR B.J. SHAW, QC: If the Court pleases, I appear with my
learned friend, MR G.J. DIGBY, for the respondent.
(instructed by Sly & Weigall).
| MASON CJ: | Mr Golvan. |
| MR GOLVAN: | If the Court pleases, would it be of assistance |
if I provided the Court with a brief outline of the
argument?
MASON CJ: Yes.
| MR GOLVAN: | I have also provided the Court with a chronology |
of events.
There is an extract from the contract on the
application, if the Court pleases. I also have copies of the entire contract, if that is of any
assistance. The extract - the appropriate clause appears in, of course, the judgment of the Full
Court and also the affidavit material, but it may
be of some assistance - - -
MASON CJ: Yes, you can hand them in, but it is a special
leave application.
| MR GOLVAN: | Yes. | If the Court pleases, the appeal relates |
to the construction of clause 31 of the edition Sb
contract, which is a construction contract which is
widely used throughout Victoria and in other States
of Australia, and has been in use since 1971.It relates to the construction of clause 31, which is the final certificate clause, and it is
submitted that the appeal raises three issues of
significance. The first is whether the final certificate issued by the architect which is
valid certificate on its face, and whether the referred to on page 66 of the appeal book is a finality of that certificate can be impugned by reference to documents delivered with it. In essence, clause 3l(b) of the contract
provides for the architect issuing a final
certificate to the builder, a copy to theproprietor and a statement to the builder showing
the difference between the amount of the final
claim by the builder and the amount of the final
certificate. What is submitted is that if the final certificate is a valid certificate on its
face and complies with clause 3l(e) of the
conditions of the contract, then the finality of
that certificate cannot be impugned by reference to
| Warrandyte | 7/6/91 |
the contract summary, which is delivered with the
final certificate, but does not form part of the
final certificate.
That point raises a matter of general
significance because if a certificate is valid on
its face, has been issued at the appropriate time,
namely after the final claim of the builder,contains all the requirements of a final
certificate under clause 3l(e), it is submitted
that the certificate cannot be impugned.
The decision of the Full Court was, in
essence, that the finality of the certificate could
be impugned after the delivery of the certificate
by referring to other documents served with the
certificate.
It creates, in relation to a major
construction contract, a great deal of uncertainty
because it raises the significant possibility inthis contract that a contract which is intended to
be final and certain can be impugned - or a
certificate which is intended to be final and
certain can be impugned - some considerable time
after the certificate has been presented, by
reference to documents which are contained with the
certificate, showing that in some cases the
architect did not give final consideration to every
single item of the builder's claim.
It is submitted that both parties in this case
treated the final certificate as a valid
certificate.
| DAWSON J: | What was the status of the document that went |
with the final certificate saying that adjustments
had to be made?
| MR GOLVAN: | The status of those documents are that they do |
not form part of the final certificate. In other
words, after the architect has issued a .final
certificate then he is functus officio, and whether he wants to make adjustments or does not want to
make adjustments, he cannot make adjustments.
What he is entitled to do is to gratuitously
recommend to the proprietor that if the builder is
able to establish that the builder is entitled to
adjustments made after the certificate has been
issued, then he will be paid extra by the
proprietor. But he has no ability to amend the
certificate, or indeed present a new certificate.
This is a case where the architect issued the
certificate after there had been requests by the
architect upon the builder to provide.all relevant
| Warrandyte | 3 | 7/6/91 |
and necessary information. At page 7 of the appeal book the judge at first instance concluded that:
the architect over a period of time
endeavoured to obtain information from the
builder, and ultimately in the absence of that
information made a proper determination of the
amount due.
It is submitted on behalf of the applicant
that the Full Court, in so far as it sought to
impugn the certificate by reference to other
documents, was not entitled to do so.
MASON CJ: But was not the document, by reference to which
it was impugned, the contract summary, referred to
in the final certificate itself?
| MR GOLVAN: | The final certificate appears at page 66 of the |
appeal book, and the only reference to the contract
summary is adjacent to the total of the amountpreviously certified by the builder. It merely
says "(REFER CONTRACT SUMMARY)", so that it is not
indicated by the certificate that the contract
summary was intended to form part of the
certificate, and indeed the contract summary is a
document that is required to be provided with the
certificate under clause 3l(b).
DAWSON J: But that cannot be so because the final
certificate, or what purported to be a final
certificate, was accompanied by a letter saying,"Adjustment to the final balance will be made when
you have submitted the information requested."
| MR GOLVAN: | Yes, but the letter, it is submitted, |
Your Honour, does not form part of the certificate.
DAWSON J: But when you have the letter, the reference in
the final certificate to the contract summary, the
letter referring to both the contract summary and
the final certificate, it would be very hard to say that the documents should be considered separately, would it not, the contention being that what was said to be a final certificate was not in fact a
final certificate.
| MR GOLVAN: | That is what the position was of the Full Court, |
but the applicant's position is that it clearly was
intended to be a final certificate under the
contract. It complied with all the requirements of
the final certificate - - -
| DAWSON J: Can I just ask you this. | If in fact it was not |
final, it was not a final certificate, was it, no
matter what it was headed? Is that right?
| Warrandyte | 4 | 7/6/91 |
MR GOLVAN: If the certificate, on its face, was not a final
certificate - - -
| DAWSON J: No, no, just forget how it comes about. | If in |
fact the final certificate was not certifying a
final sum, it was not a final certificate. Do you agree with that?
| MR GOLVAN: | If it was not certifying a final sum it was not |
a final certificate, subject to the provisions of
clause 3l(i), which entitle amendments to be made,
or alterations to be made, by reason of any
accidental or erroneous conclusion or inclusion of
any work, materials, goods or figures, or any other
arithmetical error in any computation.
The actual contract summary is included as
part of the application book and it indicates that
the nature of the kinds of things that the
architect had to deal with and the complaints are
made about, for example, at page 87. We are dealing with something like 187 variations. In one
variation the architect states in the contract
summary "DETAILS REQUESTED HAVE NOT BEEN RECEIVED"; 126 on page 88 "PROVISIONAL INFORMATION REQUESTED OF EDUC. HAS NOT BEEN RECEIVED". It is
the same in relation to several other items.
So what the judge at first instance concluded
was that the architect had sought that information,
the information had not been provided and therefore
he had provided a final certificate as best as he
could and that the letter that was contained with
the final certificate and the contract summary that
was included with the contract certificate
constituted an offer made by the architect to the
builder to make adjustments to the final balance -
not to issue a new certificate, in my respectful
submission, but to make adjustments to the final
balance, if the builder could satisfy the architect
that he in fact was entitled to additional sums by
reason of providing information that he should have provided some time earlier at the frequent request
of the architect.
So what is submitted the effect of that letter
and the contract summary is, is that it contains a
gratuitous offer on behalf of the architect, and
not an unfair offer, to the builder to give him an
additional benefit if he could show that in fact he
was entitled to more, by reason of the information
being provided to the architect. It did not
contain an indication that it was going to be a
fresh final certificate - - -
DAWSON J: But it did indicate that the sum certified as
final was not final.
| Warrandyte | 7/6/91 |
MR GOLVAN: | In my respectful submission, that is not the case, Your Honour. The sum certified as final was |
| final. In other words, there was no provision, or the sum was not of a provisional nature. It was clearly expressed to be a final balance due by the | |
| builder to the proprietor. |
DAWSON J: But the architect said the adjustment to the
final balance will be made when you have submitted
the information requested.
| MR GOLVAN: | Yes, and that is consistent not with the amount |
certified not being final, but it is consistent
with the architect giving the builder an
opportunity to provide additional information on
the basis that adjustments - that he would
recommend to the proprietor the making of credits
to the proprietor in the event that information
supplied by the proprietor indicated he was
entitled to adjustments.
But the force of that offer depended upon the
proposal made in the letter. It did not depend
upon the certificate itself being anything other
than a final certificate. The certificate in the form provided was a final certificate. It showed a
clear unequivocal balance that was due one way or
the other; it complied with clause 3l(e) in
relation to what ought to be part of a final
certificate, and that is the point for argument as
to whether or not one is entitled to look at
surrounding correspondence, such as letters or
surrounding documentation, to ascertain whether infact the architect may have intended to have made
alterations to the final figure. In my respectful
submission, he is not entitled to do so.
For example, if the architect, having issued
that final certificate, then subsequently said to
the builder, "I think that we have not given the
proprietor enough; I think that we ought to give the proprietor a bit more money, and I am going to
some additional money because I now realize there issue a fresh certificate and give the proprietor are additional errors in my final certificate". The builder could said, and would have said, in my respectful submission, "Well, you can't do
that because you have issued a final certificate. Having issued that final certificate you are functus officio, you can't do any more about the amount that forms part of the final certificate".
MASON CJ: But clearly enough the architect did not see it
that way because if you look at the letter, the
| Warrandyte | 6 | 7/6/91 |
last sentence in the second paragraph of the letter
says:
The adjustment to the final balance will
be made when you have submitted the
information requested.
So that it seems that the architect was issuing the
certificate, if one can use the description, as a
provisional final certificate, which would be
replaced or supplemented by an actual final
certificate in the event that the builder submitted
the information requested resulting in the
adjustment contemplated.
| MR GOLVAN: | The other interpretation, in my respectful |
submission, the interpretation that is properly
open from the construction of the letter, is that
he is making an offer to the builder that
"Notwithstanding that you have not provided all the
necessary information that enables me to deal
finally with every - - -
MASON CJ: But it is not really susceptible of that
interpretation because that sentence indicates that
an adjustment to the final balance in the
certificate will be made when the information
requested is submitted.
MR GOLVAN: It raises two possibilities: firstly, that
whether he says that he is going to make an
adjustment to the final balance or does not say it,
he is not entitled to make an adjustment to the
final balance, because having issued a final
certificate he cannot make an adjustment to it. It
is a bit like - - -
MASON CJ: But that is the point, is it not? Is it a final
certificate, in the circumstances? You are assuming it is a final certificate.
| MR GOLVAN: Well, it is a final certificate because it |
clearly was intended to be the final certificate.
MASON CJ: But I am suggesting to you that is not the
interpretation that you put upon it when you read
it in the light of the accompanying letter.
MR GOLVAN: With respect, Your Honour, the other two
arguments that are available are that that merely
establishes the architect's right under clause
3l(i) to adjust erroneous inclusions or exclusions
from the certificate. In other words - and the
evidence in the case was, indeed, that was the way
he was treating that particular comment, that he
saw that as his entitlement, that if it could be
shown that what he placed in the certificate was
| Warrandyte | 7/6/91 |
erroneous, that he was entitled to adjust the
figure by reference to clause 3l(i)(iii), whichgives him that possibility - - -
MASON CJ: | I must say, at this stage, that the tenor of the discussion that has taken place so far between you |
| and the Bench does not indicate that this is a | |
| special leave point. | |
| MR GOLVAN: | It is one of the three points that arise in this |
MASON CJ: Perhaps we might move on to the next point.
McHUGH J: Grounds 2 and 3 do not really arise unless you
make good this point.
| MR GOLVAN: | I have to succeed on an arguable or a special |
leave point that it is a valid final certificate.
McHUGH J: Well, if the foundation is shaky, that is the end
of the case, from the point of view of special
leave, is it not?
| MR GOLVAN: | It is submitted that the point raised by the |
validity of the certificate is arguable.
DAWSON J: Apart from anything else, Mr Golvan, the purpose
of your wanting to say that this was in fact a
final certificate is to establish that time runs so
that the builder was no longer able to give notice
of a dispute.
MR GOLVAN: That is so.
DAWSON J: But of course the very nature of the document
shows that there were disputes outstanding. The
document that purports to be a final certificate
refers to the contract summary and the contract
summary refers to amounts which, if not in dispute,
have not been settled.
| MR GOLVAN: | Yes, and the position is that the builder was |
entitled to refer those disputes to arbitration if
he believed that there were disputes. It is
admitted that there were disputes. The situation was that the architect had sought information that
the builder was obliged to provide and that
information had not been provided.
But if there were disputes, the builder was
entitled to refer those disputes to arbitration
within the time limit stipulated.
| MCHUGH J: | By clause 3l(i). |
| Warrandyte | 8 | 7/6/91 |
| MR GOLVAN: | By clause 3l(i). | Namely, within 14 days after |
receipt of the certificate.
McHUGH J: But what he did was not intended to trigger that
clause, was it? There had been no notice of
dispute given under clause 32, had there?
MR GOLVAN: That is the argument in the case, Your Honour,
because in fact the builder then gave, some two and
a half months after receiving the certificate, a
notice of dispute, not challenging the validity of
the final certificate but in fact challenging the
amount that was certified under the terms.
| McHUGH J: | No, what I was putting to you was that nothing |
that the architect did, either in the certificate
or the accompanying material, was intended to do
anything under 31(i), was it?
| MR GOLVAN: | No, it was not. | But His Honour Justice Dawson |
said the position was that there were disputes at
the time that the certificate was issued.
DAWSON J: What I was getting at was that 32(i) is
predicated upon there being a final certificate
because that having been given and it being final,that is the end of the matter unless a notice of dispute is given within the specified time. One
can understand that.
But here you have the builder getting these
documents showing that there are matters
outstanding. He would not dream that time was
going to run against him in the circumstances.
MR GOLVAN: Well, he did, because the notice of dispute that
was issued in the case treated the final
certificate as being a valid final certificate.
The notice of dispute is on page 67 of the
application book - it runs from page 68 to
page 70/71. In fact the schedule is on page 70/71
and it does not challenge the validity of the final certificate. What it seeks to do is challenge the
amount that the architect certified as the balance
outstanding on the final certificate.
Indeed, as is apparent from the judgment of
the judge at first instance, the issue in the case
was not that the builder ever thought that it was
not a valid final certificate but that the builder
said that he entered into an arrangement with the
architect prior to the expiration of the 14-day
period, that time would not run under the contract
to allow negotiations to occur and that was a major
issue of credit between the parties, and the judge
at first instance did not accept the builder's
evidence on that aspect.
| Warrandyte | 9 | 7/6/91 |
That is consistent with, in fact, the opposite conclusion, namely that the builder did treat that
as being a valid and binding final certificate and
the builder says he then entered into an
arrangement with the architect that time would not run under that certificate while negotiations were
taking place.
So that it is a case where certainly both
parties treated the final certificate as a valid
final certificate and it is our respectfulsubmission that they were perfectly justified in
doing so because the quality of the final
certificate is essentially set out in clause 3l(e),
that is that it has to contain the contract sum
adjusted as necessary, according to the terms and conditions of the contract and the total value of all previous certificates issued and stipulate the
difference between the two sums, the balance due
one way or the other. That is exactly what the
certificate does.
Once the certificate has been issued in those
sorts of terms it is a valid and binding final
certificate and cannot be impugned, because it
raises the spectre that instead of being a
conclusive document and a final document, as it is
intended to be, that well after the document is
issued parties can go behind the certificate, lookat other documents that the architect might use in
the preparation of the certificate, and say, "Look,
that certificate cannot be final because not everysingle claim that you have assessed in that
certificate were you able to assess with the
appropriate degree of finality". And that would - - -
McHUGH J: But that does not follow at all, does it, from
what happened in this case, or what the Full Court
decided. They had a document which was headed "Final certificate" together with a contract
summary to which the certificate itself referred, together with a letter, and when you look at those
three documents they indicate that there was nofinal certificate within the meaning of 3l(e).
| MR GOLVAN: | The very first sentence of the letter says: |
Enclosed find contract summary and final
certificate.
Which shows a final balance of $28,000 et cetera payable to the proprietor.
McHUGH J: If I purport to give you a licence to my house
and I in fact give you exclusive possession, it does not mean that you have a licence, that you
| Warrandyte | 10 | 7/6/91 |
have a lease. So the fact that you called it final certificate means nothing if in fact it is not a
final certificate.
| MR GOLVAN: | That is the issue for argument, as to whether it |
is or is not a final certificate, and what the
applicant says is that it is a final certificate
because a final certificate is a creature of the
contract and so long as it has the characteristics
required under clause 3l(e) it is a final
certificate; that you cannot go behind the
certificate to ascertain whether there may be some
matters that the architect had in mind that he
could not deal with finally.
Once the final certificate is issued the
architect is functus officio, so that the
deficiency in the letter is the architect is saying
that he is going to make adjustment to the final
balance; he is not entitled to make adjustment to
the final balance. It is not a deficiency in the
final certificate, it is a deficiency in the
architect's assessment of what he can do after the
final certificate has been issued and received by
the builder.
The other two matters, if I can - - -
DAWSON J: Well, you have got the difficulties of that very
badly drafted clause, have you not?
| MR GOLVAN: | It is a badly drafted clause, but it is, as the |
High Court said, a vital clause in the contract and
it is submitted that some meaning should be
appropriated to the clause. In other words, it
ought not to be, if at all possible, regarded as
being an uncertain clause. If one looks at
clause 3l(i), together with clause 3l(e), one can
get a reasonable - - -
DAWSON J: It is just a question of construction, is it not?
There is no general principle involved and one
clause, be confident one had given it the right could not, having regard to the wording of the construction, in terms of special leave, I am speaking.
MR GOLVAN: Well, were it is just a contract between the
parties, I would say yes.
DAWSON J: But I know it is a standard form of contract, but
it is a standard form of contract which has been
varied from time to time, there is no great
difficulty about that. This is Mark No something
or other, is it not?
| Warrandyte | 11 | 7/6/91 |
MR GOLVAN: Well, it is edition Sb; there have been five
previous editions. But it is a contract that has been in existence since 1971, it is a major
construction contract, and clause 3l(i), which is
the clause that gives the conclusive evidence
attribute to the final certificate, is a critical
clause in that contract, and the parties are
entitled to know how that clause ought to be
interpreted.
There is a decision by Mr Justice Legoe, of the Supreme Court of South Australia -
MASON CJ: Before you get to that, the position has been
established that you have got to succeed on this
first point before the second and third points
arise.
In the course of debate the Court has taken up with you the arguments that you presented in favour of challenging the correctness of the decision of
the Full Court on the first point. If you cannot
satisfy us on that point that your case is
sufficiently arguable, then of course special leave
will be refused because of your inability to mount
a sufficient challenge on that point.
Can we come back to it, and can I ask you, is
there anything else you want to say to us with a
view to persuading us that you do have a
sufficiently arguable case on that question?
| MR GOLVAN: | Can I just ask the Court whether the principal |
concern is whether it is a point of adequate
significance or whether the decision of the Full
Court is attended with sufficient doubt?
| MASON CJ: The latter. | In other words, prima facie it looks |
as if the Full Court is correct in concluding that
this was not a final certificate.
MR GOLVAN: All I can really add to what I have already
appears to have not concerned itself with the submitted to the Court is that the Full Court nature of a final certificate as defined by
clause 3l(e) of the contract.In the course of the judgment the Full Court has said there is nothing that indicates what
constitutes a final certificate, and in fact clause 3l(e) does stipulate specifically what a final certificate must contain, and the certificate in this case contains all the attributes of a final certificate in accordance with the contract. It is a creature of the contract, and once a
conclusion is formed that it is intended to be a
| Warrandyte | 12 | 7/6/91 |
final certificate for the purpose of the contract,
in our respectful submission it constitutes a final
certificate, and that an approach by the architect
whereby he had in mind making adjustments to the
final balance in the future does not derogate from
the fact that the final certificate is an
appropriate final certificate. It merely indicates
an incorrect approach in law so far as the
architect is concerned.
In my respectful submission, he has either
taken an approach that he can make changes to the
final balance, which he is not entitled to make
because he is functus officio, which seems to be
what actually did occur. He has taken the approach that notwithstanding that a final certificate has
been issued he is entitled to recommend to the
proprietor, if the builder could satisfy him that
the builder has been badly done by as a result of information that had not previously been provided but subsequently provided, that the builder isentitled to more, and recommend to the proprietor
that the builder be paid more.
Nothing prevents a proprietor from paying a
builder an additional amount of money,
notwithstanding that the architect may have
certified a lesser amount in the final certificate.
The final point is that the architect, in any
event, is entitled to exercise his right under
clause 3l(i)(iii) to adjust erroneous exclusions
from evaluation of the work that he has given.
But the principal point is that all those
matters are outside the face of the final
certificate, which is a valid and, in accordance
with what the Full Court said, an unambiguous final
certificate in the sense that it shows a final
balance due one way or the other, and can form the
subject of being a debt from the builder to the
proprietor, and is conclusive. Other than that, I really do not feel I have
anything more to add to that. If the Court
pleases.
| MASON CJ: | Thank you. | The Court need not trouble you, |
Mr Shaw.
The primary and fundamental question sought to
be raised by the applicant in this application is
whether the Full Court of the Supreme Court was
correct in concluding that a certificate issued by
an architect under a building contract purporting
to be a Final Certificate was in truth a Final
Certificate or a provisional certificate of some
| Warrandyte - | 13 | 7/6/91 |
kind. Unless the applicant succeeds in obtaining a
favourable answer to this question, the proposed
appeal will fail.
In our opinion the conclusion reached by the Full Court upon this question was not attended with
sufficient doubt to justify the grant of special
leave to appeal. The application is therefore refused.
| MR SHAW: | I ask for costs, if the Court pleases. | ||
| MASON CJ: |
|
application for special leave is refused with
costs.
AT 4.32 PM THE MATTER WAS ADJOURNED SINE DIE
| Warrandyte | 14 | 7/6/91 |
Key Legal Topics
Areas of Law
-
Contract Law
-
Statutory Interpretation
Legal Concepts
-
Appeal
-
Breach
-
Contract Formation
-
Remedies
-
Statutory Construction
0
0
0