| CITATION: | Walsh v Australian Building and Construction Group [2016] QCAT 187 |
| PARTIES: | Michael Walsh (Applicant) |
| v | |
| Australian Building and Construction Group (Respondent) |
| APPLICATION NUMBER: | BDL146-16 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Senior Member Brown |
| DELIVERED ON: | 20 June 2016 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The application is dismissed; 2. The applicant is at liberty to file an application for domestic building dispute; 3. Any application filed in accordance with order 2 must be accompanied by evidence of compliance by the applicant with s 77(2) of the Queensland Building and Construction Commission Act 1991; 4. If an application is commenced in accordance with order 2, all documents filed in this proceeding will be taken to have been filed in the further proceeding. |
| CATCHWORDS: | JURISDICTION – where proceeding for building dispute commenced as minor civil dispute – where applicant did not comply with a process established by the Queensland Building and Construction Commission to attempt to resolve a building dispute before commencing proceeding – where provision in enabling Act has substantive effect – whether Tribunal has power to waive compliance with substantive provision of enabling Act – where application dismissed for lack of jurisdiction Queensland Building and Construction Commission Act 1991 (Qld), s 77 Chief Executive, Department of Justice and Attorney-General v Campaigntrack Victoria Pty Ltd & Ors [2015] QCATA 61 |
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REASONS FOR DECISION
Michael Walsh and The Tiny Tradies Group Pty Ltd (who I will collectively refer to as ‘Tiny Tradies’) say that Tiny Tradies contracted with Australian Building & Construction Group (‘ABC Group’) to undertake painting work at domestic premises. Tiny Tradies says that it was not paid for work it has performed.
Tiny Tradies filed application for a minor civil dispute claiming an amount of $12,121.45 from ABC Group. ABC Group filed a response in which it says that the applicant named in the application is ‘Michael Walsh (The Tiny Tradies Group Pty Ltd)’. ABC Group says that the contract it had for the performance of the painting work (‘the contract’) was with ‘Tiny Tradies Painting’. ABC Group says that Michael Walsh and The Tiny Tradies Group Pty Ltd do not have standing to bring the application as they were not parties to the contract.
In the alternative, ABC Group says that the painting work carried out by Tiny Tradies is defective and claims a set off for the costs of rectification.
On 10 June 2016 the application came before the Tribunal. An Adjudicator directed that Tiny Tradies file…
Keep reading for free
Create a free CaseChat account to read Walsh v Australian Building and Construction Group and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] QCAT 187
- Decision Date
CaseChat Overview and Summary
The central issue was whether the Tribunal had the power to waive compliance with a substantive provision of the enabling Act, which required Walsh to attempt to resolve his dispute with Australian Building and Construction Group through the Queensland Building and Construction Commission before commencing proceedings in the Tribunal. The appeal hinged on whether the Tribunal had the discretion to overlook the requirement for Walsh to first attempt to resolve the dispute through the Commission.
The Court held that the Tribunal did not have the power to waive compliance with the substantive provision of the enabling Act. The Court found that the requirement to attempt to resolve the dispute through the Commission before commencing proceedings in the Tribunal had substantive effect and could not be waived by the Tribunal. The Court held that the Tribunal’s power to determine its own jurisdiction was limited by the provisions of the enabling Act, and that the Act did not confer on the Tribunal the power to waive compliance with its substantive provisions. Consequently, the Court held that the Tribunal did not have the power to hear the matter and dismissed the appeal. The Court ordered that Walsh could recommence the proceeding, provided he complied with the requirement to attempt to resolve the dispute through the Commission before commencing proceedings in the Tribunal. If Walsh recommenced the proceeding, the Court ordered that any documents filed in the original proceeding would be taken to have been filed in the further proceeding.
Orders
Orders of the court
1. The application is dismissed;
2. The applicant is at liberty to file an application for domestic building dispute;
3. Any application filed in accordance with order 2 must be accompanied by evidence of compliance by the applicant with s 77(2) of the Queensland Building and Construction Commission Act 1991;
4. If an application is commenced in accordance with order 2, all documents filed in this proceeding will be taken to have been filed in the further proceeding.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.