Walker v City of Adelaide; Adelaide Civil Pty Ltd v Walker

Link copied
Case Copied 51 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Full Court: Civil)

WALKER & ANOR v CITY OF ADELAIDE & ORS; ADELAIDE CIVIL PTY LTD v WALKER & ORS

Judgment of The Full Court

(The Honourable Chief Justice Doyle, The Honourable Justice Vanstone and The Honourable Justice White)

9 June 2005

TORTS - NEGLIGENCE - ESSENTIALS OF  ACTION FOR NEGLIGENCE - DUTY OF CARE - SPECIAL RELATIONSHIPS AND DUTIES - PROFESSIONAL PERSONS

STATUTES - ACTS OF PARLIAMENT - ENFORCEMENT OF STATUTORY RIGHTS AND REMEDIES - BREACH OF STATUTORY DUTY

PROFESSIONS AND TRADES - OTHER PROFESSIONS, TRADES OR CALLINGS - ENGINEERS

First appellant owned, and second appellant operated a business on, land with a building the western wall of which was adjacent to land owned by Estoril Developments Pty Ltd – First respondent approved development application for subdivision of Estoril’s land - Estoril engaged fifth respondent as consulting engineer and engaged third appellant to carry out some excavation – Plan for subdivision included a public road – Part of Estoril’s land transferred to first respondent for public road – Third appellant dug public lighting conduit trench adjacent to western wall on first appellant’s land – Third appellant discovered concrete protrusions from base of wall – Fifth respondent told third appellant to stop excavation of the trench – Third appellant removed protrusions – Western wall on first appellant’s land collapsed into trench – Trial Judge found third appellant liable in negligence – First and second appellants appealed against dismissal of their claim against first respondent – Consideration of requirement of s 60 of the Development Act 1993 (SA) that notice be given where a building owner proposes to carry out building work involving an excavation of a prescribed kind – First respondent did not propose to carry out building work – First respondent did not authorise third appellant to excavate trench adjacent to wall – First respondent not required to give notice – Third appellant appealed against dismissal of the claim against second respondent as supervising engineer – Second respondent had not given final approval for excavation of trench – Plans indicating position of trench were indicative only – Second respondent owed no duty of care to first and second appellants or if it owed such a duty it did not breach that duty – Third appellant argued that Estoril was a building owner proposing building work and therefore was required to give notice under s 60 of the Development Act – Regulations promulgated for the purpose of s 60 did not add to the definition of building work applicable to s 72 – Excavation of the trench did not constitute building work – Appeals by first and second appellants, and by third appellants, dismissed.

Development Act 1993 s 4, s 33, s 34, s 60 and s 72; Development Regulations 1993 reg 75; Local Government Act 1934; Local Government Act 1999 s 208 and s 212; Wrongs Act 1936 s 25, referred to.
Pantalone v Alaouie (1989) 18 NSWLR 119, discussed.
Voli v Inglewood…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Walker v City of Adelaide; Adelaide Civil Pty Ltd v Walker and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2005] SASC 206
Decision Date

CaseChat Overview and Summary

The appeal in Walker v City of Adelaide; Adelaide Civil Pty Ltd v Walker involved multiple parties, including the Walkers (first and second appellants), the City of Adelaide (first respondent), Estoril Developments Pty Ltd (second respondent), and Adelaide Civil Pty Ltd (ADCIV, third respondent). The dispute centered on the collapse of a western wall on the Walkers' property, which occurred during excavation work adjacent to the wall, performed by a third party on behalf of Estoril. The Walkers sought damages for breach of statutory duty, alleging that the City of Adelaide failed to provide required notices under the Development Act 1993 (SA) regarding the excavation work. The third party also appealed against the dismissal of their claim, arguing that Estoril, as the building owner, should have provided the necessary notices. The court was tasked with determining whether the City of Adelaide was obligated to provide statutory notice under s 60 of the Development Act and whether Estoril or the third party had a duty of care towards the Walkers.

The primary legal issue was whether the City of Adelaide was required to give notice under s 60 of the Development Act regarding the excavation work. The court had to interpret the scope of s 60 and determine if it applied to the situation where the City of Adelaide approved the development but did not directly carry out the excavation. Additionally, the court considered whether Estoril or the third party owed a duty of care to the Walkers, particularly in light of the statutory obligations. The court also examined the role of ADCIV as a supervising engineer and whether it had any duty towards the Walkers. The appeals hinged on the interpretation of statutory obligations and the scope of duties owed by the parties involved.

The court concluded that the City of Adelaide was not required to give notice under s 60 of the Development Act because it did not propose to carry out the building work that involved the excavation. The court found that the third party, who performed the excavation, did not owe a duty of care to the Walkers as it had not given final approval for the excavation of the trench. The court also held that Estoril, as the building owner, was not required to give notice because the excavation did not constitute building work under the relevant regulations. The court found that the third party's actions did not breach any duty of care it may have owed to the Walkers. As a result, the appeals by both the Walkers and the third party were dismissed.

The court's decision dismissed the appeals by both the Walkers and the third party, affirming the lower court's ruling that no breach of statutory duty occurred. The court held that the City of Adelaide was not obligated to provide notice under s 60 of the Development Act, and that neither Estoril nor the third party owed a duty of care to the Walkers. The final orders of the court upheld the dismissal of the claims against the City of Adelaide, Estoril, and the third party.

Orders

Orders of the court

Background

Background to the litigation

The appellants now appeal against the Judge’s dismissal of their claim for breach of statutory duty against the Corporation. No complaint was made about the decision of the Judge with respect to the alleged negligence of, or nuisance by, the Corporation. ADCIV appeals against the amount of the judgment in favour of the appellants entered against it, or alternatively, against the dismissal of its claim to contribution from ABG. ADCIV’s submission was that the Judge should have found that ABG had breached a duty of care which it owed to the appellants. Both appeals were heard together.Background Circumstances It is appropriate to set out some of the factual circumstances and some of the Judge’s findings which are common to both appeals. In February 1999 Estoril purchased the adjoining land. Shortly afterwards Performa, on behalf of Estoril, lodged with the Corporation the development application to which I referred earlier. As the Walker land and the adjoining land were located within the City of Adelaide, the Corporation was the “relevant authority” from which approval for the subdivision and development had to be obtained.[1][1] Development Act 1993, ss 33 and 34. The application proposed the demolition of an existing building and the subdivision of the site into 20 residential allotments, together with an internal private road and a public road, Myers Lane, on the eastern boundary of the land. It was proposed that Myers Lane would run in a northerly direction from Gilbert Street and that its eastern boundary would be contiguous with the western boundary of the Walker land (and therefore with the western wall of the building on that land). On 5 May 1999 the Corporation issued an approval for the development but subject to certain conditions. Condition No 7 specified:The proposed public road shall be constructed to the Corporation’s specification and satisfaction, and at the cost of the applicant prior to acceptance as a public road and will be subject to [a] defects liability period of 12 months from the date of completion.The public road referred to in Condition No 7 is Myers Lane. Prior to obtaining the approval, Estoril had engaged ABG as its engineer for the project. There was no written contract between Estoril and ABG specifying the scope of the work which ABG was to perform. The trial Judge found that the scope of ABG’s work was “in substance”:§Designing and documenting the works, including preparation of plans and specifications.§Obtaining and advising on tenders or quotations.§Preparation of contract documents and seeing to their execution.§Furnishing such other drawings and details as ABG deemed necessary.§Monitoring construction with a view to ensuring compliance with “design intent”. The trial Judge found that the role of ABG in monitoring the construction was to involve periodic inspection and attending, where appropriate, meetings with contractors and suppliers, but that it did not include continuous or detailed supervision such as would be provided by a resident engineer or clerk of works.

Evidence

Evidence before the court

Decision

Reasons for decision

Thus, for this further reason, s 60 did not bind the Corporation to give notice to the appellants. Conclusion In my opinion, each of the appeals should be dismissed.

Ratio Decidendi

Legal principle established

Whilst he was carrying out the excavation, the western wall collapsed partially, into the trench. The Judge accepted that the failure of the wall was a direct result of the excavation of the trench immediately adjacent to it and below the level of the base of the footing supporting the wall. The Claim Against the Corporation As already noted, on the appeal the appellants complained only of the dismissal of their claim for breach of statutory duty. It was submitted that the trial Judge should have found that the Corporation was in breach of an obligation imposed on it by s 60 of the Development Act 1993. Section 60 of the Development Act provides for notice to be given to an adjoining owner where building work is to be carried out which will affect the stability of the land of the adjoining owner. It provides as follows:(1) Where a building owner proposes to carry out building work of a prescribed nature that is, in accordance with the regulations, to be treated for the purposes of this section as building work that affects the stability of other land or premises (the affected land or premises), the following provisions apply:(a) the building owner must, at least 28 days before the building work is commenced, cause to be served on the owner of the affected land or premises a notice of intention to perform the building work and the nature of that work; and(b) the building owner must (in addition to complying with any condition imposed by a relevant authority at the time of approval) take such precautions as may be prescribed to protect the affected land or premises and must, at the request of the owner of the affected land or premises, carry out such other building work in relation to that land or premises as that adjoining owner is authorised by the regulations to require; and(c) nothing in this section relieves the building owner from liability for injury resulting from the performance of any building work.(2)A building owner who fails to comply with a provision under subsection (1) is guilty of an offence.Penalty: Division 6 fine.(3)A building owner may apply to the Court for a determination of what proportion (if any) of the expense incurred by the building owner in the performance of the building work requested by the owner of affected land or premises under subsection (1) should be borne by the owner of that land or premises, and the building owner may recover an amount determined by the Court from the owner of the affected land or premises as a debt. It was submitted that the excavation of the trench on 26 November 1999 came within the description of work to which reg 75(2)(a) of the Development Regulations 1993, promulgated for the purposes of s 60, applied. This is a matter to which I shall return later in these reasons. It was common ground that the Corporation had not given notice of any kind to the appellants. The evidence of the appellants was that, had such notice been given, an engineer would have been retained to give appropriate advice. An engineer gave evidence to the effect that, if so retained, he would have advised relocation of the trench so as to avoid compromising the stability of the western wall.