W.A. Marine Amendment Regulations 2001 (WA)

Case
No judgment structure available for this case.

27 July 2001 GOVERNMENT GAZETTE, WA 3803
Regulations 2001.

TR305*

Western Australian Marine Act 1982

W. A. Marine Amendment Regulations 2001

Made by the Governor in Executive Council.

1.           Citation

These regulations may be cited as the W. A. Marine Amendment

3804 GOVERNMENT GAZETTE, WA 27 July 2001

2.             Commencement

These regulations come into operation on 1 August 2001.

3.            W.A. Marine (Certificates of Competency and Safety

Manning) Regulations 1983 amended

Schedule 3 to the W.A. Marine (Certificates of Competency and

Safety Manning) Regulations 1983* is repealed and the

following Schedule is inserted instead -

IV  

Schedule 3 - Fees

[r. 31 A]

Reg. Subject matter Fee
9(1) Addition or deletion of endorsement: $52
9(2) Approval of foreign certificate: $52
10(1) Revalidation of certificate: $42
14 Issue of replacement certificate:
17(1) Registration of application for Certificate of
Competency (fee includes 2 oral
examinations): $90
17(1) Further examinations if required: $42/examination
oral examination conducted at a place or $84/10ur for an
time outside normal scheduled period or examiner
location (at request of examinee):  $54/hour for
a clerk-
27A(3) Issue of Certificate of Proficiency: $8
28 Determination of manning requirements: $22
29(1) Issue of dispensation: $52

[* Reprinted as at 30 July 1997.

For amendments to 10 July 2001 see 2000 Index to Legislation of Western Australia, Table 4, p. 396.]

4.            W.A. Marine (Hire and Drive Vessels) Regulations 1983

amended

Regulation 4(2)(e) of the W.A. Marine (Hire and Drive Vessels)

Regulations 1983*  is amended as follows:
(a)

in substituted clause 3.1.2(1 )(b) by deleting "$262.90" " $269.50 ";

(b)

in substituted clause 3.1.2(3)(b) by deleting "$130.90" " $134.20 ";

(c)

in substituted clause 3.1.3(m) by deleting "$50.60" and inserting instead -

[* Reprinted as at 9 March 2001.] " $51.70 ".
27 July 2001 GOVERNMENT GAZETTE, WA 3805
5. W.A. Marine (Radiotelephony) Regulations 1981 amended

Regulation 16 of the W.A. Marine (Radiotelephony)

Regulations 1981* is amended as follows:
(a)

in subregulation (2a) by deleting "$250.80" and " $257.40 ";

(b) in subregulation (2b) by deleting "$125.40" and inserting instead -

46

$128.70 ".

[* Reprinted as at 16 February 2001.]

6.             W.A. Marine (Surveys and Certificates of Survey) Regulations 1983 amended

Schedule 1 to the W.A. Marine (Surveys and Certificates of
Survey) Regulations 1983* is repealed and the following
Schedule is inserted instead -

Schedule I - Fees

[r. 4A]

1.             Survey Fees

(a)

Subject to paragraph (b), the standard fees for examination of plans of a vessel, initial surveys and subsequent surveys are as follows -

Length of vessel Examination Initial Subsequent
of plans survey surveys

(metres)

($) () ($)
Not exceeding 5 326.70 458.70 13530
Over 5 but not exceeding 6 378.40 631.40 161.70
Over 6 but not exceeding 7 412.50 889.90 196.90
Over 7 but not exceeding 8 531.30 1 181.40 212.30
Over 8 but not exceeding 9 654.50 1 538.90 227.70
Over 9 but not exceeding 10 767.80 1892.00 240.90
Over 10 but not exceeding 11 946.00 2274.80 265.10
Over 11 but not exceeding 12 1124.20 2663.10 291.50
Over 12 but not exceeding 13 1298.00 3047.00 319.00
Over 13 but not exceeding 14 1481.70 3428.70 343.20
Over 14 but not exceeding 15 1659.90 3813.70 369.60
Over 15 but not exceeding 16 1830.40 4199.80 392.70
Over 16 but not exceeding 17 2007.50 4583.70 420.20
Over l7 but not exceeding l8 2191.20 4967.60 446.60
Over 18 but not exceeding 19 2361.70 5351.50 470.80
Over 19 but not exceeding 20 2539.90 5737.60 499.40
Over 20 but not exceeding 21 2745.60 6150.10 535.70
3806 GOVERNMENT GAZETTE, WA 27 July 2001
Length of vessel Examination Initial Subsequent
of plans survey surveys

(mettes)

() ($) ($)
Over 21 but not exceeding 22 2952.40 6562.60 577.50
Over 22 but not exceeding 23 3159.20 6975.10 618.20
Over 23 but not exceeding 24 3370.40 739420 654.50
Over 24 but not exceeding 25 3572.80 7803.40 691.90
Over 25 but not exceeding 26 3786.20 8214.80 730.40
Over 26 but not exceeding 27 3987.50 8627.30 767.80
Over 27 but not exceeding 28 4199.80 9047.50 810.70
Over 28 but not exceeding 29 4402.20 9460.00 848.10
Over 29 but not exceeding 30 4609.00 986920 886.60
Over 30 but not exceeding 31 4844.40 10313.60 938.30
Over 31 but not exceeding 32 5084.20 10763.50 992.20
Over 32 but not exceeding 33 5 315.20 11 202.40 1041.70
Over 33 but not exceeding 34 5555.00 11 647.90 1 095.60
Over 34 but not exceeding 3s 5790.40 12090.10 1147.30
Over 35 but not exceeding 36 6029.10 12532.30 1199.00
Over 36 but not exceeding 37 6271.10 12973.40 1 252.90
Over 37 but not exceeding 38 6499.90 13424.40 1299.10
Over 38 but not exceeding 39 6738.60 13 863.30 1350.80
Over 39 but not exceeding 40 6975.10 14306.60 1403.60
Over 40 but not exceeding 41 7243.50 14776.30 1472.90
Over 41 but not exceeding 42 7506.40 15251.50 1536.70
Over 42 but not exceeding 43 7771.50 15 730.00 1 599.40
Over 43 but not exceeding 44 8039.90 16 19420 1665.40
Over 44 but not exceeding 45 8305.00 16676.00 1730.30
Over 45 but not exceeding 46 8570.10 17 141.30 1791.90
Over 46 but not exceeding 47 8837.40 1761320 1857.90
Over 47 but not exceeding 48 9101.40 18090.60 1921.70
Over 48 but not exceeding 49 9372.00 18561.40 1 985.50
Over 49 but not exceeding 50 9634.90 1903220 2052.60
Over 50 9897.80 19506.30 2115.30

(b) The fees set out in paragraph (a) are subject to the following

variations -

(i) for vessels under construction -

(A) The fee for examination of

plans provides for the
examination of the initial plans
and one amendment. Fee for a

second and each further

amendment to plans:  $101 .20/hour
27 July 2001 GOVERNMENT GAZETTE, WA 3807
(B) If plans are changed to change (a) $101 .20/hour; or
class of the vessel or to add a (b) the sum of the
class, fee for examination of amounts set out in
plans:
and (ll), item 1Q-,XiiXH)(1)

whichever is greater

(C) If vessel is to be issued with a
Classification Certificate in
respect of its hull and
machinery by a recognised
Classification Society -
(I) fee for examination of 50% of fee for
plans:  examination of plans
set out in item 1(a)
(II) fee for initial survey: 50% of fee for initial
survey set out in
item 1(a)
(D) If vessel is to be issued with a
Classification Certificate in
respect of its hull only, or
machinery only, by a
recognised Classification
Society—
(I) fee for examination of 75% of fee for
plans:  examination of plans
set out in item 1(a)
(II) fee for initial survey: 75% of fee for initial
survey set out in
item 1(a)
(E) Where a vessel is to be built
and surveyed during
construction to the Uniform
Shipping Laws (USL) code,
for hull structure only, the 1e
to be paid is -
(I) fee for examination of 50% of fee for
plans:  examination of plans
set out in item 1(a)
(II) fee for initial survey: 50% of fee for initial
survey set out in
item 1(a)

(F) Where a vessel is to be built

and surveyed during
construction to the Uniform
Shipping Laws (USL) code,
for hull structure and
machinery only, the fee to be
paid is -
(I) fee for examination of
75% of fee for
plans:  examination of plans
set out in item 1(a)
3808 GOVERNMENT GAZETTE, WA 27 July 2001
(II) fee for initial survey:  75% of fee for initial
survey set out in
item 1(a)

(G) Where a vessel that has been

built and surveyed during
construction to the Uniform
Shipping Laws (USL) code,
for hull structure and
machinery only, and is now
surveyed for fire, safety and
miscellaneous equipment, the

fee to be paid is—

(I) fee for examination of
plans:
25% of fee for
examination of plans
set out in item 1(a)
(II) fee for initial survey:  25% of fee for initial
survey set out in
item 1(a)

(H) If vessel is a commercial ski

boat:
(I) fee for examination of
50% of fee for
plans:  examination of plans
set out in item 1(a)
(II) fee for initial survey:  100% of fee for
subsequent survey set
out in item 1(a)
(I) If vessel is to be built in
accordance with plans
approved in respect of another
vessel, and is to be used for the
same operations, fee for
examination of plans Nil
(ii) for existing vessels -
(A) The fee for annual or
subsequent survey provides for
the initial survey and one

further inspection to clear a deficiency notice. Fee for a second and each further

inspection to complete a $101 .20/hour plus
survey:  travel expenses
(13) If vessel is in more than one Fee for subsequent
class, fee for subsequent surveys set out in

surveys: 

item 1(a) plus 50% of that fee for each additional class

(C) If class of vessel to be changed

or a class is to be added -

27 July 2001 GOVERNMENT GAZETTE, WA 3809
(I) examination of plans:  (a) $101 .20/hour

plus fee for issue of new certificate of survey; or

(b) the sum of the
amounts set out in
item 1(bXiiXHXI)
and (II),

whichever is greater

(II) conducting survey:  (a) $101 .20/hour; or
(b) the sum of the
amounts set out
in item 1(bxii)(l-f)(1)
and (ll
whichever is greater

(D)

If vessel is to be surveyed for the first time in WA and has a current Classification

Certificate in respect of its hull
and machinery issued by a
recognised Classification
Society -
(I) fee for examination of 50% of fee for
plans:  examination of plans
set out in item 1(a)
(II) fee for initial survey: 50% of fee for initial
survey set out in
item 1(a)

(E) If vessel is to be surveyed for the first time in WA and has a current Classification

Certificate in respect of its hull
only, or machinery only,

issued by a recognised

Classification Society -
(I) fee for examination of
plans:
75% of fee for

examination of plans

set out in item 1(a)

(II) fee for initial survey:  75% of fee for initial
survey set out in
item 1(a)

(F) If vessel has a current

Classification Certificate in

respect of its hull and machinery issued by a recognised Classification

50% of fee for

Society, fee for subsequent subsequent surveys
surveys:  set out in item 1(a)
3810 GOVERNMENT GAZETTE, WA 27 July 2001
(G) If vessel has a current
Classification Certificate in
respect of its hull only, or
machinery only, issued by a
recognised Classification 75% of fee for
Society, fee for subsequent subsequent surveys
surveys:  set out in item 1(a)
(H)  If significant alterations are to
be made to vessel -
(I)  fee for examination of 10% of fee for

plans: 

examination of plans set out in item 1(a) if structure requires

assessment plus a
further 10% of that
fee for each of the
following that
require
reassessment -
• machinery
• accommodation,
water tight
arrangements, or
structural fire
protection;
• equipment

(II)

fee for initial survey:

10% of fee for initial survey set out in item 1(a) if structure

requires assessment
plus a further 10% of
that fee for each of
the following that
require
reassessment -
• machinery
• accommodation,
water tight
arrangements, or
structural fire
protection;
• equipment
(I) If Certificate of Survey
previously issued in respect of
vessel but not currently valid
for the purposes of the
Australian Marine Authority,
the fee for reissue is -
(I) fee for examination of 50% of fee for
plans:  examination of plans
set out in item 1(a)
27 July 2001 GOVERNMENT GAZETTE, WA 3811
(II) fee for initial survey:  150% of fee for
subsequent survey
set out in item 1(a)
(J) If vessel not fitted with deck 50% of fees set out
structure or machinery:  in item 1(a) may
apply

Note: Hourly fees are charged per hour or part thereo1

2.            Other Fees and Chaies

The following fees are payable in relation to the matters set out in this item -

(a) issue of certificate of survey where the

Department accepts a certificate of survey

issued by another marine authority:  $73.70
(b)  extension of period of validity of certificate of
survey:  $73.70
(c)  issue of replacement or copy of certificate of
survey:  $73.70
(d)  pressure vessel -
(i)  examination of the plans (*see note 1): $101.20/hour
(ii)  initial survey and test: $101 .20/hour
(e)  crane installation on a vessel -
(i)  examination of the plans (*see note 1): $101 .20/hour
(ii)  survey and test: $101 .20/hour
(0  towage permit -
(i)  inspection of towage arrangement $101 .20/hour
before the issue of permit:  plus travel
expenses
(ii) issue of permit: $73.70
(g) permit to operate -
(i) inspection before the issue of a permit: $101 .20/hour
expenses
Plus travel
(ii) issue of permit: $73.70
(h) permit to trial -
(i) inspection before the issue of permit: $101 .20/hour
Plus travel
expenses
(ii) issue of permit: $73.70

(i)       data checking -

(i)

Check of Vessel Stability Data categories 5, T. C.4, M. C.] 1. C.12.7.1, C.14.1 -

(I) cost for first category or class: $506

(II) cost for each additional

category or class:  $253
3812 GOVERNMENT GAZETTE, WA 27 July 2001
(ii)
Check of Vessel Stability for (1) cost lbr first category or class t: $1 518

(11) cost for each additional

category or class t:  $506

(Ill) cost for each additional

category 5, T, C.4, M, C.1 1,
C. 12.7. 1, C. 14.1
$253

j The fees for these remaining categories will be subject to a 50%

reduction if complete technical information is supplied in an electronic
form compatible with the software held at the Departmenz (Software

submission format: HYDROA'fAX, WOLFSON, A4A57)

(iii) Checking of lightship data $506

(j)

attendance at inclining experiment, roll period test, authorised practical stability test or lightship test:

$506

(k) issue of Load Line Certificate: $50.60/m x
length of
vessel
(1) surveyor required to attend a vessel, site or $101 .20/hour
meeting: plus travel
expenses

(m) performance of survey or service during

overtime hours, weekends or public holidays
(in addition to other applicable fees):
$121.00/hour

(n) request for information requiring search of-

(i) printed records: $91 .30/hour,
minimum
charge $9130
(ii) computer records: $101.20/hour,
minimum
charge
$101.20

(o) photocopying:

(p) for a surveyor to attend a vessel, site, meeting 90c/page
or other survey or service outside the 73c/km
metropolitan area, on the request of the travelled by
owner:  car

Notes: 1. The fees for examination of plans and for checking stability data [items

marked (*)] allow for returning plans/data to the applicant for one
amendment If further amendment or checking is required, the fee for the
surveyor's time for checking, examining and approving plans or data is
$101 .20/hour.

2.    Hourly fees are charged per hour or part of an hour.

3.

chief executive officer -
(a)the service is delivered in the interest of the Commercial Safety section
(e.g. extension of survey where surveyor unavailable); or

Fees provided for in this item maybe waived if, in the opinion of the regulations have not allowed (e.g. permit to operate issued if Certificate of Survey is authorised, but cannot be printed).

27 July 2001 GOVERNMENT GAZETTE, WA 3813

3.             Fees for Hire and Drive Vessels

The survey fees for vessels licensed under the W.A. Marine (Hire and

Drive Vessels) Regulations 1983 are as follows —

(a) power boats not exceeding 5 m in length: $66.00
(b) sailing boats: $66.00
(c) boats propelled exclusively by oars or paddles:
$40.70
(d) all other boats exceeding 5 m in length fees set out in
(including houseboats): item 1

4.             Annual exemption fee

The annual exemption fee where the length of the vessel

(a) does not exceed 5 m: $55.00
(b) exceeds 5 m but does not exceed 10 m: $108.90
(c) exceeds 10 m but does not exceed 20 m: $201.30
(d) exceeds 20 m but does not exceed 30 m: $275.00
Recording of transfer of vessel:  $27.50

1,

[* Reprinted as at 30 July 1997.

For amendments to 10 July 2001 see 2000 Index to Legislation of Western Australia, Table 4, p. 400.]

By Command of the Governor,

M. C. WAUCHOPE, Clerk of the Executive Council.