Visual Building Construction Pty Ltd v Armitstead (No 2)

Link copied
Case Copied 17 min read

Court of Appeal


Supreme Court


New South Wales

  • Summary available
Medium Neutral Citation: Visual Building Construction Pty Ltd v Armitstead (No 2) [2019] NSWCA 280
Hearing dates: 11 November 2019
Date of orders: 21 November 2019
Decision date: 21 November 2019
Before: Bell ACJ at [1]; Macfarlan JA at [40]; White JA [41]
Decision:

Appeal dismissed with costs

Catchwords: CONTRACTS – termination – whether building contract validly terminated – whether in the circumstances, 10 business days notice giving opportunity to remedy default needed to be given prior to termination – alternative bases for termination – Shepherd v Felt & Textiles of Australia Ltd
Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW) ss 109F(1A), 121B, 149E(1)(a)
Local Government Act 1993 (NSW)
Cases Cited: Batson v De Carvalho (1948) 48 SR (NSW) 417
Burger King Corporation v Hungry Jack’s Pty Limited [2001] NSWCA 187
L.Schuler AG v Wickman Machine Tool Sales Ltd [1973] UKHL 2; [1974] AC 235
Shepherd v Felt & Textiles of Australia Ltd (1931) 45 CLR 359; [1931] HCA 21
Tricontinental Corporation Ltd v HJFI Ltd (1990) 21 NSWLR 689
Category:Principal judgment
Parties: Visual Building Construction Pty Ltd (Appellant)
David Armitstead (First Respondent)
Maria-Luisa Patisso (Second Respondent)
Representation:

Counsel:
Q Nguyen, Solicitor Advocate (Appellant)
D Hand (First and Second Respondents)

  Solicitors:
Legal and Company Solicitors (Appellant)
Adams & Partners Lawyers (First and Second Respondents)
File Number(s): 2018/265807
Publication restriction: N/A
 Decision under appeal 
Court or tribunal:
District Court of New South Wales
Jurisdiction:
Civil
Date of Decision:
21 August 2018
Before:
Sorby ADCJ
File Number(s):
2016/384392; 2016/384311

Headnote

[This headnote is not to be read as part of the judgment]

In proceedings brought in the District Court of New South Wales, Mr David Armitstead and Ms Maria-Luisa Patisso, the respondents in the current proceedings, sought damages for breach of a twice varied building contract (the Contract) with Visual Building Construction Pty Ltd (the appellant) for the construction of two duplex buildings on a block of land in Caddens, NSW.

The respondents had purported to terminate the contract due to the appellant’s failure to complete the works by the date for completion specified in the Contract, its failure to obtain the required Construction Certificate and its failure to rectify defective works. The primary judge held that the respondents had validly terminated the Contract, and entered judgment in their favour in the sum of $651,536.

The appellant filed an appeal, contending that the primary judge erred in finding that the Contract had been validly terminated, as the respondents had not provided the required 10 business days’ notice prior to termination to allow for the defaults to be remedied. By notice of contention, the respondents argued that there were grounds additional to those relied upon by the primary judge which supported the valid termination of the Contract.

The Court held (Bell ACJ, Macfarlan and White JJA agreeing), dismissing the appeal with costs:

  1. The primary judge did not err in finding that the Contract was…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Visual Building Construction Pty Ltd v Armitstead (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2019] NSWCA 280
Decision Date

CaseChat Overview and Summary

The proceeding concerned an appeal from a decision of the Supreme Court of New South Wales. The appellant, Visual Building Construction Pty Ltd, sought to challenge the validity of its termination of a building contract with the respondent, Armitstead. The core of the dispute revolved around whether the termination was lawful, particularly in relation to the notice provisions within the contract.

The primary legal issue before the Court of Appeal was whether the respondent was entitled to 10 business days' notice to remedy a default before the appellant could validly terminate the contract. The court also considered whether there were alternative grounds upon which the contract could have been terminated, referencing the principles established in *Shepherd v Felt & Textiles of Australia Ltd*.

The Court of Appeal affirmed the decision of the primary judge, finding that the notice provided by the appellant was insufficient to effect a valid termination under the contract. The court reasoned that the contractual terms required a specific period for the respondent to remedy any alleged default, and this period had not been adequately afforded. Consequently, the termination was deemed unlawful.

The appeal was dismissed, and the appellant was ordered to pay the costs of the appeal.

Orders

Orders of the court

Appeal dismissed with costs

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established