Court of Appeal
Supreme Court
New South Wales
- Summary available
Medium Neutral Citation: Visual Building Construction Pty Ltd v Armitstead (No 2) [2019] NSWCA 280 Hearing dates: 11 November 2019 Date of orders: 21 November 2019 Decision date: 21 November 2019 Before: Bell ACJ at [1]; Macfarlan JA at [40]; White JA [41] Decision: Appeal dismissed with costs
Catchwords: CONTRACTS – termination – whether building contract validly terminated – whether in the circumstances, 10 business days notice giving opportunity to remedy default needed to be given prior to termination – alternative bases for termination – Shepherd v Felt & Textiles of Australia Ltd Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW) ss 109F(1A), 121B, 149E(1)(a)
Local Government Act 1993 (NSW)Cases Cited: Batson v De Carvalho (1948) 48 SR (NSW) 417
Burger King Corporation v Hungry Jack’s Pty Limited [2001] NSWCA 187
L.Schuler AG v Wickman Machine Tool Sales Ltd [1973] UKHL 2; [1974] AC 235
Shepherd v Felt & Textiles of Australia Ltd (1931) 45 CLR 359; [1931] HCA 21
Tricontinental Corporation Ltd v HJFI Ltd (1990) 21 NSWLR 689Category: Principal judgment Parties: Visual Building Construction Pty Ltd (Appellant)
David Armitstead (First Respondent)
Maria-Luisa Patisso (Second Respondent)Representation: Counsel:
Solicitors:
Q Nguyen, Solicitor Advocate (Appellant)
D Hand (First and Second Respondents)
Legal and Company Solicitors (Appellant)
Adams & Partners Lawyers (First and Second Respondents)
File Number(s): 2018/265807 Publication restriction: N/A Decision under appeal
- Court or tribunal:
- District Court of New South Wales
- Jurisdiction:
- Civil
- Date of Decision:
- 21 August 2018
- Before:
- Sorby ADCJ
- File Number(s):
- 2016/384392; 2016/384311
Headnote
[This headnote is not to be read as part of the judgment]
In proceedings brought in the District Court of New South Wales, Mr David Armitstead and Ms Maria-Luisa Patisso, the respondents in the current proceedings, sought damages for breach of a twice varied building contract (the Contract) with Visual Building Construction Pty Ltd (the appellant) for the construction of two duplex buildings on a block of land in Caddens, NSW.
The respondents had purported to terminate the contract due to the appellant’s failure to complete the works by the date for completion specified in the Contract, its failure to obtain the required Construction Certificate and its failure to rectify defective works. The primary judge held that the respondents had validly terminated the Contract, and entered judgment in their favour in the sum of $651,536.
The appellant filed an appeal, contending that the primary judge erred in finding that the Contract had been validly terminated, as the respondents had not provided the required 10 business days’ notice prior to termination to allow for the defaults to be remedied. By notice of contention, the respondents argued that there were grounds additional to those relied upon by the primary judge which supported the valid termination of the Contract.
The Court held (Bell ACJ, Macfarlan and White JJA agreeing), dismissing the appeal with costs:
-
The primary judge did not err in finding that the Contract was…
Keep reading for free
Create a free CaseChat account to read Visual Building Construction Pty Ltd v Armitstead (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2019] NSWCA 280
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the Court of Appeal was whether the respondent was entitled to 10 business days' notice to remedy a default before the appellant could validly terminate the contract. The court also considered whether there were alternative grounds upon which the contract could have been terminated, referencing the principles established in *Shepherd v Felt & Textiles of Australia Ltd*.
The Court of Appeal affirmed the decision of the primary judge, finding that the notice provided by the appellant was insufficient to effect a valid termination under the contract. The court reasoned that the contractual terms required a specific period for the respondent to remedy any alleged default, and this period had not been adequately afforded. Consequently, the termination was deemed unlawful.
The appeal was dismissed, and the appellant was ordered to pay the costs of the appeal.
Orders
Orders of the court
Appeal dismissed with costs
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi