Land and Environment Court
New South Wales
Medium Neutral Citation: Vigor Master Pty Ltd v Hornsby Shire Council [2019] NSWLEC 1110 Hearing dates: 22 – 23 January 2019 and 20 February 2019 Date of orders: 21 March 2019 Decision date: 21 March 2019 Jurisdiction: Class 1 Before: Smithson C Decision: The Court orders that:
(1) In terms of Modification Application DA/543/2012/D for the construction of affordable rental housing containing two dwellings at Lots 16 and 17 in DP 2706309, being 6A and 6 Maroota Way, Beecroft respectively;
(a) Leave is granted for the applicants to amend the application in accordance with condition 1 of the revised conditions of consent at Annexure “A”.
(b) The appeal is upheld subject to the conditions in Annexure “A”.
(2) In terms of building certificate application number BC/15/2017 for dwellings at Lots 16 and 17 in DP 2706309, being 6A and 6 Maroota Way, Beecroft respectively;
(a) Leave is granted for the applicants to amend the application in accordance with revised plans 6M0119 – B000, B103, B104, B105, B106, B202, B203, B204, B205, B206, D000, D103, D104, D105, D202, D203, D204 and D205, all Revision 2 and dated 01/02/2019, with associated schedule of works.
(b) The appeal is upheld.
(c) Hornsby Shire Council is directed, pursuant to s 8.25(3)(a) of the Environmental Planning and Assessment Act 1979, to issue a building information certificate in respect of the dwellings at 6 and 6A Maroota Way, Beecroft upon the satisfaction of the Council that the conditions in Annexure “B” have been met within 180 days of these orders.
(3) In relation to both appeals, the exhibits are returned other than Exhibits A, B, 1 and 6.Catchwords: APPEALS: approved affordable rental housing dwellings – unauthorised works to dwellings sought to be regularised – modification application to amend existing consent to retain some unauthorised works – approved use now prohibited but has existing use rights – whether modifications result in substantially the same development – whether compatible with character of local area – compliance with the National Construction Code – capacity to be used as additional dwellings – amenity impacts – building information certificate to issue to reflect approved modification – neighbour objections Legislation Cited: Environmental Planning and Assessment Act 1979
Environmental Planning and Assessment Amendment Act 2017
Environmental Planning and Assessment Regulation 2000
Hornsby Local Environmental Plan 2013
Hornsby Shire Local Environmental Plan 1994
State Environmental Planning Policy (Affordable Rental Housing) 2009Texts Cited: Building Code of Australia
Hornsby Development Control Plan 2014
National Construction CodeCategory: Principal judgment Parties: Vigor Master Pty Ltd (First Applicant)
Zhen Zi (Second Applicant)
Ke Li (Third Applicant)
Hornsby Shire Council (Respondent)Representation: Counsel:
Solicitors:
J Doyle (Applicants)
H Irish (Respondent)
Vigor Master (Applicants)
Local Government Legal (Respondent)
File Number(s): 2018/43723; 2018/300885 Publication restriction: No
Judgment
-
COMMISSIONER: These proceedings concern two appeals lodged by Vigor Master Pty Ltd (Vigor Master), subsequently also appointed, with the leave of the Court, as the agent of Zhen Xi and Ke Li; the three parties…
Keep reading for free
Create a free CaseChat account to read Vigor Master Pty Ltd v Hornsby Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWLEC 1110
- Decision Date
CaseChat Overview and Summary
The Court found that the applicants had demonstrated that the modifications to the original development application were necessary to comply with relevant planning policies and would not substantially alter the character or scale of the site. The Court also found that the revised plans for the building certificate application met the requirements of the relevant legislation and policies. Consequently, the Court granted leave for the applicants to amend their applications and upheld the appeals, subject to the conditions outlined in the annexures. The Court directed the Council to issue a building information certificate once the specified conditions were met within 180 days.
In summary, the Court allowed Vigor Master to proceed with its development plans for the two lots in Beecroft, subject to certain conditions being met. The Court's decision provided clarity on the legal requirements and the steps necessary for the applicants to obtain the required consents from the Council. The Court also directed the Council to issue a building information certificate within a specified timeframe, ensuring that the development can proceed in accordance with the law.
Orders
Orders of the court
The Court orders that:
(1) In terms of Modification Application DA/543/2012/D for the construction of affordable rental housing containing two dwellings at Lots 16 and 17 in DP 2706309, being 6A and 6 Maroota Way, Beecroft respectively;
(a) Leave is granted for the applicants to amend the application in accordance with condition 1 of the revised conditions of consent at Annexure “A”.
(b) The appeal is upheld subject to the conditions in Annexure “A”.
(2) In terms of building certificate application number BC/15/2017 for dwellings at Lots 16 and 17 in DP 2706309, being 6A and 6 Maroota Way, Beecroft respectively;
(a) Leave is granted for the applicants to amend the application in accordance with revised plans 6M0119 – B000, B103, B104, B105, B106, B202, B203, B204, B205, B206, D000, D103, D104, D105, D202, D203, D204 and D205, all Revision 2 and dated 01/02/2019, with associated schedule of works.
(b) The appeal is upheld.
(c) Hornsby Shire Council is directed, pursuant to s 8.25(3)(a) of the Environmental Planning and Assessment Act 1979, to issue a building information certificate in respect of the dwellings at 6 and 6A Maroota Way, Beecroft upon the satisfaction of the Council that the conditions in Annexure “B” have been met within 180 days of these orders.
(3) In relation to both appeals, the exhibits are returned other than Exhibits A, B, 1 and 6.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.