| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY, ENGINEERING & CONSTRUCTION LIST
S ECI 2018 00125
| VANGUARD DEVELOPMENT GROUP PTY LTD (ACN 167 084 648) AS TRUSTEE FOR THE TAYLOR FAMILY TRUST NO. 2 | Plaintiff |
| v | |
| PROMAX BUILDING DEVELOPMENTS PTY LTD (ACN 114 054 741) | First Defendant |
| JOHN O’BRIEN | Second Defendant |
---
JUDGE: | Kennedy J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 12 July 2018 |
DATE OF JUDGMENT: | 6 August 2018 |
CASE MAY BE CITED AS: | Vanguard Development Group Pty Ltd v Promax Building Developments Pty Ltd & Anor |
MEDIUM NEUTRAL CITATION: | [2018] VSC 386 |
---
BUILDING CONTRACTS – Building and Construction Industry Security of Payment Act 2002 (Vic) – Where ‘final claim’ issued after termination of contract – Whether valid reference date – No reference date existed such that jurisdictional error made – Whether further error committed in failing to assess alleged defects which existed at time of earlier adjudication but only identified subsequently – Further jurisdictional error found.
--
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr M Robins QC | KCL Law |
For the First Defendant | Mr J Twigg QC with Mr A Morrison | Brixton Legal |
| For the Second Defendant | No appearance | … |
HER HONOUR:
This is an application for judicial review seeking an order in the nature of certiorari to quash an adjudication determination made by the second defendant (Adjudicator) on 24 May 2018 (Adjudication Determination) pursuant to s 23 of the Building and Construction Industry Security of Payment Act 2002 (Vic) (Act).
In circumstances where grounds 1 and 2 were abandoned, the further amended originating process essentially raised two groups of grounds for review which will be set out more fully below.
First, that the Adjudicator did not have jurisdiction to make the Adjudication Determination given there was no valid reference date (grounds 3 and 6).
Second, that the Adjudicator erred in failing to consider and assess claims relating to alleged defects (grounds 4 and 5).
In relation to the first issue, the Adjudicator had proceeded on the premise that the plaintiff, Vanguard Development Group Pty Ltd (Vanguard), had validly terminated the contract at common law. This however was challenged by the first defendant, Promax Building Developments Pty Ltd (Promax), who claimed that it had validly terminated the contract. In the result, pursuant to an order made by the Honourable Justice Riordan on 2 July 2018, the hearing was not to include any issue as to whether the first defendant was entitled to terminate under the Contract. However, as will be seen below, the construction I have adopted means it will be unnecessary to resolve the issue of who validly terminated the contract.
The second defendant Adjudicator has indicated that he did not intend to take an active role in the proceeding but would seek to be heard prior to the making of any costs order against him.[1]
[1]See letter from Ms Lorraine Djuricin, General Manager of Adjudicate Today Pty Ltd dated 15…
Continue reading Vanguard Developments v Promax
Sign in free to access the full text
- AGLC
- Vanguard Developments v Promax [2018] VSC 386
- Case
- [2018] VSC 386
- Decision Date
CaseChat Overview and Summary
The court found that the tribunal erred in concluding that no reference date existed. The termination of the contract did not nullify the reference date under the Act. Consequently, the tribunal lacked jurisdiction to dismiss the claim. Additionally, the tribunal failed to consider the alleged defects that existed at the time of the earlier adjudication but were identified later. This omission constituted another jurisdictional error. The tribunal's failure to address these issues meant that the tribunal did not properly exercise its jurisdiction.
The court quashed the decision of the tribunal and remitted the matter for reconsideration in light of the findings. The tribunal was instructed to determine the validity of the reference date and to assess the alleged defects that existed at the time of the earlier adjudication but were identified later.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.