Court of Appeal
Supreme Court
New South Wales
- Summary available
Medium Neutral Citation: Valmont Interiors Pty Ltd v Giorgio Armani Australia Pty Ltd (No 2) [2021] NSWCA 93 Hearing dates: 3 May 2021 Date of orders: 19 May 2021 Decision date: 19 May 2021 Before: Bell P at [1];
Macfarlan JA at [127];
Leeming JA at [128]Decision: 1. Appeal allowed with costs.
2. Set aside the orders of the primary judge and in lieu thereof, make the following orders:
(a) Judgment for the plaintiff in the amount of $255,493.
(b) Judgment for the defendant on the cross-claim in the amount of $219,083.29.
3. Leave be granted to both parties to file any submissions of no more than 3 pages each within 7 days if an order as to costs at first instance is sought by either party, with any reply to be filed within a further 7 days.
Catchwords: BUILDING AND CONSTRUCTION – contract – damages – defects – whether the contractor was responsible for defects in materials supplied by a third party – where the relevant contractual warranty was confined to “works required to be performed by the contractor”
BUILDING AND CONSTRUCTION – contract – termination – quantum meruit – whether the contract operated to generate release and waiver of subsequent claims for payment by the contractor – where the contractor had suffered irreversible detriment by incurring liability to pay for materials prior to the principal’s insistence upon strict adherence to the contract
BUILDING AND CONSTRUCTION – contract – variation – implied promise to pay – whether the works constituted “variations” as defined in the contract – where the principal requested that the contractor supply materials that it had originally insisted upon supplying itself – where written approval was sought by the contractor in respect of all other variation works
CONTRACTS – breach of contract – consequences of breach – right to damages – estoppel – promissory estoppel – whether it was unconscionable for the principal to resist payment for the performance of certain works – where the principal was positively encouraging the contractor to complete outstanding works – where such encouragement followed the principal’s purported departure from the assumption that it had approved these works
EQUITY – estoppel – promissory estoppel – general principles and maxims – equity will not permit detriment to be visited upon or remain with the party who has not been sufficiently clearly disabused of the counter-party’s intended departure from the relevant assumption inducing reliance
ESTOPPEL – promissory estoppel – detrimental reliance – whether the principal discharged its duty to inform the contractor labouring under an assumption that the basis for that assumption had “materially changed” – where such material change must be communicated in sufficiently clear terms – where the relevant communication did not expressly refer to or address the topic of the assumption – where the principal was positively encouraging the contractor to complete outstanding works in respect of materials that the principal knew it had originally undertaken to supply itself
Keep reading for free
Create a free CaseChat account to read Valmont Interiors Pty Ltd v Giorgio Armani Australia Pty Ltd... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2021] NSWCA 93
- Decision Date
CaseChat Overview and Summary
The central legal issues before the Court of Appeal were whether the contractor was responsible for defects in materials supplied by a third party, despite a contractual warranty limited to works performed by the contractor; whether the contract precluded the contractor from claiming payment for certain works on a quantum meruit basis, particularly where the contractor had incurred liability for materials prior to the principal's insistence on strict contractual adherence; and whether certain works constituted "variations" under the contract, giving rise to an implied promise to pay, especially when the principal had requested the contractor supply materials the principal had initially intended to supply itself. The court also considered whether the principal's conduct gave rise to a promissory estoppel, preventing it from resisting payment for works where it had encouraged the contractor to complete them after a purported departure from an assumption that the principal had approved those works.
The Court of Appeal reasoned that the contractual warranty regarding defects was confined to the contractor's own works and did not extend to materials supplied by a third party, particularly where the principal had directed the contractor to use those materials. The court found that the principal's conduct, in encouraging the contractor to complete works involving materials the principal had originally agreed to supply, and in failing to clearly communicate any departure from the assumption that these works were approved, created a situation where it would be unconscionable to deny payment. This was particularly so as the contractor had incurred detriment by becoming liable for the cost of those materials. The court applied the principles of promissory estoppel, holding that the principal had a duty to clearly inform the contractor of any material change to the basis of the contractor's assumption, and that the communication in this instance was insufficient to discharge that duty.
The Court of Appeal allowed the appeal with costs, setting aside the primary judge's orders. In lieu, judgment was entered for the plaintiff (contractor) in the amount of $255,493 and for the defendant (principal) on the cross-claim in the amount of $219,083.29. Leave was granted for parties to file submissions regarding costs at first instance.
Orders
Orders of the court
1. Appeal allowed with costs.
2. Set aside the orders of the primary judge and in lieu thereof, make the following orders:
(a) Judgment for the plaintiff in the amount of $255,493.
(b) Judgment for the defendant on the cross-claim in the amount of $219,083.29.
3. Leave be granted to both parties to file any submissions of no more than 3 pages each within 7 days if an order as to costs at first instance is sought by either party, with any reply to be filed within a further 7 days.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi