| IN THE SUPREME COURT OF VICTORIA AT MELBOURNE COMMERCIAL COURT TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST | Not Restricted |
S ECI 2018 0072
| VALEO CONSTRUCTION PTY LTD (ACN 139 755 801) | Plaintiff |
| v | |
| PENTAS PROPERTY INVESTMENTS PTY LIMITED (ACN 102 933 406) | Defendant |
---
JUDGE: | Digby J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 14 May 2018 |
DATE OF JUDGMENT: | 15 May 2018 |
CASE MAY BE CITED AS: | Valeo Construction v Pentas |
MEDIUM NEUTRAL CITATION: | [2018] VSC 243 |
---
BUILDING CONTRACTS – Progress payment claims – Revision and correction and withdrawal of progress payment claim – Compliance with statutory requirements – Whether revised payment claim constituted a prohibited second claim in relation to same reference date – Building and Construction Industry Security of Payment Act 2002 (Vic), s 14(8).
BUILDING CONTRACTS – Progress payment claims – Payment schedule served out of time – Application for recovery of debt - Building and Construction Industry Security of Payment Act 2002 (Vic), s 16(2)(a)(i).
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr J Twigg QC with Ms F Cameron | Giannakopoulos Solicitors |
| For the Defendant | Mr M Robins QC with Mr N Phillpott | Champion Lawyers |
HIS HONOUR:
Overview
By Originating Process dated 26 March 2018, Valeo Construction Pty Ltd (the plaintiff) applies for judgment against Pentas Property Investments Pty Ltd (the defendant) under s 16(2)(a)(i) of the Building and Construction Industry Security of Payment Act 2002 (Vic) (the Act) for $1,733,649.80.
The amount claimed is in the nature of an outstanding progress payment of $2,240,160.13 for work done under a construction contract between the parties dated 28 March 2014, minus $667,561.67 excluded under the Act, plus contractual interest at 8% per annum.
The principal issue in this proceeding is the validity of a payment claim served on the defendant on 1 March 2018. That claim was issued in circumstances which included the plaintiff earlier issuing a payment claim #45 on 28 February 2018, for a sum of approximately $25,000 less.
The defendant submits that the revised payment claim #45 dated 1 March 2018 is invalid because it is an attempt by the plaintiff to issue a second payment claim in respect of the same reference date in contravention of s 14(8) of the Act.
Chronology
On or about 28 March 2014, the parties entered into a contract whereby the plaintiff would construct a five-storey residential apartment building, with two levels of basement car-parking and some commercial tenancies at 178 Victoria Avenue, Albert Park in the State of Victoria for the defendant, for the total sum of $18,490,170.00 (exclusive of GST) (the Contract).[1]
[1]Affidavit of Nicholas Tsiakiris sworn 23 March 2018 (Tsiakiris Affidavit), Exhibit ‘DT-3’.
Pursuant to the terms of the Contract,[2] the plaintiff was entitled to make claims for payment under the Act on the fifteenth day of each month by serving a payment claim on the Superintendent. By subsequent agreement between the parties, the day upon which the plaintiff was entitled to serve payment claims was changed from the fifteenth day of the month to the…
Keep reading for free
Create a free CaseChat account to read Valeo Construction v Pentas and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2018] VSC 243
- Decision Date
CaseChat Overview and Summary
The central issue for the court was whether the revised payment claim made by Valeo complied with the statutory requirements set out in section 14(8) of the Building and Construction Industry Security of Payment Act 2002 (Vic). Specifically, the court needed to determine if the revised claim constituted a prohibited second claim in relation to the same reference date. Additionally, the court examined whether Pentas's payment schedule was served out of time, impacting Valeo's ability to recover the debt under section 16(2)(a)(i) of the Act.
In its judgment, the court found that the revised payment claim made by Valeo did not constitute a second claim as it was made within the 10-day period prescribed by section 14(8) of the Act. The court reasoned that the revision and correction of the claim, while not initially compliant, were subsequently corrected within the statutory timeframe and thus did not violate the prohibition on multiple claims for the same reference date. Regarding the payment schedule, the court held that it was served outside the allowable period, which impacted the timeliness of Valeo's application for recovery of the debt.
The court ordered that the revised payment claim by Valeo was valid and that Pentas was required to make payment in accordance with the revised claim. Additionally, due to the late service of the payment schedule, the court ruled that Valeo was entitled to recover the debt, subject to certain conditions regarding the timeliness of the payment schedule.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi