SUPREME COURT OF QUEENSLAND
CITATION:
Urban Properties Centenary Pty Ltd v Cairns Regional Council [2019] QSC 160
PARTIES:
URBAN PROPERTIES CENTENARY PTY LTD
ACN 169 863 987(Plaintiff)
v
CAIRNS REGIONAL COUNCIL(Defendant)
FILE NO/S:
No 117 of 2019
DIVISION:
Trial
PROCEEDING:
Trial
ORIGINATING COURT:
Supreme Court at Cairns
DELIVERED ON:
26 June 2019
DELIVERED AT:
Cairns
HEARING DATE:
28 May 2019, 29 May 2019
JUDGE:
Henry J
ORDERS:
1. It is declared that pursuant to clause 6.3 of the parties’ agreement, the requirement for payment of:
(a) adopted infrastructure charges notice Council reference 8/7/3305 (5028457) (the first notice referred to in schedule 3 of the agreement) is partly waived so that $322,548.96, of the charged total of $851,120.52, is not required to be paid;
(b) adopted infrastructure charges notice Council reference 8/30/160 (5369780) (the second notice referred to in schedule 3 of the agreement) is wholly waived;
(c) adopted infrastructure charges notice Council reference 8/13/2039 (5409183) (the third notice referred to in schedule 3 of the agreement) is wholly waived;
(d) infrastructure charges notice Council reference 8/30/246 (5633901) (the fourth notice referred to in schedule 3 of the agreement) is wholly waived;
(e) infrastructure charges notice Council reference 8/13/2128 (5755524) is not waived;
(f) infrastructure charges notice Council reference 8/13/2152 (5787991) is not waived.
2. I will hear the parties as to costs, if costs are not agreed in the interim, at 9.15 am 17 July 2019.
CATCHWORDS:
ENVIRONMENT AND PLANNING – ENVIRONMENTAL PLANNING – DEVELOPMENT CONTROL – CONSENTS, APPROVALS, PERMITS AND AGREEMENTS – INTERPRETATION AND CONSTRUCTION – PARTICULAR CASES – where the applicant developer and respondent Council entered into an infrastructure agreement – where the agreement waived the requirement for payment of certain infrastructure charges, to which the agreement referred, in the event the applicant met various development obligations – where the development obligations were met – where the applicant and respondent dispute which infrastructure charges were accordingly waived under the agreement – where the applicant and respondent each seek declarations from the Court as to which infrastructure charges have been waived
Planning Act 2016 (Qld) ss 49, 61, 113, 119, 121, 122, 123, 144
Sustainable Planning Act 2009 (Qld) ss 7, 10
Amcor v CFMEU (2005) 222 CLR 241
Gladstone Regional Council v Homes R Us (Australia) Pty Ltd (2015) 209 LGERA 302
Maggbury Pty Ltd v Hafele Australia Pty Ltd (2001) 210 CLR 181
Mulgrave Shire Council v Red Hills Pty Ltd (1994) 83 LGERA 323
COUNSEL:
MA Jonsson QC for the plaintiff
RS Litster QC with MR Wylie for the defendant
SOLICITORS:
Miller Harris Lawyers for the plaintiff
MacDonnells Law for the defendant
The applicant (“the developer”) and respondent (“the Council”) each seek declarations in connection with infrastructure charges on a land and residential development in suburban Cairns known as Village Edge. At issue is whether certain infrastructure charges are due and payable by the developer or have been waived by the Council.
Background
Infrastructure charges are levied upon development by local Councils as part…
Keep reading for free
Create a free CaseChat account to read Urban Properties Centenary Pty Ltd v Cairns Regional Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2019] QSC 160
- Decision Date
CaseChat Overview and Summary
The central legal issue revolved around the interpretation of the agreement's waiver clause, particularly clause 6.3, which states that certain infrastructure charges would be waived if the developer met specific development obligations by a designated sunset date. The disagreement between the developer and the Council centred on the exact nature and extent of the infrastructure charges that were waived under this clause. The definition of "infrastructure charges" in the agreement and the references to various notices listed in Schedule 3 were pivotal to resolving this dispute.
The Court meticulously examined the language and structure of the agreement, including the definition of "infrastructure charges" and the references in Schedule 3. It determined that certain infrastructure charges were wholly waived while others were only partly waived or remained unwaived. The Court found that the developer had met its obligations, but the scope of the waiver under clause 6.3 was limited to specific charges as defined and referenced in the agreement. Consequently, the Court made specific declarations regarding which infrastructure charges were waived and which were not, based on the terms of the agreement and the evidence presented.
The Court's final orders included declarations that certain infrastructure charges were waived while others were not, as detailed in the Court's judgment. Additionally, the Court scheduled a further hearing to address the issue of costs, indicating that the parties would need to discuss and potentially agree on the allocation of costs involved in the proceedings.
Orders
Orders of the court
1. It is declared that pursuant to clause 6.3 of the parties’ agreement, the requirement for payment of:
(a) adopted infrastructure charges notice Council reference 8/7/3305 (5028457) (the first notice referred to in schedule 3 of the agreement) is partly waived so that $322,548.96, of the charged total of $851,120.52, is not required to be paid;
(b) adopted infrastructure charges notice Council reference 8/30/160 (5369780) (the second notice referred to in schedule 3 of the agreement) is wholly waived;
(c) adopted infrastructure charges notice Council reference 8/13/2039 (5409183) (the third notice referred to in schedule 3 of the agreement) is wholly waived;
(d) infrastructure charges notice Council reference 8/30/246 (5633901) (the fourth notice referred to in schedule 3 of the agreement) is wholly waived;
(e) infrastructure charges notice Council reference 8/13/2128 (5755524) is not waived;
(f) infrastructure charges notice Council reference 8/13/2152 (5787991) is not waived.
2. I will hear the parties as to costs, if costs are not agreed in the interim, at 9.15 am 17 July 2019.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi