Urban Constructions (NSW) Pty Ltd v Brett Shearer and Bronwyn Shearer

Link copied
Case Copied 87 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Urban Constructions (NSW) Pty Ltd v Brett Shearer and Bronwyn Shearer [2015] NSWCATCD 9
Hearing dates:23, 24, 25 and 26 June 2014
Date of orders: 10 February 2015
Decision date: 10 February 2015
Jurisdiction:Consumer and Commercial Division
Before: D. Goldstein, Senior Member
Decision:

Brett Shearer and Bronwyn Shearer must pay Urban Constructions (NSW) Pty Ltd the sum of $170,220.03 within 21 days of the date of this order.
Either party is at liberty to make a costs application in these proceedings.
Any costs application pursuant to section 53 of the Consumer, Trader and Tenancy Tribunal Act 2001 or regulation 20 of the Consumer, Trader and Tenancy Tribunal Regulation 2009 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this order either attaching or referring to the documents relied upon in support of the application.

The costs respondent will have 21 days after the date of receipt of the costs application referred to above, to lodge in the Tribunal and serve on the costs applicant the submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.
The cost applicant will have 14 days after the date of receipt of the cost respondent’s submissions to lodge in the Tribunal and serve on the costs respondent the submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon.
The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal
Catchwords: Section 94(1A) of the Home Building Act 1989, quantum meruit, defects, unfinished work
Legislation Cited: Civil and Administrative Tribunal Act 2013,
Consumer, Trader and Tenancy Tribunal Act 2001,
Consumer, Trader and Tenancy Tribunal Regulation 2009,
Home Building Act,1989
Cases Cited: Brenner v First Artists’ Management Pty Ltd [1993] 2 VR 221,
Eddy Lau Constructions Pty Ltd v Transdevelopment Enterprise Pty Ltd [2004] NSWSC 273,
Makita (Australia) Pty Ltd v Sprowles (2001) 52 NSWLR 705,
Nguyen v Cosmopolitan Homes [2008] NSWCA 246,
Pender v Robwenphi Pty Limited & Anor [2008] NSWSC 1144,
Pownall v Conlon Management Pty Ltd (1995) 12 WAR 370,
Stephenson v State Bank of New South Wales (1996) 39 NSWLR 101,
Sullman v Sullman [2002] NSWSC 169,
Talga v MBC International Limited (1976) 133 CLR 622,
Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd 20 NSWLR 251.
Texts Cited: Dorter & Sharkey Building and Construction Contracts in Australia, Second Edition
Category:Principal judgment
Parties: Applicant: Urban Constructions (NSW) Pty Ltd
Respondents: Brett Shearer and Bronwyn Shearer
Representation:

Counsel: Mr G. Carolan for the applicant
Ms F. Ashworth for the respondents

Solicitors: Darcy Sloman Peacock for the applicant
PMF Legal for the respondents
File Number(s):HB 10/44316
Publication restriction:Nil

reasons for decision

  1. In these proceedings the applicant originally sought to recover the amount of $152,373.66 for work…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Urban Constructions (NSW) Pty Ltd v Brett Shearer and Bronwy... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] NSWCATCD 9
Decision Date

CaseChat Overview and Summary

Urban Constructions (NSW) Pty Ltd filed a claim against Brett Shearer and Bronwyn Shearer, seeking payment for work that was completed on a residential property but left unfinished, as well as for defects identified during the inspection. The dispute was heard in the Consumer, Trader and Tenancy Tribunal. The central issue before the Tribunal was whether Urban Constructions was entitled to payment for the unfinished work and defects under Section 94(1A) of the Home Building Act 1989, or if the claim should be assessed under the principle of quantum meruit.

The Tribunal considered the evidence and submissions from both parties, focusing on the contractual obligations and the extent to which Urban Constructions had fulfilled its duties. It was determined that Urban Constructions had completed some of the work but had failed to finish all tasks and had also left some defects. The Tribunal found that the Shearers were liable to pay Urban Constructions for the unfinished work and defects. The Tribunal ruled that the claim was not subject to the principle of quantum meruit, as there was a contractual basis for the claim under the Home Building Act.

In conclusion, the Tribunal ordered Brett Shearer and Bronwyn Shearer to pay Urban Constructions (NSW) Pty Ltd the sum of $170,220.03 within 21 days. The Tribunal also outlined the process for any costs applications, specifying that they must be lodged with the Tribunal and served on the opposing party within the stipulated timeframes. The Tribunal will determine any costs application based on the documents and submissions provided by the parties.

Orders

Orders of the court

Brett Shearer and Bronwyn Shearer must pay Urban Constructions (NSW) Pty Ltd the sum of $170,220.03 within 21 days of the date of this order.

Either party is at liberty to make a costs application in these proceedings.

Any costs application pursuant to section 53 of the Consumer, Trader and Tenancy Tribunal Act 2001 or regulation 20 of the Consumer, Trader and Tenancy Tribunal Regulation 2009 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this order either attaching or referring to the documents relied upon in support of the application.

The costs respondent will have 21 days after the date of receipt of the costs application referred to above, to lodge in the Tribunal and serve on the costs applicant the submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.

The cost applicant will have 14 days after the date of receipt of the cost respondent’s submissions to lodge in the Tribunal and serve on the costs respondent the submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon.

The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established