Upper South East Dryland Salinity and Flood Management Variation Regulations 2005 (SA)
South Australia
Upper South East Dryland Salinity and Flood Management Variation Regulations 2005
under the Upper South East Dryland Salinity and Flood Management Act 2002
Contents
Part 1—Preliminary
Short title
Commencement
Variation provisions
Part 2—Variation of Upper South East Dryland Salinity and Flood Management Regulations 2002
Variation of regulation 5—Establishment of Project scheme
Insertion of regulation 10
10Variation of Schedule 1 of the Act
Variation of Schedule 2—Project Works Scheme
Part 1—Preliminary
1—Short title
These regulations may be cited as the Upper South East Dryland Salinity and Flood Management Variation Regulations 2005.
2—Commencement
These regulations come into operation on the day on which they are made.
3—Variation provisions
In these regulations, a provision under a heading referring to the variation of specified regulations varies the regulations so specified.
Part 2—Variation of Upper South East Dryland Salinity and Flood Management Regulations 2002
4—Variation of regulation 5—Establishment of Project scheme
Regulation 5(2)—after paragraph (b) insert:
(ba)the project scheme as described in the document lodged as Deposit No. 461 of 2004 in the General Registry Office, as varied from time to time; and
5—Insertion of regulation 10
After regulation 9 insert:
10—Variation of Schedule 1 of the Act
(1)Schedule 1, Part B, item 1—after "Adelaide" insert:
, as varied from time to time
(2)Schedule 1, Part B, item 2—after "Adelaide" insert:
, as varied from time to time
6—Variation of Schedule 2—Project Works Scheme
Schedule 2, clause 1, table—delete the table and substitute:
Item
Project Works
Date
1
Commence design of Kercoonda Drain extensions
January 2004
2
Commence construction of Northern Catchment drains (Mt Charles, Taunta Hut, Bunbury and Northern Outlet drains)
March 2004
3
Commence design of Bakers Range, Ballater East, East Avenue, Rosemary Downs and Wongawilli drains
April 2005
4
Commence cadastral surveys of constructed drains
March 2005
5
Complete design of Kercoonda Drain extensions
December 2004
6
Complete design of Central Catchment drains (Taratap, Bald Hill, Wimpinmerit and Didicoolum drains)
October 2005
7
Commence construction of Kercoonda Drain extensions
April 2005
8
Complete construction of Northern Catchment drains (Mt Charles, Taunta Hut, Bunbury and Northern Outlet drains). Northern Outlet drain includes Deepwater offshoot
April 2005
9
Commence construction of Central Catchment drains (Taratap, Bald Hill, Wimpinmerit and Didicoolum drains)
April 2005
10
Complete construction of Kercoonda Drain extensions
June 2005
11
Complete design of Bakers Range, Ballater East, East Avenue, Rosemary Downs and Wongawilli drains
August 2005
12
Commence construction of Bakers Range, Ballater East, East Avenue, Rosemary Downs and Wongawilli drains
October 2005
13
Complete construction of Central Catchment drains (Taratap, Bald Hill, Wimpinmerit and Didicoolum drains). Didicoolum includes extension and upgrades
December 2006
14
Complete construction of Bakers Range, Ballater East, East Avenue, Rosemary Downs and Wongawilli drains
March 2006
15
Complete upgrade of Ashby Drain (privately constructed drain)
June 2005
16
Complete minor works, fencing and modification to Tilley Swamp Drain
August 2005
17
Complete minor works including fencing to Watervalley Drain
August 2005
18
Complete cadastral surveys of all constructed drains
December 2006
Note—
As required by section 10AA(2) of the Subordinate Legislation Act 1978, the Minister has certified that, in the Minister's opinion, it is necessary or appropriate that these regulations come into operation as set out in these regulations.
Made by the Governor
with the advice and consent of the Executive Council
on 16 June 2005
No 137 of 2005
EC04/0088CS