Upper South East Dryland Salinity and Flood Management (Project Works Corridors) Regulations 2009 (SA)
South Australia
Upper South East Dryland Salinity and Flood Management (Project Works Corridors) Regulations 2009
under the Upper South East Dryland Salinity and Flood Management Act 2002
Contents
Short title
Commencement
Interpretation
Variation of Schedule 1 of Act—Project works corridors
Schedule 1—Revocation of Upper South East Dryland Salinity and Flood Management (Amendment of Act) Regulations 2008
Revocation of regulations
1—Short title
These regulations may be cited as the Upper South East Dryland Salinity and Flood Management (Project Works Corridors) Regulations 2009.
2—Commencement
These regulations come into operation on the day on which they are made.
3—Interpretation
In these regulations—
Act means the Upper South East Dryland Salinity and Flood Management Act 2002.
4—Variation of Schedule 1 of Act—Project works corridors
Part B of Schedule 1 of the Act is varied by deleting "13 June 2008" wherever occurring and substituting in each case:
21 August 2009
Schedule 1—Revocation of Upper South East Dryland Salinity and Flood Management (Amendment of Act) Regulations 2008
1—Revocation of regulations
The Upper South East Dryland Salinity and Flood Management (Amendment of Act) Regulations 2008 are revoked.
Note—
As required by section 10AA(2) of the Subordinate Legislation Act 1978, the Minister has certified that, in the Minister's opinion, it is appropriate that these regulations come into operation as set out in these regulations.
Made by the Governor's Deputy
with the advice and consent of the Executive Council
on 1 October 2009
No 243 of 2009
WBCS08/0022
0