University of Tasmania v Tasmanian Planning Commission

Link copied
Case Copied 22 min read

[2019] TASSC 7

COURT:  SUPREME COURT OF TASMANIA

CITATION:                University of Tasmania v Tasmanian Planning Commission

[2019] TASSC 7

PARTIES:  UNIVERSITY OF TASMANIA
  v
  TASMANIAN PLANNING COMMISSION
  THE HONOURABLE ELISE ARCHER
  ATTORNEY-GENERAL

FILE NO:  2020/2018
DELIVERED ON:  28 February 2019
DELIVERED AT:  Hobart
HEARING DATE:  21 February 2019
JUDGMENT OF:  Estcourt J

CATCHWORDS:

Administrative Law – Judicial review – Failure to exercise jurisdiction – Planning authority refused applicant's request for planning scheme amendment – Reasons for decision not to be over zealously scrutinised – Natural justice – Application for deferment – Refusal to defer assessment a denial of procedural fairness.

Tasmanian Planning Commission Act 1997 (Tas), s 10(1)(b)(v).
Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259; Russell v Duke of Norfolk [1949] 1 All ER 109; Streets v Lucas [2013] TASSC 45, referred to.
Aust Dig Administrative Law [1045]

REPRESENTATION:

Counsel:
             Applicant:  A Spence
             Intervenor:  P Turner
Solicitors:
             Applicant:  Page Seager
             Intervenor:  Solicitor General

Judgment Number:  [2019] TASSC 7
Number of paragraphs:  30

Serial No 7/2019

File No 2020/2018

UNIVERSITY OF TASMANIA v TASMANIA PLANNING COMMISSION
and THE HONOURABLE ELISE ARCHER ATTORNEY-GENERAL

REASONS FOR JUDGMENT  ESTCOURT J
  28 February 2019

The proceedings

  1. This is an application for review of a decision of the Tasmanian Planning Commission pursuant to the provisions of the Judicial Review Act 2000. The respondent Commission filed a notice of submission and the Attorney-General became an intervenor in the proceedings.

The background

  1. The following background to this application is taken from the written submissions of counsel for the applicant, Mr Spence:

    "The legislative regime is the applicable version of the LUPAA s30 Division 2, ss31 through to ss43 and the Tasmanian Planning Commission Act 1997 (TPC Act).

    The University conducted an audit of, inter alia, its Sandy Bay campus to consider properties surplus to requirements.  It identified three Sandy Bay properties and Mount Nelson Villas, being student accommodation.

    The Sandy Bay campus was zoned a special purpose planning zone under the Hobart Interim Planning Scheme 2015.  It had a similar zone status under the prior City of Hobart Planning Scheme 1982 (CHPS).

    The University, for its own purposes, has a Master Plan.  Volume 2 relates to the Sandy Bay and Hobart City Campus.  It is not a planning document.  It provided design ethos, breakup of precincts, use of precincts and the like.

    With the transmission from the CHPS to the HIPS, the University considered the new scheme.  It sought an urgent amendment to the HIPS in July 2015.  The University was concerned that some aspects of the Master Plan had been sourced for the scheme controls and that was inappropriate.  It sought flexibility given the likelihood of disposal of buildings.  That urgent amendment was approved by the Commission.

    Of relevance was the addition of subparagraph (g) to the desired future character statement.

    'The Upper Campus is an area in transition as the University divests itself of redundant…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read University of Tasmania v Tasmanian Planning Commission and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2019] TASSC 7
Decision Date

CaseChat Overview and Summary

The University of Tasmania has challenged the decision of the Tasmanian Planning Commission to refuse a request for an amendment to the planning scheme. The dispute was heard and determined in the Supreme Court of Tasmania. The University sought to amend the planning scheme to permit a development on its property, which the Commission refused. The key issues before the Court were whether the Commission had failed to exercise its jurisdiction and whether the refusal to defer the assessment constituted a denial of procedural fairness.

The Court considered that the Commission's reasons for decision did not need to be over zealously scrutinised, but rather, should be assessed in light of the statutory objectives. The Court found that the Commission had considered the relevant objectives in making its decision but had not provided sufficient reasons for rejecting the draft amendment. The Court held that the Commission had failed to exercise its jurisdiction as it did not adequately consider the specific criteria against which the development was to be tested. Regarding the refusal to defer the assessment, the Court found that it did not constitute a denial of procedural fairness as the University had not demonstrated a legitimate expectation of a deferral.

The Court concluded that the Commission's decision to refuse the amendment was unlawful due to the failure to exercise jurisdiction. The Court set aside the decision of the Commission and remitted the matter back for reconsideration. The Court did not make any orders regarding costs.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

The Commission in its written reasons for decision expressed its "decision" as follows:"Decision on draft amendmentThe draft amendment is rejected under section 41(b) of the Land Use Planning and Approvals Act 1993 because it does not further Objective (a) of Part 2, Schedule 1 of the Act." As very helpfully pointed out by counsel for the intervenor, Mr Turner, in his written submissions:"… s 33(1) of the Land Use Planning and Approvals Act 1993 (LUPAA). Schedule 6 of LUPAA sets out transitional provisions in relation to the Land Use Planning and Approvals Amendment (Tasmanian Planning Scheme) Act 2015. That commenced on 17 December 2015 (Statutory Rule 92 of 2015). In consequence, and by virtue of cl (2)(b) of Schedule 6 Parts 2A and 3 of LUPAA, extant immediately before that date, governed the amendment process. References to sections of LUPAA in this Outline are to those in that version of the Act unless otherwise specified. That version of the Act (ie the version current from 1 April 2015 to 16 December 2015) is most readily accessed on the Tasmanian Planning Commission website – Counsel for the applicant argues these issues in his written submissions as follows:"Schedule 1 to LUPAA contains 'Objectives'. S5 states that they are to be 'furthered'. Neither term is defined but, in Macquarie Concise Dictionary 'Objective' is defined as 'an end towards which efforts are directed; something aimed at' and 'further' is 'promote; advance; forward'.The Part 1 Objectives are of the 'Resource Management and Planning System of Tasmania' and they are broad and aspirational.The Part 2 Objectives are of the planning process established by this act and support Objectives in Part 1.In my submission Objectives have no work to do in respect of an individual process. They are at a higher level and are not absolute. Indeed, they are conflicting, the Objectives in Schedule 1 creates a framework but not afford a basis to refuse or approve a development or amendment. See Abret Pty Ltd v Wingecarribee Shire Council[1].[1] Abret Pty Ltd v Wingecarribee Shire Council (2011) 180 LGERA 343'42 …, it is apparent that his Honour's reasoning is directed to the objectives of the zoning table. They are not provisions of the LEP that control development. Rather, they set the framework in which the LEP operates. The objectives themselves are not necessarily consistent, but reflect the conflicting demands upon development within the particular Local Government Area. ... It was not suggested by Council that there is a priority of objectives in the clause. Accordingly, there was no basis for the trial judge to rely upon the objective in para (d) rather than the objective in para (i).'See also AMP Capital v Tim Shellshear & Associates Pty Ltd & Anor[2].[2] AMP Capital v Tim Shellshear & Associates Pty Ltd & Anor (2012) 189 LGERA 304'52 AMP cites no authority for the submission that the relevant objectives are not to be read as a whole. On the contrary, it is a well-known principle of construction that the such provisions must always be read in their context: … The relevant context is the group of the various objectives of the zone. The objectives are not necessarily consistent but reflect the conflicting demands upon development within the area: ...'There is a long line on authority for the proposition that general objectives cannot be used as a basis to refuse a proposal, see Von Witt v Hobart City Council[3] and Krushka v Peacock and Hobart City Council[4].This authority has been held to apply to Schedule 1 Objectives, see Novak International Pty Ltd v Resource Planning and Development Commission[5]. In referring to the Objectives and the framework of Objectives, his honour Slicer J held:'Whilst cl 1(e) refers to the sharing of responsibility, here, although it provides a framework of objectives, it provides no additional power to that afforded by LUPA, except in the most general terms. But it is required to pay regard to all of the statutory objectives and not selective reliance. As Wright J stated in Von Witt v Hobart City Council (1995) 86 LGERA 134 at 141: …'More recently I turn to Clarence City Council v Resource Management and Planning Appeal Tribunal[6].'56 …. The objectives are stated in general terms. Their formulation makes it clear that they are intended to operate by providing context and guidance in respect of the evaluative assessment engaged in in respect of various decisions required within the planning system generally, including in respect of the exercise of a specific discretion. … However, they cannot supplant the specific criteria against which the development is to be tested, nor in themselves constitute a test of a proposed development. ...'The difficulty in using general stated policy statements as a form of control was addressed in another context in Richard Bejah Insurance and Financial Services Pty Ltd v Maning[7]."[3] Von Witt v Hobart City Council (1995) 86 LGERA 134[4] Krushka v Peacock and Hobart City Council (1997) 95 LGERA 427[5] Novak International Pty Ltd v Resource Planning and Development Commission (2008) 161 LGERA 277[6] Clarence City Council v Resource Management and Planning Appeal Tribunal (2018) TASSC 41[7] Richard Bejah Insurance and Financial Services Pty Ltd v Maning (2002) 123 LGERA 349 pages 353 to 358

Ratio Decidendi

Legal principle established