Universal Property Group Pty Ltd v Blacktown City Council

Case

[2017] NSWLEC 1748

28 December 2017

No judgment structure available for this case.

Land and Environment Court


New South Wales

Medium Neutral Citation: Universal Property Group Pty Ltd v Blacktown City Council [2017] NSWLEC 1748
Hearing dates:Conciliation conference on 13, 22 December 2017
Date of orders: 28 December 2017
Decision date: 28 December 2017
Jurisdiction:Class 1
Before: Bish C
Decision:

See (4) below

Catchwords: DEVELOPMENT APPLICATION: conciliation conference; agreement between the parties; orders
Legislation Cited: Land and Environment Court Act 1979
Category:Principal judgment
Parties: Universal Property Group Pty Ltd (Applicant)
Blacktown City Council (Respondent)
Representation: Counsel:
Dr J Smith (Applicant)
Solicitors:
SWAAB Attorneys (Applicant)
Mr D Loether, Bartier Perry Lawyers (Respondent)
File Number(s):2017/230544
Publication restriction:No

Judgment

  1. COMMISSIONER: In this matter, at or after a conciliation conference, an agreement under s 34(3) of the Land and Environment Court Act 1979 (the Court Act) was reached between the parties as to the terms of a decision in the proceedings that was acceptable to the parties. As the presiding Commissioner, I was satisfied that the decision was one that the Court could have made in the proper exercise of its functions (this being the test applied by s 34(3) of the Court Act). As a consequence, s 34(3)(a) of the Act required me to “dispose of the proceedings in accordance with the decision”.

  2. The Court Act also required me to “set out in writing the terms of the decision” (s 34(3)(b)). The orders made to give effect to the agreement constitute that document.

  3. In making the orders to give effect to the agreement between the parties, I was not required to make, and have not made, any merit assessment of the issues that were originally in dispute between the parties.

  4. The final orders to give effect to the parties’ agreement under s34(3) of the Land and Environment Court Act 1979 are:

  1. The appeal is upheld.

  2. The Applicant is granted leave to amend Development Application No. DA-17-01094 and to rely upon the following amended plans, copies of which are behind Annexure “A”:

Drawing/Document Number

Drawing/Document Title

Prepared by

Date

DA 01 Rev 2

Site Analysis Plan

The Bathla Group

29 November 2017

DA 02 Rev 2

Subdivision Plan

The Bathla Group

29 November 2017

DA 03 Rev 3

Building Envelope Plan

The Bathla Group

13 December 2017

DA 04 Rev 3

Site plan

The Bathla Group

13 December 2017

DA 05 Rev 2

Ground and first floor plans – Stage 1

The Bathla Group

29 November 2017

DA 06 Rev 2

Elevations and sections – Stage 1

The Bathla Group

29 November 2017

DA 07 Rev 2

Shadow analysis – Stage 1

The Bathla Group

29 November 2017

DA 08 Rev 2

Ground and first floor plans – Stage 2

The Bathla Group

29 November 2017

DA 09 Rev 2

Elevations and sections – Stage 2

The Bathla Group

29 November 2017

DA 10 Rev 2

Shadow analysis – Stage 2

The Bathla Group

29 November 2017

Coversheet Rev G

Pulver Cooper & Blackley

14 December 2017

Sheet 2 Rev G

Index plan

Pulver Cooper & Blackley

14 December 2017

Sheet 3 Rev G

General arrangement sheet 1

Pulver Cooper & Blackley

14 December 2017

Sheet 4 Rev G

General arrangement sheet 2

Pulver Cooper & Blackley

14 December 2017

Sheet 5 Rev G

General arrangement sheet 3

Pulver Cooper & Blackley

14 December 2017

Sheet 6 Rev G

Typical cross sections

Pulver Cooper & Blackley

14 December 2017

Sheet 7 Rev G

Basin Long Sections

Pulver Cooper & Blackley

14 December 2017

Sheet 8 Rev G

Bulk earthworks plan

Pulver Cooper & Blackley

14 December 2017

Sheet 9 Rev G

Tree clearing plan

Pulver Cooper & Blackley

14 December 2017

Sheet 10 Rev G

Long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 11 Rev G

Long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 12 Rev G

Long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 13 Rev G

Long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 14 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 15 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 16 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 17 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 18 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 19 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 20 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 21 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 22 Rev G

Cross sections Glengarrie Road

Pulver Cooper & Blackley

14 December 2017

Sheet 23 Rev G

Cross sections Road 01

Pulver Cooper & Blackley

14 December 2017

Sheet 24 Rev G

Cross sections Road 01

Pulver Cooper & Blackley

14 December 2017

Sheet 25 Rev G

Cross sections Road 01

Pulver Cooper & Blackley

14 December 2017

Sheet 26 Rev G

Cross sections Road 01

Pulver Cooper & Blackley

14 December 2017

Sheet 27 Rev G

Cross sections Road 01

Pulver Cooper & Blackley

14 December 2017

Sheet 28 Rev G

Cross sections Road 01

Pulver Cooper & Blackley

14 December 2017

Sheet 29 Rev G

Cross sections Road 02

Pulver Cooper & Blackley

14 December 2017

Sheet 30 Rev G

Cross sections Road 03

Pulver Cooper & Blackley

14 December 2017

Sheet 31 Rev G

Cross sections Road 03

Pulver Cooper & Blackley

14 December 2017

Sheet 32 Rev G

Cross sections Road 04

Pulver Cooper & Blackley

14 December 2017

Sheet 33 Rev G

Cross sections Road 05

Pulver Cooper & Blackley

14 December 2017

Sheet 34 Rev G

Catchment plan

Pulver Cooper & Blackley

14 December 2017

Sheet 35 Rev G

Stormwater network

Pulver Cooper & Blackley

14 December 2017

Sheet 36 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 37 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 38 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 39 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 40 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 41 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 42 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 43 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 44 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 45 Rev G

Drainage long sections

Pulver Cooper & Blackley

14 December 2017

Sheet 46 Rev G

Drainage calculation tables 5 years ARI storm

Pulver Cooper & Blackley

14 December 2017

Sheet 47 Rev G

Drainage calculation tables 100 years ARI storm

Pulver Cooper & Blackley

14 December 2017

Documents

Updated Waste Management Plan prepared by Universal Property Group Pty Ltd dated December 2017

Engineering Design Report prepared by Pulver Cooper & Blackley, Revision B dated 1 December 2017.

  1. The Applicant is to pay the Respondent’s costs pursuant to section 97B of the Environmental Planning and Assessment Act 1979, as agreed or assessed.

  2. Development Application No. DA-17-01094 for the staged subdivision to create 106 residential lots, 2 residue lots (former Stage 1 being Lots 137 to 155 and superlot 156 and former Lots 1 to 30), 1 super lot for the construction of 30 multi-dwellings, 1 residue lot for future RE1 Public Recreation, construction and dedication of public roads, ancillary stormwater drainage works, tree removal and public domain landscaping works on Lots 4 in Deposited Plan 1202472 and Lot 45 in Deposited Plan 262886, be approved subject to the conditions which are behind Annexure “B”.

……………………….

Commissioner Bish

Annexure B (C)

Decision last updated: 28 December 2017