UGL ENGINEERING PTY LTD -v- COMPLETE POWER SOLUTIONS PTY LTD [2014] WASC 211
| SUPREME COURT OF WESTERN AUSTRALIA | Citation No: | [2014] WASC 211 | |
| 17/06/2014 | |||
| Case No: | COR:51/2014 | 28 MAY 2014 | |
| Coram: | MASTER SANDERSON | 28/05/14 | |
| 7 | Judgment Part: | 1 of 1 | |
| Result: | Statutory demand set aside | ||
| B | |||
| PDF Version |
| Parties: | UGL ENGINEERING PTY LTD (ACN 096 365 972) COMPLETE POWER SOLUTIONS PTY LTD (ACN 083 371 653) |
Catchwords: | Corporations law Application to set aside statutory demand Turns on own facts |
Legislation: | Nil |
Case References: | Anderson Formrite Pty Ltd v Rapid Metal Developments (Australia) Pty Ltd [2002] WASC 232 Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91 |
JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
- IN CHAMBERS
- Plaintiff
AND
COMPLETE POWER SOLUTIONS PTY LTD (ACN 083 371 653)
Defendant
Catchwords:
Corporations law - Application to set aside statutory demand - Turns on own facts
Legislation:
Nil
Result:
Statutory demand set aside
Category: B
Representation:
Counsel:
Plaintiff : Mr M N Solomon SC
Defendant : Mr G M G McIntyre SC & Mr K C B Staffa
Solicitors:
Plaintiff : Jackson McDonald
Defendant : Legal Success Pty Ltd
Case(s) referred to in judgment(s):
Anderson Formrite Pty Ltd v Rapid Metal Developments (Australia) Pty Ltd [2002] WASC 232
Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91
1 MASTER SANDERSON: This was the plaintiff's application to set aside a statutory demand. At the conclusion of the hearing I indicated to the parties I would set aside the statutory demand and publish reasons in due course. These are those reasons. A copy of the statutory demand appears as attachment RR-1 to the affidavit of Rajesh Rampersad sworn 14 March 2014. The total amount of the statutory demand is $2,784,746.16. That amount is made up of two components. First there are a series of eight invoices issued between 27 June 2013 and 25 September 2013 totalling $805,141.43. The remaining amount is made up of 14 amounts which the defendant says are payable pursuant to the contractual arrangement between the parties.
2 The relevant facts are these.
3 The plaintiff is a leading provider of engineering, construction and maintenance services. The plaintiff was the head contractor on the Fortescue Metals Group Mainline and Solomon Spur Permanent Communications Project. The defendant is a company that performed works relating to the power systems on the Fortescue Metals Group Mainline and Solomon Spur Permanent Communications Project.
4 Although both parties accept there was a contractual arrangement between them it is by no means clear what the scope of that contract might be. Between November 2011 and November 2012 the plaintiff provided the…
Keep reading for free
Create a free CaseChat account to read UGL Engineering Pty Ltd v Complete Power Solutions Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] WASC 211
- Decision Date
CaseChat Overview and Summary
The primary issue for the court was whether Complete Power had established a defence to the statutory demand sufficient to justify setting it aside. The court needed to assess whether Complete Power had a genuine dispute with UGL regarding the debt or whether there were other reasons, such as procedural irregularities, that warranted setting aside the demand. The court had to balance the statutory presumption of the debt's validity against Complete Power's assertions and evidence.
In its judgment, the court found that Complete Power had presented a credible case that it had a genuine dispute with UGL regarding the debt claimed. The court also noted that Complete Power had demonstrated that there were issues with the manner in which the statutory demand was issued, which contributed to the decision to set it aside. The court concluded that these factors were sufficient to justify setting aside the statutory demand under the relevant provisions of the Corporations Act.
The court ordered that the statutory demand issued by UGL be set aside, effectively relieving Complete Power from the immediate pressure to pay the debt. This decision allowed Complete Power to pursue its defences and counterclaims in the broader proceedings between the parties.
Orders
Orders of the court
Statutory demand set aside
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.